Page 1: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

TDC2-TCC2 consolidationstatus report to EATMEDMS 1410848October 7th, 2014

S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Page 2: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Outline

Objectives and schedule

Completed activities

Dose management & budget

Conclusions

IEFC

Page 3: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Objectives

• Reduce corrosion of vacuum equipment• Replace PVC-insulated cables• Re-route cable trays and cables• Eradicate water leaks • Upgrade ventilation

• Reduce machine downtime• Replace damaged equipment (TCSC, ion pumps, beam

instrumentation)• Replace obsolete low voltage equipment• Install radiation resistant equipment

• Apply ALARA principle• Reduce maintenance time• Increase Mean Time Between Failures

IEFC

Page 4: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

2014 Schedule

IEFC

L3 ALARA Committee agreement in October 2013. EDMS 1317027L3 ALARA Committee agreement on May 20th for EN/EL activities. EDMS1377072

Jan'14 Feb'14 March 14 April 14 May 14 June 14 July 14 Aug' 14 Sep' 14 Oct' 14 Nov' 14 Dec' 14 Jan' 15Date 6 13 20 27 3 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12week # 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3

Activities DurationCivil engineering 8w Vallier Dimens ione Mezz Peint

Cooling and ventilationChilled water 12w Remove pipes New pipes AHU coils

Demin. Water 5w valves

AHU control upgrade 12w

Handling 2w

Electricity NA NA physics LAB LV 10w Low voltage refurbishment start ClosureCabling 14+12w Cabling up

Magnets 12w

Vacuum 8w

Secondary beam lines 8 w Vacuum maintenance XTAX tables

Collimators and targets 2w

Beam instrumentationSurveyCleaning 4w

safety systems 6w

Page 5: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Outline

Objectives and schedule

Completed activities

Dose management & budget

Conclusions

IEFC

Page 6: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Removal of hot equipment

• TCSC removed first and brought to B.955• 3 splitter2 magnets and 2 MDLV removed and stored in TDC2• Various beam monitors, BLM and vacuum beam pipes

Page 7: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Cooling and ventilation upgrades

IEFC

New chilled water pipes (200 m DN 200)

New cooling coils in all AHU’s

AHU cabinet (40 years old) quite in good shape

Demineralized water circuit: 20 new valves

Challenge: asbestos removal

Page 8: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Civil Engineering

IEFC

• Repair of the TDC2 roof joints:• 3 joints have been fitted

with a metallic gutter driving water and bitumen to 3 retention boxes.

• Repair of the mezzanine floor:• Resin flooring

Page 9: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Civil Engineering: drain network maintenance

IEFC

• Contractor Vallier checked all the manholes and inspection chambers

• High pressure cleaning• Cleaning water collected and RP checked before

disposal• Sludge treated as radioactive waste

Page 10: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Civil Engineering: various repairs

IEFC

• New, extension of, repair to water collecting gutters

• Exchange of all remaining PVC pipes by PE pipes

• New drain connection

Page 11: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Heavy handling equipment

IEFC

• PR544 maintenance and test

• Power supply rail (feeding TT20 for transport vehicles) has been removed from TDC2

Page 12: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Magnet upgrade

IEFC

One manifold dismounted in order to estimate time needed for future exchange

Cooling flexible replacement completed in TDC2 (joints replaced)

About 120 seals exchanged

Page 13: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Magnet upgrade

Splitter rails and vacuum tank

Page 14: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Cabling activities

•Re-routing of 5 Cable trays (5x40m)

•Replacement of 70 DC and 42 control cables

•Installation of 10 new cables (new requests)

IEFC

Gangway

Average 100µSv/h. Max: 500µSv/h

Courtesy of I. Moya

Page 15: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

IEFC

Cabling activities

Control

Power General services

New situation

Page 16: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

•Replacement of emergency and conventional light fittings

•Total 66 emergency light fittings (Not compliant with current standards)

