ta contract management 13-14 th july, 2011 aslı gülgör burcu arıkan kara
DESCRIPTION
Bölgesel Rekabet Edebilirlik Operasyonel Programı’nın Uygulanması için Kurumsal Kapasitenin Oluşturulmasına Yönelik Teknik Yardım Technical Assistance on Institutional Building for the Implementation of RCOP in Turkey. TA Contract Management 13-14 th July, 2011 Aslı Gülgör Burcu Arıkan Kara. - PowerPoint PPT PresentationTRANSCRIPT
1
Bölgesel Rekabet Edebilirlik Operasyonel Programı’nın Uygulanması için Kurumsal Kapasitenin Oluşturulmasına Yönelik Teknik Yardım
Technical Assistance on Institutional Building for the Implementation of RCOP in Turkey
This project is co-financed by the European Union and the Republic of Turkey
This project is co-financed by the European Union and the Republic of Turkey
2
This project is co-financed by the European Union and the Republic of Turkey
Tender decision
Selection of procurement method
Determination of the PQ criteria
Collection of proposals
Call for proposals Preparation of the tender document Evaluation of PQ
Evaluation of the proposals
Selection of the eligible proposal
Contract negotiations
Contract Award
Post-implementation liabilities
Expiration of the Contract
Dispute Management
Implementation of the contract
Preparation of the PQ documents
There are strict rules governing the way in which contracts are awarded.Ensuring the suitably qualified contractors are chosen without bias and that the best value for money is obtained, with the full transparency appropriate to the use of EU and public funds.
This project is co-financed by the European Union and the Republic of Turkey
THE LOWEST OFFER IS NOT ALWAYS THE BEST!THE FOLLOWING CRITERIA SHOULD BE TAKEN INTO ACCOUNT:
TO OFFER THE BEST PRICE AND QUALITY,TO BE A WELL KNOWN BRAND, TO BE ABLE TO SUPPLY THE CURRENT NEEDS, TO
PROVIDE SECURITY, AFTER-SALES SERVICE, SPARE PARTS, TO PROVIDE EQUAL CONDITIONS TO POSSIBLE SUPPLIERS FOR
PROCUREMENT AND TO AVOID CONFLICT OF INTERESTS.
WHO CAN PROVIDE SERVICE?ALL THE SERVICE PROVIDERS WHO WILL
PARTICIPATE IN THE TENDER SHOULD MEET THE REQUIREMENTS STATED IN THE
TENDER DOCUMENTATIONS AND COME FROM AN ELIGIBLE COUNTRY
THIS RULE IS EXACTLY APPLICABLE FOR THE EXPERTS WITHIN THE SERVICE
PROJECTS
WHERE MUST THE EQUIPMENT AND MATERIALS BE PROVIDED FROM?
ALL SUPPLIES AND MATERIALS PURCHASED UNDER A CONTRACT FINANCED UNDER A COMMUNITY
INSTRUMENT MUST ORIGINATE FROM THE COMMUNITY OR FROM AN ELIGIBLE
COUNTRY
THE TENDERERS MUST PROVIDE DOCUMENTARY PROOFS
General Procurement Rules
This project is co-financed by the European Union and the Republic of Turkey
General Rules Governing the Procurement of Services, Supplies Works and Grant Schemes and Small Grant
Contracts PRAGhttp://ec.europa.eu/europeaid/work/procedures/index_en.htm
Practical Guide
to
Contract Procedures for EC External
Actions
This project is co-financed by the European Union and the Republic of Turkey
Tender Procedures
Open Tender ProcedureRestricted Tender
ProcedureCompetitive Negotiated
ProcedureSimplified ProcedureSingle Tender
Practical Guide
to
Contract Procedures for EC External
Actions
This project is co-financed by the European Union and the Republic of Turkey
Competitive tendering process Transparent selection process Support for the project of the successful offer Contract setting the details of actions that
will be implemented These actions are,
Service Procurement of consultancy, research, know-how and training
Procurement of supplies Procurement of equipment and materials
Works Infrastructure and other engineering works
This project is co-financed by the European Union and the Republic of Turkey
Tresholds PRAG
SERVICES
≥ € 200,000International
restricted tender procedure
1. < € 200,000 but > € 10,000 Framework contracts2.Competitive negotiated procedure
≤ € 10,000
Single tender
SUPPLIES
≥ € 150,000 International open tender procedure
< € 150,000 but ≥ € 60,000
Local open tender procedure
< € 60,000 but > € 10,000
Competitive negotiated procedure
WORKS
1. ≥ € 5,000,000 International open
tender procedure
2. International restricted
tender procedure
< € 5,000,000 but ≥
€ 300,000 Local open
tender procedure
< € 300,000 but> € 10,000
Competitive negotiated procedure
8
This project is co-financed by the European Union and the Republic of Turkey
19-21/06/07
Contract Managem
ent Training
SERVICE CONTRACT
THE CONTRACTS OF 200,000 € OR MORE
1 MUST BE CARRIED OUT ACCORDING TO INTERNATIONAL RESTRICTED TENDER PROCEDURES
2 THE TENDERING TERMS AND CONDITIONS MUST BE PUBLISHED ON THE RADIO, TELEVISION, THE WEB SITE OF THE CONTRATCING AUTHORITY, INTERNATIONAL AND LOCAL NEWSPAPERS
3 A SHORTLIST MUST BE ESTABISHED
4 THE NUMBER OF SHORTLISTED TENDERERS (USUALLY BETWEEN 4 TO 8) MUST BE PUBLISHED
5 THE EVALUATION OF PROPOSALS MUST BE UNDERTAKEN OBJECTIVELY AND INTEGRITY OF THE COMPETITIVE PROCESS MUST BE PRESERVED.
6 ONLY THE CANDIDATES MEETING THE TENDERING CRITERIA STATED ON THE ANNOUNCEMENT AND THE ONES WHO ARE INVITED CAN SENT THEIR OFFERS
This project is co-financed by the European Union and the Republic of Turkey
19-21/06/07
Contract Managem
ent Training
NEGOTIATION PROCEDUREEXCEPTIONAL CASES
ONLY FOR THOSE SPECIFIED CONDITIONS BELOW ONLY ONE OFFER CAN BE ACCEPTED TO NEGOTIATE
•WHERE, FOR REASONS OF EXTREME URGENCY BROUGHT ABOUT BY EVENTS WHICH THE CONTRACTING AUTHORITIES COULD NOT HAVE FORESEEN
•OPERATIONS CARRIED OUT IN CRISIS SITUATIONS
•WHERE CONTRACTS EXTEND ACTIVITIES ALREADY UNDER WAY;
•WHERE THE TENDER PROCEDURE HAS BEEN UNSUCCESSFUL, THAT IS WHERE NO QUALITATIVELY AND/OR FINANCIALLY WORTHWHILE TENDER HAS BEEN RECEIVED.
•WHERE, FOR TECHNICAL REASONS, OR FOR REASONS CONNECTED WITH THE PROTECTION OF EXCLUSIVE RIGHTS, THE CONTRACT CAN BE AWARDED ONLY TO A PARTICULAR SERVICE PROVIDER.
•WHERE ONE ATTEMPT FOR THE USE OF THE COMPETITIVE NEGOTIATED PROCEDURE/SIMPLIFIED PROCEDURE FOLLOWING THE UNSUCCESSFUL USE OF A FRAMEWORK CONTRACT HAS FAILED.
•FOR CONTRACTS DECLARED TO BE SECRET, OR FOR CONTRACTS WHOSE PERFORMANCE MUST BE ACCOMPANIED BY SPECIAL SECURITY MEASURES OR WHEN THE PROTECTION OF THE ESSENTIAL INTERESTS OF THE EUROPEAN UNION OR THE BENEFICIARY COUNTRY SO REQUIRES.
This project is co-financed by the European Union and the Republic of Turkey
Contract Execution
11
This project is co-financed by the European Union and the Republic of Turkey
Service Contract Outline
Contract Agreement and Special Conditions with annexes:
General Conditions for service contracts Terms of Reference Organisation and Methodology (To be submitted by
the tenderer according to the template provided) Key experts (including templates for the summary
list of key experts and their CVs) Budget [For fee-based contracts: breakdown] Forms and other relevant documents
This project is co-financed by the European Union and the Republic of Turkey
Contract Management Highlights
This project is co-financed by the European Union and the Republic of Turkey
Basic Principals
Identification and management of risks Effects of risk management to price Cost variation when risk is transferred to the contractorMethods of avoiding claims
Identifying the hot spotsActing against problems at the beginning of the project Problem solving techniques
Friction caused by claimsResolution of claims with cooperation
This project is co-financed by the European Union and the Republic of Turkey
Basic Principals
Amicable solutionIdentification of claims in advanceExaggerated claims ??Financing Plan Budget Monitoring
This project is co-financed by the European Union and the Republic of Turkey
Name of the Training 16
Contract – Highlights
Time ExtensionAdditional PaymentGeneral Conditions Special Conditions
This project is co-financed by the European Union and the Republic of Turkey
Contract – Highlights
Delays Changed Circumstances Abandonment, Suspension or TerminationPayment Outputs Conflict of Interest / Corruption and Fraud
Universal Law Systems
German Law (Favouring the Employer and the Supplier)French Law (Favouring the Employee and the Buyer)British Law (in balance)
Reasons for Claims
MisstatementWithout anybody's faultUncertainty of documentsWilful misinterpretation
Legal negligenceDirect breach of contract
Ambiguous Contracts
General AmbiguityHierarchy of the contract documentsFuzzy expressions"Eligible" Contractor and Consultant
Claims for Price Adjustments
Claims due to delaysVerification of the critical pathQuantitative analysisAgreement on the secondary costs
Claims due to time extensionOverheads
Claims concerning break-down of the activities
This project is co-financed by the European Union and the Republic of Turkey
Changes
Cardinal ChangeChanges which highly affect the content of the work
Constructive changeThe instructions which are not defined clearly within
the contract Formal change
Changes which do not affect the content of the contract significantly
Cost Increase
Client's RequestsRevisionsIncrease of decrease in the content of the ServicesPredefined variations and flexibilitiesEffects of increasing, decreasing of the content of the Services and break down
DelaysAn extraordinary event or circumstance
beyond control of the parties preventing both or one of the parties from fulfilling their liabilities is considered as a Force Majeure (Events from God)
Delays caused by the Client shall be accepted not in the responsibility of the other party
The circumstances and events which can be controlled by the Contractor shall not be considered as eligible reasons for delay
There is no time extension for ineligible delays and legal penalties shall be applied
This project is co-financed by the European Union and the Republic of Turkey
Questions and Discussions.