task 1 gc
TRANSCRIPT
ID Task Mode
Task Name Duration Start
2 Produce a proposal on digital video technology
7 days Mon 17/09/12
3 Write an illustrated report on Structure of Briefs
6 days Wed 26/09/12
6 Make a Client Brief for the Client and email it him arranging a time to negotiate
7 days Tue 30/10/12
7 Write a short report on where I am up to and the changes I have made
2 days Thu 08/11/12
17 Produce a SWOT analysis 5 days Mon 12/11/12
18 Produce a Gantt Chart 4 days Mon 19/11/1219 Produce a project
schedule2 days Fri 23/11/12
20 Write a risk assessment 5 days Tue 27/11/1221 Research an idea e.g.
location, age, gender etc.3 days Tue 04/12/12
22 Produce a questionaire 1 day Fri 07/12/12
S M T W T F S S M T W T F S S M T W T F S S M T10 Sep '12 17 Sep '12 24 Sep '12 01 Oct '12 08 Oct '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: Gantt_chartDate: Mon 14/01/13
ID Task Mode
Task Name Duration Start
23 Produce content specific pre‐production planning
5 days Mon 10/12/12
24 Produce a outline proposal with my team
5 days Mon 17/12/12
25 Pitch my products 7 days Mon 24/12/1226 Make any required
changes to fit to the Clients standards
2 days Wed 02/01/13
27 Write a short report on the changes I have made
3 days Fri 04/01/13
28 Complete Asset table 5 days Wed 09/01/1329 Sourcing any assets used
for the final product1 day Mon
18/02/13
30 Shoot my promotional video
14 days Mon 21/01/13
31 Produce a production diary
7 days Fri 08/02/13
32 Import and organise my video
1 day Tue 19/02/13
33 Edit my video 7 days Wed 20/02/1334 Write about
post‐production software techniques
7 days Fri 29/03/13
S M T W T F S S M T W T F S S M T W T F S S M T10 Sep '12 17 Sep '12 24 Sep '12 01 Oct '12 08 Oct '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 2
Project: Gantt_chartDate: Mon 14/01/13
ID Task Mode
Task Name Duration Start
35 Export my video to the web, DVD and a presentation
2 days Tue 09/04/13
36 Produce a report/evidence on the editing
7 days Thu 11/04/13
37 Devise my questionnaire 4 days Mon 22/04/13
38 End of Project Review Meeting with my client
1 day Fri 26/04/13
39 Produce an evaluation 7 days Mon 29/04/13
S M T W T F S S M T W T F S S M T W T F S S M T10 Sep '12 17 Sep '12 24 Sep '12 01 Oct '12 08 Oct '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 3
Project: Gantt_chartDate: Mon 14/01/13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W08 Oct '12 15 Oct '12 22 Oct '12 29 Oct '12 05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 4
Project: Gantt_chartDate: Mon 14/01/13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W08 Oct '12 15 Oct '12 22 Oct '12 29 Oct '12 05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 5
Project: Gantt_chartDate: Mon 14/01/13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W08 Oct '12 15 Oct '12 22 Oct '12 29 Oct '12 05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 6
Project: Gantt_chartDate: Mon 14/01/13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T19 Nov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 7
Project: Gantt_chartDate: Mon 14/01/13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T19 Nov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 8
Project: Gantt_chartDate: Mon 14/01/13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T19 Nov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 9
Project: Gantt_chartDate: Mon 14/01/13
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F31 Dec '12 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 10
Project: Gantt_chartDate: Mon 14/01/13
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F31 Dec '12 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 11
Project: Gantt_chartDate: Mon 14/01/13
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F31 Dec '12 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 12
Project: Gantt_chartDate: Mon 14/01/13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S11 Feb '13 18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 13
Project: Gantt_chartDate: Mon 14/01/13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S11 Feb '13 18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 14
Project: Gantt_chartDate: Mon 14/01/13
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S11 Feb '13 18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 15
Project: Gantt_chartDate: Mon 14/01/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S25 Mar '13 01 Apr '13 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 16
Project: Gantt_chartDate: Mon 14/01/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S25 Mar '13 01 Apr '13 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 17
Project: Gantt_chartDate: Mon 14/01/13
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S25 Mar '13 01 Apr '13 08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 18
Project: Gantt_chartDate: Mon 14/01/13