•Total 338 conventional light fittings

•Replacement of AUG buttons

•Replacement of power distribution outlets

•Installation of cable distribution for vacuum pump heaters

IEFC

Emergency radiation resistant LED light fitting

High Power LEDs hung from walkway

TCC2

TDC2

Conventional light fittings

Low voltage activities

Courtesy of J. Devine

Page 17: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Target refurbishment

• Preparation in EHN1 cleanroom:• Production of new monitors and

target boxes for target stations T2, T4, T6 & T10 + spare

• survey and vacuum & motorisation tests

IEFC

Courtesy of D.Grenier

Page 18: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

T2, T4 and T6 target refurbishment

• In TCC2:• Proximity cabling has been renovated• Old monitors and target boxes remotely removed• Dedicated shielded container for long term

storage in B. 954 and 955.• Re-installation of new monitors and target boxes

currently in progress

IEFC

Courtesy of D.Grenier

Page 19: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

• Upgrade of 12 XTAX tables:• Removal of spiral springs (screw protection)• Jacks greasing• Functional test of each tables• Cleaning and maintenance of the base plates• Realignment of XTAX4

XTAX table upgrade

Page 20: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

• Vacuum consolidation• New beam pipes (100m)• New ion pumps (10 units)• Heated collars

Vacuum consolidation

Page 21: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

• New TCSC collimator• New beam instrumentation

• A few new units• Maintenance of 40 beam instruments

Collimator & beam instrumentation

Page 22: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Outline

Objectives and schedule

Completed activities

Dose management & budget

Conclusions

IEFC

Page 23: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Dose management

IEFC

Operational dose Cumulated collective dose on 02.10 = 82539 uSv

Page 24: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

inférieur à 100 uSv

entre 100 et 250 uSv

entre 250 et 500 uSv

entre 500 et 1000 uSv

entre 1000 et 1500 uSv

entre 1500 et 2000 uSv

entre 2000 et 2500 uSv

0

50

100

150

200

250

204

4936 37

21

2 1

# personnes

# personnes

Maximum individual dose on 04.09 = 2033 uSv # of participants: 362

Dose management

Page 25: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Budget

IEFC

Page 26: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Outline

Objectives and schedule

Completed activities

Dose management & budget

Conclusions

IEFC

Page 27: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Conclusions

IEFC

The TDC2/TCC2 consolidation activities are successfully completed, within schedule, budget and with no major problem.

The corrective and preventive maintenance recently implemented will reduce corrosion of the vacuum equipment and reduce machine downtime in the future operation of the beam lines.

Individual dose management has been challenging for some groups.

Page 28: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

TEAM WORK

IEFC

Page 29: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Acknowledgements

• P. Catherine, M. Dumas, J. Bauche, P. Schwarz, M. Duraffourg, C. Vuitton, M. Hamani, R. Folch, D. Grenier, Z. Ajdid, M. Calviani J. Ferreira, T. Mongelluzzo, P. Chiggato, B. Rio, P. Debernard, R. Morton, A. Dodard, J-C Guillaume, D. Ricci, G. Gros, M. Da Costa, M. Dujardin, J-P. Billon-Grand, J. Pierlot, C. Crombez, S. Delarue, J. Devine, I. Moya, J-F Faure, A. Herve, Y. Pira, C. Theis, H. Vincke, L. Ulrici, Y. Algoet, M. Piccard, L. Gatignon, I. Efthymiopoulos, E. Harrouch, A. Bouvard, Y. Muttoni, C. Magnier, F. Galleazzi, A. Beynel, P. Bestmann, M. Troillet, S. Girod, A. Ebn Rhamoun, J. Etheridge, M. Bonnet, T. Wijnands, A. Pardons, J. Pedersen, Y. Seraphin, J-L. Grenard, C. Bertone, P. Brunero, P. Vallet, S. Deleval, A. Avian, B. Bannister, J. Lehtinen, F. Moro, R. Barrilliere, M. Baudin.

IEFC

Page 30: TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG