technical workshop implementing vspex in a private cloud
TRANSCRIPT
Technical Workshop
Implementing VSPEX in a private cloud
• Geoffrey McGowan
• Solutions Architect at Comsys
• Specialising in Virtualised high complexity
environments
Introduction
Introduction to the Environment
• Medical Imaging Customer based in Ireland
• Main Sites in Dublin
• Provides centralised image datastore for
multiple clinics and hospitals
• Requirement to meet stringent ISO
certifications for data practices and data
retention
Customers Requirements
• Move to a completely virtualised environment
• Virtualise mission critical General Electric Centricity RISi
application
• Increase redundancy and RTO for mission critical General
Electric Centricity RISi application
• Build a modular SAN environment which would form the basis
of a new virtualised environment to replace the current
physical environment.
• Reduced RTO for critical backup restores
Customers roadblocks
• Highly complex application General Electric Centricity RISi
with stringent set of requirements.
• First time that the General Electric Centricity RISi application
would be virtualised in Ireland
• Due to mission critical requirements, multiple vendor support
cases had been an issue in the past (Support Ping-Pong)
• Limited budget
• Small amount of dedicated specialised IT staff
• Short window for project completion
Comsys Proposed Solution
• 4 Phase approach
• Phase 1 - Design
• Phase 2 – Proof of Concept
• Phase 3 – Implementation
• Phase 4 – Go live
Phase I
Design
Phase I – Design steps
• Initial Workshop with customer to details required Service
levels, RPO/RTO, growth levels, support requirements and
datacentre constraints if any.
• Design call with GE RISi architects to ascertain software
requirements and possible Caveats with it running in a
virtualised environment.
• Create a design using the VSPEX approved framework.
• Create service offering with SPoC for all hardware
components, eliminating “support Ping Pong”
• Create and document final design, present to customer and
GE architects for final approval
Phase I – Design overview
• Compute – Customer has existing HP estate, so Comsys
recommended 2 x HP DL380 G7 servers in HA cluster.
• Storage– The customer would like future expansion, as well
as high performance disk. Comsys recommended a VNX 5100
SAN with redundant Brocade 300B switches.
• Software- Comsys recommended VMWare Essentials Plus to
virtualise this workload.
• Backup – Comsys recommended 2 x Data Domain DD160
Appliances for backup. These would be replicated between
sites for high availability.
Phase IIProof of Concept
Phase II Description – Proof of Concept
• Establish Test criteria and sign off requirements
• Create Project Plan
• Implement demo equipment
• Do Live P2V of running GE RISi instance to create test image
• Do online out of hours data copy utilising PowerPath
Migration Enabler.
• Engage GE to do testing of virtual instance.
• Finalise Proof of Concept
Phase IIISolution Implementation
Phase III Description – Implementation
• Final Site survey
• Rack and Stack of all equipment
• Installation and configuration, including VaaI and VaSA
enablers.
• Stress test of environment and final sign off by all parties
• Dial home and reporting setup.
• DataDomain backup and replication policies configured.
Phase IV
Phase IV Description – Go Live
• Full RISi application shutdown
• Final synchronisation of data
• Final testing of virtual machines
• Physical shutdown of RISi servers.
• Moving all virtual machines to production VMNetwork.
• Final testing of access to environment.
• First backup of environment and confirmation of replication.
Project Overview
• Move from physical to virtual environment, increasing uptime,
decreasing physical footprint and management over head
• Solution is a certified VSPEX solution, allowing for single point
of support through Comsys, who in turn utilise support
agreements EMC have in place with major vendors.
• Ability to quickly scale solution to encompass rest of the
environment while keeping complexity and support costs
down