Page 1: TechSoup Global: SOUP Overview

Site Overhaul and Upgrade ProjectJuly 29, 2009

Page 2: TechSoup Global: SOUP Overview

The Site Overhaul and Upgrade Project (SOUP) is an 18 month effort

that will touch all the systems that power TechSoup.org.

Page 3: TechSoup Global: SOUP Overview

How will SOUP improve the experience of the users who come to

our site?

Page 4: TechSoup Global: SOUP Overview

The cleaner, more modern look allows users to focus on the reasons

they visit: Access to impactful technology donations in a learning

environment.

Page 5: TechSoup Global: SOUP Overview

How will SOUP improve our ability to deliver technology product donations

and related information?

Page 6: TechSoup Global: SOUP Overview

Up-to-date technology will provide us with an opportunity to streamline our processes, take advantage of

additional marketing and promotion features, and increase overall site

security and stability.

Page 7: TechSoup Global: SOUP Overview

What gets delivered?

Phase 3

Migrate Content to New platform

Phase 2

DonationProcessing

Technical Operational

Phase 1

SearchInitial securityimprovementsInfrastructure Home Page

Page 8: TechSoup Global: SOUP Overview

While there is much that we want to share, this deck

focuses on Phase 1.

Page 9: TechSoup Global: SOUP Overview

Currently in process, Phase 1 lays the groundwork for the

future.

Page 10: TechSoup Global: SOUP Overview

• New server hardware

• Web server software

• Database

• Content management system

• Modern application development language

• Improved and increased firewalls

Page 11: TechSoup Global: SOUP Overview

The public launch of Phase 1 is currently

scheduled for August 22.

Page 12: TechSoup Global: SOUP Overview

Today, the TechSoup home page looks like

this:

Page 13: TechSoup Global: SOUP Overview

Current Home Page

Page 14: TechSoup Global: SOUP Overview

On August 22, if everything goes right,

it will look like this:

Page 15: TechSoup Global: SOUP Overview
Page 16: TechSoup Global: SOUP Overview

Today, the TechSoup search results page

looks like this:

Page 17: TechSoup Global: SOUP Overview
Page 18: TechSoup Global: SOUP Overview

On August 22, if everything goes right,

it will look like this:

Page 19: TechSoup Global: SOUP Overview
Page 20: TechSoup Global: SOUP Overview

Today, article and product pages looks

like this:

Page 21: TechSoup Global: SOUP Overview
Page 22: TechSoup Global: SOUP Overview

And this:

Page 23: TechSoup Global: SOUP Overview
Page 24: TechSoup Global: SOUP Overview

On August 22, if everything goes right, they will still look like

this:

Page 25: TechSoup Global: SOUP Overview
Page 26: TechSoup Global: SOUP Overview

And this:

Page 27: TechSoup Global: SOUP Overview
Page 28: TechSoup Global: SOUP Overview

In Phase 1, key pages will change,

but the majority of the site will retain its

current look and feel.

Page 29: TechSoup Global: SOUP Overview

Why, you might ask, are we doing a site redesign this way?

Page 30: TechSoup Global: SOUP Overview

We are emphasizing an approach that

brings value to our users as soon as we

can deliver.

Page 31: TechSoup Global: SOUP Overview

This allows us to include the feedback

of our 400,000 monthly visitors

throughout the entire effort.

Page 32: TechSoup Global: SOUP Overview

How will user feedback drive us

forward?

Page 33: TechSoup Global: SOUP Overview

EditorialBoard

Users

TechSoup.orgProduct Manager

TechSoup.org site

Web analytics & other feedback

•UI/UX design •Development priorities

Thematic content

Actual behavior, Forums, Get Satisfaction widget, Call feedback (via CSR’s)

Page 34: TechSoup Global: SOUP Overview

So, when will the changes impact the

rest of the site?

Page 35: TechSoup Global: SOUP Overview

Jan 2009 April 2009 July 2009 Oct 2009 Jan 2010 April 2010 July 2010

Page 36: TechSoup Global: SOUP Overview

We would not have been able to undertake this

project without the generous support of Microsoft and the

William Randolph Hearst Foundation.

Page 37: TechSoup Global: SOUP Overview

Questions?Just ask us.

Page 38: TechSoup Global: SOUP Overview

And, like the bonus you get when you watch

some movie credits to the very end, here’s a

sneak peek at Phase 2:

Page 39: TechSoup Global: SOUP Overview

Phase 2 – Changes to donation processing have extensive technical & operational impact.

DonationProcessing

Payment processing

Order fulfillment

Catalog Mgmt

Registration/qualification Restrictions Mgmt Product maintenance

Inventory Management

Reporting

Page 40: TechSoup Global: SOUP Overview

The deliverables in Phase 2 will help us

gain more flexibility in the way we are able to implement and manage

donation programs.

Page 41: TechSoup Global: SOUP Overview

The main benefits of Phase 2 are targeted for

delivery in July 2010.