1.0 INTRODUCTION
A site survey was carried out by Asia Debut Sdn Bhd technical team at Masjid BesarUMS with the assistance UMS Kota Kinabalu Management personnel. Prior to the
visit, drive test was done around the area and it was identified that the most suitable
place for Mobile phone and broadband operate to install a GSM, 3G, Wimax system in
order to solve outdoor and indoor coverage issue on surrounding area is at Masjid
Besar UMS, Kota Kinabalu,Sabah.
This document is produced as a proposal to UMS Management stating the component
that is going to be installed at this site. It also describes the technical issues involved.
2.0 SITE DETAILS
The site details information:
Site Name & Address Latitude Longitude AltitudeStructure
Height
Masjid Besar UMS,
Kota Kinabalu,Sabah
N 6.03693 E 116.12463 3m 25m Lamppole
The main equipment and components to be installed at the site:
i. RBS equipment (unmanned equipment and operating 24 hours per day)ii. RF antennas and feeder cablesiii. Antenna mountingiv. Microwave antenna
-
7/27/2019 Technical Proposal UMS
3/15
3.0 ANTENNA
3.1 MAXIS
Antenna RF ANTENNA MICROWAVE
No of Antenna 3 TBA
Antenna Diameter 2058 x 262 x 149mm TBA
Weight 33 kg TBA
Direction (TN) TBA TBA
TX Frequency TBA TBA
RX Frequency TBA TBA
Proposed height 24m TBA
Antenna Type SXA 120 106/1 TBA
TX Power TBA TBA
3.2 CELCOM
Antenna RF ANTENNA MICROWAVE
No of Antenna 3 TBA
Antenna Diameter 1420 x 337 x 80mm TBA
Weight 22 kg TBA
Direction (TN) TBA TBA
TX Frequency TBA TBA
RX Frequency TBA TBA
Proposed height 22m TBA
Antenna Type APX16DWV-16DWVS-C TBA
TX Power TBA TBA
-
7/27/2019 Technical Proposal UMS
4/15
3.3 DIGI
Antenna RF ANTENNA MICROWAVE
No of Antenna 3 TBA
Antenna Diameter 1319 x 323 x 71mm TBA
Weight 14.6kg TBA
Direction (TN) TBA TBA
TX Frequency TBA TBA
RX Frequency TBA TBA
Proposed height 20m TBA
Antenna Type KAT 742236 TBA
TX Power TBA TBA
4.0 CABLING
No of Radio Antenna feeder cables 6
Type of feeder cables 7/8" feeder cables
The feeder cables, antennas and equipments will be installed appointed by contractor
5.0 POWER SUPPLY
Asia Debut Sdn Bhd will deal with SESB for power supply or tapping from buildingpower source but in case of any changes in the modes of power supply Asia Debut SdnBhd will inform UMS Management.
-
7/27/2019 Technical Proposal UMS
5/15
6.0 EARTHING
6.1 Telcos will provide own Main Ground Bar at Microwave Antenna Level forall equipments on building and connected to own DC Earth Chamber atground via 50.0 mm Ground Cable.
6.2 Telcos will provide own DC Earth Chambers for all equipments at groundlevel.
6.3 Telcos will provide own AC Earth Chamber and connected to AC inlet.
6.4 All DC Earth Chambers are connected together via 25.0mm Copper Tape.
7.0 SITE ACCESSIBILITY
During the initial stage of site preparations and equipment installation, testing and
commissioning there will be frequent movement of staffs. After the site has been
commissioned the maintenance staff will visit the site periodically or if there is
shortcoming occurs.
The requirement for accessibility during the Operational Phase is 24 hours
accessibility as the site operates continuously. Permission and work permit will be
obtained prior to the above-mentioned work.
8.0 ADDITIONAL INFORMATION
ATTACHMENT :
v Site Location Mapv Proposed Structure Locationv Sample of Lamp pole
v Site Photov Site Drawingsv Detail Drawings
-
7/27/2019 Technical Proposal UMS
6/15
ATTACHMENT
-
7/27/2019 Technical Proposal UMS
7/15
SITE LOCATION MAP
Universiti MalaysiaSabah, KK, Sabah
Area: Behind mosque open areaSite Name: ST-6 Masjid Besar UMSLat: 6.03693Long: 116.12463
-
7/27/2019 Technical Proposal UMS
8/15
Location Plan For ST-6
-
7/27/2019 Technical Proposal UMS
9/15
PROPOSED STRUCTURE LOCATION
Proposed 25m Lamp Pole
-
7/27/2019 Technical Proposal UMS
10/15
SITE PHOTO
roposed submeterPDU 100A
-
7/27/2019 Technical Proposal UMS
11/15
Proposed Power Cable Route
roposed to hack hole
roposed tap power
from MCB
roposed toreplace
with new100A MCB
Existing electrical
cabinet
-
7/27/2019 Technical Proposal UMS
12/15
SITE SURVEY
DRAWINGS
(AS ATTACHMENT)
-
7/27/2019 Technical Proposal UMS
13/15
-
7/27/2019 Technical Proposal UMS
14/15
-
7/27/2019 Technical Proposal UMS
15/15