    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    SYLLABUS

    Sl.No. Subject / Module - First Semester

    No. ofWeeks

    1 Power Plant Introduction & Industrial Safety 1

    2 Power Plant Familiarisation 6

    3 Power Plant Briefing & Scheme Tracing 2

    4 Power Plant Operation 2

    5 Rotation On-job(Operation) 5

    6

    Erection, Commissioning & Construction

    Management 2

    7Power Plant Performance & EfficiencyCalculation 1

    8Power Plant Chemistry , Metallurgy ,NDT &Welding 2

    9 Gas turbine & Combined Cycle Power Plant 1

    10Advanced Steam Generation Technology-Supercritical and FBC 1

    11

    Business Communication & Personality

    Development 1First Semester Examination 1

    Subject / Module - Second Semester

    12 Power Plant Protection 1

    13 Energy Audit 1/2

    14 Maintanence Planning & Cost Control 1

    15 Nuclear Power Plant Familiarisation 1

    16 Renewable and Hydro Power Plants 1

    17 Maintanence Practice & Inspection 4

    18 Design Analysis 119 Load Despatch 1

    20 Power Reforms and regulations 1

    21 Control & Instrumentation 2

    22 IT Application in Power Sector & GIS 2

    23 Environment Management 1

    24 Rotational On Job(Maint.) 4

    25 Training & visit to Mfrs. Works 2

    26 Simulator 2

    Project Presentation 1/2Margin For Holidays 1

    Second Semester Examination 1

    Total 52 1

  • 8/6/2019 Syallabus of PGDC

    2/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Scheme of Examination

    Distinction -75% and above

    First Division -60% & Above

    Second Division -50% to less than 60 %Pass Marks -Minimum 45% in internal & external examination separately and 50 % in overall Semester

    A student failing in a particular semester in three or more subjects will have to repeat the Semester exam with

    the next batch. A student failing in a particular subject will have to appear in the subject exam.

    PaperNo. Title of the Paper - First Semester

    No. ofWeeks

    InternalTestMaxmarks

    ExternalexamMax

    Marks

    TotalMaxmarks

    Remarks

    1

    Power Plant Familiarisation-I(Power Plant Introduction & Safety, Generators &transformers) 3 50 100 150

    2Power Plant Familiarisation-II(Boiler, Turbine & BOP) 4 50 100 150

    3Power Plant Operation, Power Plant Performance &Efficiency Calculation 3 50 100 150

    4Erection, Commissioning & Construction Management,Gas turbine & Combined Cycle Power Plant 3 50 100 150

    5

    Power Plant Chemistry, Metallurgy, NDT & Welding,Advanced Steam Generation Technology- Supercriticaland FBC 3 50 100 150

    6 Rotation On-job(Operation) (Based on Viva Voce) 5 50 100 150

    7Power Plant Briefing & Scheme Tracing(Based on Viva Voce) 2 50 50 100

    8Business Communication & Personality Development(Based on Viva Voce) 1 50 50

    Total 1050

    First Semester Examination 1

    Title of the Paper - Second Semester

    1Power Plant Protection, Control & Instrumentation, EnergyAudit 3.5 50 100 150

    2

    Maintenance Planning & Cost Control, EnvironmentManagement, Nuclear Power Plant Familiarization,Renewable & Hydro Power Plants 4 50 100 150

    3 Maintenance Practice & Inspection, Design Analysis 5 50100 150

    4Load Dispatch, IT Application in Power Sector & GIS,Power Reforms & Regulation 4 50 100 150

    5. Rotation On-job(Maintenance) (Based on Viva Voce) 4 50 100 150

    6Training & visit to Mfrs. Works(Based on Viva Voce) 2 50 50

    7 Simulator 2 100100

    8Project(Based on Viva Voce) 0.5 50 100 150

    Margin for holidays 1

    Second Semester Examination 1

    Total 521050

    2

  • 8/6/2019 Syallabus of PGDC

    3/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    RULES AND REGULATIONA. ADMISSION AND ELIGIBILITY

    1. The duration of the course leading to the Post Graduate Diploma In ThermalPower Plant Engineering shall be one academic year(52 weeks) divided intotwo semesters.

    A candidate shall have to pass all the two semester examinations within amaximum period of three years of his/her admission to the first semester ofPost Graduate Diploma In Thermal Power Plant Engineering programmefailing which he/she will be deemed to be unfit for the programme. However,a candidate, who having passed the first semester examination discontinueshis studies, for legitimate and justified reasons may be permitted to joinsecond semester within one year of his passing the first semesterexamination.

    2. The minimum qualifications for admissions to the first semester of PostGraduate Diploma In Thermal Power Plant Engineering programme shall be aBachelor degree in Engineering or AMIE or equivalent degree in Mechanical,Electrical, Electronics./Control & Instrumentation/ Power Engineering. Thoseappearing in their final year examination may also apply. However, they mustsubmit their result at the time of counseling. The Admission to this P.G.Diploma will be done on the basis of Merit based on a Common Entrance Test(CET) followed by counseling. CET will be conducted on rotation basis by theInstitutes in the sequence New Delhi, Nagpur, Neyveli and Durgapurrespectively.

    3.(a) The first semester examination shall be open to a regular student who

    I) has been on the rolls of the Institute during the first semester;II) has at least 75% attendance in the class during the semester;III) has obtained pass marks in the internal assessment/

    workshop/practical exam. andIV) bears a good moral character

    (b) The second semester examination shall be open to a regular student who:

    i) has been on the rolls of the Institute for the concerned semesterii) has at least 75% attendance in the class during the semester;iii) has passed the first semester examination andiv) bears a good moral character.

    B. EXAMINATION AND FEES

    4. Every candidate shall be examined in the subject(s) as laid down in theScheme of Examinations/Syllabus prescribed . Course/Tuition fee should bedivided equally into two parts. Semester 1 fee should be deposited at the timeof counseling. Semester 2 fee should be deposited by 20th February of eachyear failing which a late fee of Rs.100/- per day may be charged. Each PGDCstudent will be charged a fee of Rs 200/- per subject as examination fee which

    3

  • 8/6/2019 Syallabus of PGDC

    4/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    may be deposited one month before start of the semester examination ie. Rs.1600/- for first semester and Rs 1600/- for second semester.

    5. The external examiner(s) will set the question papers as per the criteria laiddown in the Scheme of Examination for the program. Evaluation of semester

    exam answer sheets will not be done in the same Institute. All the writtensemester exams will be of three hour duration.

    6. The medium of instruction and examination shall be English.

    7. Mobile phones, any extra piece of paper, notebook are banned in the examhall. A student indulging in exam malpractices may be expelled by theinvigilator/Chief Supdt. for one year from the exam and he will be able to takethe semester exams only after one year.

    8. The amount of examination fee to be paid by a candidate for each semester

    shall be as per the decision of NPTI from time to time.

    9. The Examination for the first semesters shall ordinarily be held in the month ofJanuary and for the second semester in the month of July or on such dates asmay be fixed by the Director General, NPTI.

    Supplementary examinations will be held for re-appear/failed candidatesas under:-

    Semester When held

    (a) First Semester Along with the Second Semester (b) Second Semester Along with the subsequent first Semester_________________________________________________________

    10. The Course Coordinator of the concerned Institute shall forward the internal testmarks to the Principal Director/ Director at least one week before thecommencement of each semester examination alongwith list of the eligiblestudents who have satisfied the requirements of rules for appearing in theExamination.

    11. (i) As soon as possible, after the competition of the examination the Principal

    Director/ Director shall publish a list of candidates who have passed theSemester Examination.

    (ii) Each successful candidate shall receive a copy of the detailed marks cardon having passed the Semester Examination.

    12. The list of successful candidates after the Second semester examination shall bearranged as under in two divisions on the basis of the aggregate marksobtained in the first and second semester examinations taken together andthe division obtained by the candidate will be stated in his certificate.

    a) Those who obtain 50% marks but less than 60% marksSECOND DIVISION;

    b) Those who obtain 60% or more marks -

    4

  • 8/6/2019 Syallabus of PGDC

    5/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    FIRST DIVISION;

    c) Those who pass all the two semester examinations at the first attemptobtaining 75% or more marks in the aggregate shall be declared tohave passed with - DISTINCTION

    C. EVALUATION

    13. (i) The Principal Director/ Course Coordinator of the Institute will preservethe records on the basis of which the, Internal Assessment awardshave been prepared upto one month from the date of declaration of thesemester examination results. This record will be disposed off after onemonth. The first Semester results must be declared before 20 th ofFebruary of each year.

    14. (i) The internal assessment/practical/workshop/training report/project

    report award of a candidate who fails in any semester/paper(s) shall becarried forward to the next examination.

    (ii) Candidate(s) who has not obtained pass marks in the InternalAssessment in any paper(s) will not be allowed to take examination inthe said paper(s) in the relevant semester. He/she will, however, beprovided opportunity to appear before the Committee of Examiners, tobe constituted by the Principal Director/ Director of the concernedInstitute to re-assess performance of the candidate and the internalassessment given by the Committee shall be final.

    (iii) A candidate who fails to obtain pass marks in training report/projectreport shall be offered opportunity to undergo training again andconduct another project as the case may be and the same shall beassessed by a board of examinations appointed by the PrincipalDirector.

    (iv) A candidate who fails to obtain pass marks in ROJT/practical/viva-voceshall have to re-appear before the board of examiners constituted bythe PD/Director.

    15. (i) The candidate shall be required to submit three copies of his ProjectReport. The last date for receipt of Project Report in the office of theInstitute shall be one week before the commencement of the Secondsemester Examination.

    In exceptional cases, the Director General may, on therecommendation of the Principal/Director of Institute, extend the lastdate of receipt of the project Report, till the commencement of theSecond semester examination, with late fee.

    (ii) The Project Report shall be evaluated as per the guidelines specified in

    the Scheme of Examination, jointly by the external and the internalexaminers. The appointment of the external examiner shall be made bythe Director General on the recommendation of the Principal Director ofthe respective institute.

    5

  • 8/6/2019 Syallabus of PGDC

    6/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    (iii) The marks obtained by the candidate for the project report shall betaken into account when he appears in any future examination underreappear clause.

    16. (a) The comprehensive viva-voce/workshop shall be conducted by a Boardof Examiners to be appointed by the Director General on therecommendation of the Principal Director/Director of the respectiveinstitute consisting of the following members:-

    i) One Internal Faculty nominated by the Director of the concernedInstitute;

    ii) One or Two External Examiners from the Industry/Academicfield

    (b) The marks obtained by the candidate for the viva-voce/workshop shall

    be taken into account when he appears in any future examinationunder re-appear clause.

    17. The Project Report and Training Report, wherever specified will be submittedin the typed form as per the following requirements:

    (i) The typing should be done on both sides of the paper (instead of singleside printing)

    (ii) The font size should be 12 with Times Roman Format.(iii) The Project Report/Training Report may be typed in 1.5 (one and a

    half) space. But the References/Bibliography should be typed insingle space.

    (iv) The paper should be A-4 size.(v) Two copies meant for the purpose of evaluation may be bound in

    paper-back form and one copy should be in hard binding.(vi) Students will select topic of the project by 30th October of each year.

    Course Coordinator will submit the consolidated list of project withname of students to the Principal Director/Director on first working dayof November.

    D PROMOTION AND REAPPEAR

    18. The minimum percentage of marks to pass the examination in each semestershall be :-

    a) 45% in each written paper and internal assessment separately;b) 45% in Training Report/Project Report and Viva-Voce separately.c) 50% in the total of each semester examination.d) A candidate who has secured minimum marks to pass in each paper but

    has not secured the minimum marks required to pass in aggregate for thesemester concerned may take re-examination (in not more than twopapers) to obtain the aggregate percentage required to pass the

    semester.

    19. A candidate whose result is declared late without any fault on his/her part,may attend classes for the next higher semester provisionally at his own risk

    6

  • 8/6/2019 Syallabus of PGDC

    7/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    and responsibility, subject to his/her passing the concerned semesterexamination. In case a candidate fails to pass the concerned semesterexamination, his/her attendance/internal assessment in the next highersemester in which he was allowed to attend classes provisionally will standcancelled.

    20. A candidate shall be promoted to the next higher semester if he/she passes atleast 50% of the theoretical papers (i.e. excluding subjects in which marking isdone on the basis of Viva Voce) having prescribed in the semester, failingwhich he/she shall be declared as FAIL in that semester and he/she shall berequired to appear in the failed semester in all the papers currently in force as,a private candidate (as ex-student).

    EXPLANATION : 50% of five papers will be taken as three and that ofseven papers as four and that of nine papers as five under this Clause.

    E. OTHER PROVISIONS

    21. Question paper for the External exams will be common for all the institute andwill be set by a faculty who will be paid honorarium of Rs. 2500/- per subjectplus postage charges on actual basis. Question paper setting will beresponsibility of one of the institute on rotation basis ie. New Delhi, Nagpur,Neyveli and Durgapur respectively. Question papers will be broadly subjectivein nature.

    22. Answer sheets of the Semester exams will not be evaluated in the parentinstitute and sent for outside evaluation. The evaluator will be paid anhonorarium @ Rs. 40 per copy plus postage on actual basis. For evaluatingthe project report or conducting viva voce the external and the internalexaminer will be paid honorarium of Rs. 40/- and Rs. 20/- respectively perstudent plus TA. Similarly faculty evaluating for simulator will be paidhonorarium @ Rs. 20/- per student.

    23. The invigilators in the semester exams will be paid a honorarium of Rs. 200/-per sitting of 3 hour. For 30 students one invigilator, for 30-60 students twoinvigilator and for more than 60 students 3 invigilators may be employed.Principal Director/ Director in-charge will act as Chief Superintendant of the

    examination and will be responsible for smooth conduct of examination andshall be paid a lump sum honorarium of Rs 2000/- for the semester finalexams. A centre clerk and two peons (for sealing, water serving etc.) may beappointed by the Chief Supdt. for conduct of semester examination and maybe paid an honorarium of Rs.120/- and Rs.50/- per sitting respectively. Thecentre clerk will assist the Chief Supdt. in making seat plan, maintenance offiles (attendance, billing, dispatch of answer sheets etc.) for the exams.

    24. Tabulation of the internal and external marks will be done by a faculty andshall be paid honorarium @ Rs. 20 per student. He will be responsible forcollecting all the marks and tabulation and publication of the final result. The

    Principal Director /Director Incharge will nominate the tabulator of theirrespective institute. The tabulation records of the passed out students will bekept with Training Officer/Course Coordinator of the respective institutes.

    7

  • 8/6/2019 Syallabus of PGDC

    8/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    25. A sumptuary allowance of Rs.1000/- per month may be granted to the coursecoordinator of PGDC in TPPE at the respective institutes and this expenditurewill be met from the examination fee collection. The Course Coordinator willmaintain the records of registration, feedback (to be taken once in eachsemester) and will prepare the day wise module of the course and intimate

    the faculty for their lectures.

    26. Instruction For The Question Paper Setter: The question setter will set twosets of question paper for each subject and mark on the envelop Set A andSet B and seal them separately. The sealed Envelops For Set A and Set Bshould be sealed in a bigger envelop and sent to the respective principaldirector. The Paper setter should maintain the confidentiality of the questionpaper and all rough worksheets should be destroyed. The question should bebroadly subjective in nature and should cover all parts of the syllabus. Themaximum marks for each subject is 100 and pass marks is 45. The timeallowed for each paper will be 3 hours. The subject syllabus can be identified

    by the following help:

    Power Plant Familiarisation I: This includes the General Introduction module,Industrial Safety module and 5th and 6th week module of Power PlantFamiliarisation.

    Power Plant Familiarisation II: This includes 1st to 4th week module of PowerPlant Familiarisation

    All other subjects have nomenclature pertaining to the modules which havebeen included.

    27. The corporate quality committee will meet every year in the last week of Julyto review the status of the course.

    28.Any other provision not contained in the above shall be governed by the rulesand regulations framed by NPTI from time to time.

    8

  • 8/6/2019 Syallabus of PGDC

    9/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    FIRST

    SEMESTER

    PGDC IN TPPE

    9

  • 8/6/2019 Syallabus of PGDC

    10/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : General Introduction(Duration): week

    FORENOON AFTERNOON

    DAY-1 Registration and Inauguration , CourseDescription, Institute facilities

    Growth of power Industry afterIndependence

    DAY-2 Site Selection (Site availability, Rawmaterial, Fuel, load evacuation, Water,

    Transport, Pit Head Station ,Air Pollution,Topography, Skilled manpower ).

    Coal to Electricity (Coal /Air / Flue/ Gas/ Water /Steam Path ,Brief description of main equipments

    involved in a Thermal Power plant Station )

    DAY-3 General layout of a Thermal PowerStation (Block Diagram of mainequipments, Generator and theirAuxiliaries)

    Visit to Thermal Power Station

    10

  • 8/6/2019 Syallabus of PGDC

    11/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Industrial Safety(Duration): week

    FORENOON AFTERNOON

    DAY-1 Accidents (Causes & Factors, Cost ofAccidents , Accidents Prevention,Investigation of Accidents, Reporting andRecording Systems of Accidents)

    First Aid (Basics of First Aid, How injuries arecaused in lifting, falls etc.)

    DAY-2 Fire fighting (Fundamentals of Fire, FireFighting Equipments and systems, FireExtinguishing Methods, Demonstration ofvarious fire.)

    Industrial Safety & hazards(Industrial Hazards,Protective Clothing and Equipment, Safe workpractices in power Plants, permit to work system,safety in moving and storage of materials,Housekeeping Safety rules)

    11

  • 8/6/2019 Syallabus of PGDC

    12/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Familiarization

    (Duration): 6 week

    FORENOON AFTERNOON

    DAY-1 Steam Cycle Theory (Carnot cycle ,Rankine cycle, with reference to aspecific unit 500/210 MW , steamproperties)

    Coal (Types of coal and their characteristics, Theirsuitability for different kinds of Boiler, Alterations infiring methods due to change of coal composition)

    DAY-2 Coal Handling system (Location andlayout, Main Equipments and theirfunctions , Coal transportation ,preparation, storage and reclamation ,MGR system, safety aspects , Fireprevention and fire fighting in coalhanding plant )

    Combustion Theory(Definition , Combustionrequirements, factor influencing combustion,combustion of fuels , gross and net calorific value)

    DAY-3 Fuel Oil Systems (Location and siteselection, Type of fuel used , Mainequipment and their functionsTransportation, handling , storage Fueloil preparation before firing)

    Plant visit (visit to coal handling plant, visit to fueloil station)

    DAY-4 Description of Main Boiler(Classification and Types, Arrangementsof main boiler , Fundamentals of Boilerdesign , Location of various pressureparts)

    Boiler Circulation Theory (water walls boilingphenomena , Nucleate / Film boiling , Natural /Controlled / Forced circulation )

    DAY-5 Constructional detail of Super heaters,Re heaters, Economizers, De superheaters.

    Steam Separation theory ( Boiler Drum & itsinternals)

    12

  • 8/6/2019 Syallabus of PGDC

    13/61

  • 8/6/2019 Syallabus of PGDC

    14/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Familiarization(Duration): 6 week

    3RDWEEK

    FORENOON AFTERNOON

    DAY-1 Furnace, Safeguard, supervisorySystem

    (Description of field equipments (no C&I )

    Audio Visual Session (FSSS)

    DAY-2 Water Supply System (soft water,clarified water, cooling water, D. Mwater)

    Steam Turbines (Classification of TurbinesMetallurgical considerations, WorkingPrinciples

    DAY-3 Description of main components i.e.

    Turbine casing, rotor steam admissionvalves, couplings , bearings etc.

    Turbine lubrication Oil System Construction and

    working Principles of main Oil pumps , Oil coolers)

    DAY-4 Steam condensation andCondensers(film wise/drop wisecondensation, Direct/ indirectcondensation and vacuum creation)

    Audio-visual (vacuum System, Turbinelubrication Systems

    DAY-5 Power Station Pumps (Classification ofpumps, Centrifugal pumps, positivedisplacement pumps)

    Boiler Feed Pump (Function of BFPConstructional details)

    14

  • 8/6/2019 Syallabus of PGDC

    15/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Familiarization(Duration): 6 Weeks

    4TH WEEK

    FORENOON AFTERNOON

    DAY - 1 . Circulating Water System (Open/

    Closed system, CW Pumps, Cooling

    Towers, CT Pumps, CT Fans)

    Plan Visit (CW System including

    Cooling Towers, CT Pumps, CT

    Fans, Condenser Vacuum Ejectors,

    BFP)

    DAY - 2 Regenerative Feed Heating System

    (Working Principle and constructionaldetails of L.P. Heaters, Deaerators,

    H.P. Heaters GSC, Ejector)

    Visit to (Regenerating Feed

    Heating System, TurbineLubricating Oil system, Water

    Treatment Plant)

    DAY - 3 Turbine Governing System ( Types of

    Governing systems. Various

    components, systems and their

    functions, Oil circuit for Governing

    System. Overall working of governing

    system with reference to load throw

    off. Load raising).

    Turbine Governing System

    (Contd.)

    DAY - 4 Audio/Visual Session on Governing

    System.

    HP/LP Bypass system and PRDS

    and its utility, Various interlocks

    and protections

    DAY 5 Audio/Visual Session on HP/LP By

    pass System.

    Plant visit (Governing System andHP/LP By pass System).

    15

  • 8/6/2019 Syallabus of PGDC

    16/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Familiarization

    (Duration) : 6 Weeks

    5TH WEEKFORENOON AFTERNOON

    DAY - 1 Generator Constructional Details

    (Basic principle of electricity,

    generation

    Development of generator design,

    Construction details of rotor, stator etc.

    Tutorial/General discussion.

    DAY - 2 Hydrogen Cooling System and Stator

    Water Cooling System (Different types

    of cooling arrangements for rotor andstator, Selection and properties of

    coolant, Air cooling, Hydrogen

    cooling, Stator water cooling, H2

    Charging/ PurgingCycle).

    Audio visual on Hydrogen cooling

    system

    DAY - 3 Hydrogen Seal Oil System (Details of

    the system, Function and purpose of

    differential pressure regulator and

    pressure oil regulators, Types of

    Hydrogen seals and their constructiondetails).

    Generator Excitation System and

    AVR (Principles, Simple arrangem-

    nts of excitor and its field winding,

    Classification of excitation system -

    High Frequency / static excitationsystem - their merits and demerits,

    Automatic Voltage Regulator).

    DAY - 4 Audio/Visual Session on Excitation

    System.

    Plant Visit (Generator and

    Auxiliaries, Hydrogen cooling &

    Stator Water Cooling System,

    Hydrogen Seal oil system).

    DAY 5 Transformers (Working Principles,

    Various types of transformers used in apower station, Constructional features

    of main transformer and accessories,

    Bucholtz relay and main protections,

    Types of cooling, Mulsifire and other

    fire protection systems.

    Audio/Visual/Discussion session.

    16

  • 8/6/2019 Syallabus of PGDC

    17/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Familiarization

    (Duration) : 6 Weeks

    6TH WEEK

    FORENOON AFTERNOON

    DAY - 1 Motors(Fundamentals, Constructional

    details of HT/LT Motors, Various

    motors used .in Power Stations.

    Plant visit (Transformers

    Excitation System)

    DAY - 2 HT-LT Supply system/DC Supply

    System (A typical layout of 6.6 KV,

    3.3 KV and 415 V supply system in a

    TPS, DC Supply system in a TPS .

    Audio visual on electrical System.

    DAY - 3 Switchyard (A typical layout of

    Switchyard of a Thermal PowerStation, Bus system, Isolators, CTs,

    PTs, Earthing, Oil Circuit Breakers,

    Air Blast Circuit Breakers. SF6 Circuit

    Breakers).

    Plant Visit (Switchyard, HT/LT

    System, DC Supply System).

    DAY - 4 Audio/Visual Session Discussion

    DAY 5 Written Appraisal.

    17

  • 8/6/2019 Syallabus of PGDC

    18/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Scheme Briefing & Tracing

    (Duration) : 2 Weeks1ST

    WEEK

    FORENOON AFTERNOON

    DAY - 1 Scheme briefing in class room on

    Boiler Drum connections, Feed

    regenerating Heating System, Air and

    Flue Gas Path.

    Class Room briefing on Fuel oil

    system and milling system.

    DAY - 2 Class Room briefing on Main steam.

    Cold reheat, Hot reheat lines,

    condensate & feed water lines, BFP,

    CW schemes.

    Class Room briefing on Hydrogen

    cooling, stator water cooling, seal

    oil system, switchyard, AC/DC

    auxiliary power supply system,

    DAY - 3 Scheme Tracing: Coal Handling,

    Receiving points. stocking lines,weighing, sampling. Screening,

    crushing, bunker filling, conveyors,

    tension arrangement for conveyors.

    Oil Handling (Unloading

    arrangements, oil tank mountings,oil pump house connections, tank

    heating. pipe line layout with

    provisions for expansion.).

    DAY - 4 Boiler - Feed Water Schemes (Feed

    control station arrangement,economiser connections, economiser

    recirculation lines, boiler drum, water

    wall connections; drain header, blow

    down lines, CBD, IBD, SH/RH,attemperator station).

    Steam Schemes (MS, CR & HRH

    lines up to turbine control valvesincluding HP/LPby pass, locationof safety valves, vents and drains,

    auxiliary PRDS schemes, auxiliary

    steam distribution, soot blowing

    steam lines).

    DAY 5 Air and Flue Gas Schemes (ID,FD, PA

    fans and their control system including

    Seal air/ Scanner air/ Igniter air

    Fans/Systems/ Damper control forsecondary air.

    Fuel Schemes (Scheme of RC

    bunkers and RC feeders, Coal mill

    connections. Light oil and.

    atomising air system, location oftrip valves, air control valves,

    nozzles valves and igniters. Heavy

    oil and atomising steam system).

    18

  • 8/6/2019 Syallabus of PGDC

    19/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Scheme Briefing & Tracing

    (Duration) : 2 Weeks2ND WEEK

    FORENOON AFTERNOON

    DAY - 1 Water Treatment Plant (Raw water

    tanks to DM Water storage tanks,

    arrangement of Pressure

    sand/Activated carbon filters, cation,

    anion, mixed beds, degassifier, back

    washing system, regeneration,

    Phosphate and Hydrazine dozing

    scheme.

    Ash Handling System - Bottom

    Ash and Fly ash disposal system

    hoppers/Clink grinder, HP/LP

    water injection, Ash slurry pumps

    etc.

    DAY - 2 Steam Extractions and Drains(Schemes of turbine extractions,

    FCNRVS, Heater drain connections,

    HP/LP drips. Schemes for heating

    flanges and studs. Steam

    connections/condenser air line

    connections to ejectors, Unit drain

    tank/flash tank connections).

    Condensate and Feed WaterSchemes (CEP connections,

    scheme of condensate flow,

    ejectors, gland steam coolers, LP

    heater, deaerator connections.

    Scheme of Feed Water flow, BFP

    connections, Feed water

    connections to HP heaters,

    Location of valves,interconnections, by pass

    arrangement for heaters)

    DAY - 3 Turbine Oil System (Turbine lube oil

    schemes, lube oil purification schemes,

    location of MOT & lube oil pumps, Oil

    coolers, cooling water connections.

    CW System and Cooling Towers

    (locating moving screens, CW

    Pumps, Venting arrangements,

    Valve locations, Chlorination

    schemes).

    DAY - 4 Generator (Seal oil scheme, Hydrogen

    scheme, Stator water cooling schemes,

    Excitation arrangements).

    Switchyard (GT to feeder line

    arrangements, locating various

    transformers (GT, UA SAT, CTO,PTO), switchgears, isolator

    earthing arrangement, buses etc

    DAY 5 Auxiliary Power Supply (6.6 KV

    schemes/ 420 V Schemes, arrangement

    of breakers, buses. DC system, battery

    bank arrangement).

    Viva-voce.

    19

  • 8/6/2019 Syallabus of PGDC

    20/61

  • 8/6/2019 Syallabus of PGDC

    21/61

  • 8/6/2019 Syallabus of PGDC

    22/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (OPERATION)

    (Duration): 5 Weeks

    1STWEEK

    FORENOON AFTERNOON

    DAY - 1 Working with Boiler Firing floor Operator :(Cleaning of oil guns/Filters and their trial run,

    Checking feed control valves, blow down valves,

    air vents, coal feeders, secondary air dampers,

    ash level in economisers hoppers, Operation of

    Blow downs, chemical dosing valves operation,

    Charging of drum gauge glass aux. steam for

    soot blowing).

    Continue.....

    DAY - 2 Working with Coal Mill Operator (Shift taking

    over/handing over checks, Pre start checks,Routine checks, Mechanical Isolation of mills,

    Cold and hot air damper operation, Activities

    during emergency in mill area, Changing over of

    seal air filter, Oil filling into mill gear box)..

    Continue .....

    DAY - 3 Working with. Ash. Disposal operator

    (Checking for Shift taking over/handing over,

    Routine check (Note atleast one reading), Ash

    flow rate in full load and partial load unit

    operation (from Bottom ash and ESP Hoppersetc., ESP field electrical system, Isolation and

    charging of ESP fields, Ash disposal urn Color

    of Ash

    Continue .....

    DAY - 4 Working with Boiler Fans Operator (Checking

    -for shift taking over and handing over, Routine

    checks (Note: atleast one reading), Isolation of

    ID,FD,PA fans, Charging of lube Oil system,

    Change over of lube oil pump)

    Continue .....

    DAY 5 Working with Compressor Operator (Shift

    handing over/taking over checks, Routine checks

    (Note: atleast one reading), Charging of Drier,

    Regeneration of Drier, Starting and stopping

    procedure. Emergency operation.

    Continue .....

    Note:- The students shall Undertake the 'Rotational On-job Training (Oprn),in the Power Station

    identifiedby the concerned NPTI. The course Co-ordinator shall make the appropriate shiftroaster suiting to local conditions/shift roaster of the power plant.

    22

  • 8/6/2019 Syallabus of PGDC

    23/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (OPERATION)

    (Duration) : 5 Weeks

    2ND WEEK

    FORENOON AFTERNOON

    DAY 6 Working with Boiler side supervisor(Shift taking over/handing over checks,

    Coordination with local operators,

    Reporting to Control Room,. Routine

    checks (Note: atleast one reading).

    Continue .....

    DAY 7 Working with Boiler Control Desk

    Operator (Shift handing/taking over

    checks, Receiving site report from

    operators and supervisor concern,

    Logging of parameter (Note: atleast onereading), Operation procedure of

    different equipment

    Continue .....

    DAY 8 Working with Boiler Control Desk

    Operator

    (Shift handing/taking over checks,

    Receiving, site report from operators

    and supervisor concern Logging of

    Parameter (note: atleast one reading),

    Operation procedure of differentequipment.

    Continue .....

    DAY 9 Working with CEP Operator (Shift

    handing over and taking over, Routine

    checks, Chemical dosing pump, starting

    procedure and making of chemical

    solution, Checking of make up and other

    controller, Priming of water box, Start of

    ejectors, Charging of LP Heat

    Continue .....

    DAY 10 Working with BFP Operator (Shift

    handing over and taking over, Routine

    checks (Note: atleast one reading),

    Precheck for starting BFP, Charging of

    lub oil system, Change over of filters,

    checking of control v/vs., Operation of

    Recirculation valves, Charging Isolation

    of HP Heaters, Deaerator water heating,

    Aux.. steam charging/isolation) Valve

    Continue .....

    23

  • 8/6/2019 Syallabus of PGDC

    24/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (OPERATION)

    (Duration) : 5 Weeks

    3RD WEEK

    FORENOON AFTERNOON

    DAY 11 Working with Turbine Operator(Shift handing over & taking over, Routine checks

    (Note: one reading), rechecks for starting lub oil

    system, Filling of oil in Main Oil Tank, AC, DC,Jacking oil pump checks, Instrumentation fitted with

    main oil tank, Parameters of Governing system,

    Charging and isolation of governing system, ESV, IVs

    and control V/Vs, local operation, HP/LP By pass

    Continue .....

    DAY - 12 Working with Generator Operator ( Shift handing

    and taking over, Routine checks, Pre start checking ofseal oil, Hydrogen cooling, Stator water cooling system,

    Purging of H2 and C02 of Hydrogen cylinder charging,

    Cooler/Filter charging.

    Working with Turbine Supervisor (Shift

    handing/taking over, Routine checks by supervisor,

    Coordination with Operator, Reporting to Control

    Room)

    Continue .....

    DAY - 13 Working with Turbine Desk Operator (Shift handing

    over & taking over, Receiving report from supervisorsand operators, .Logging of parameters, Operation

    Procedure of main equipment, ATT & ATRS operation,

    Emergency operation).

    Continue .....

    DAY - 14 Working with Electrician/Supervisor (Shift handing

    over and taking over, Routine check of Diesel set and

    other parameter, HT & LT Breaker Isolation and

    normalisation procedure, Charging of DC Batteries,

    Checking ofGT, U AT and service transfolll1ers, Safety

    devices, Operation of switchgear compressor).

    Continue .....

    DAY 15 Working withElectrical Desk Engineer(Shift handing over/taking over checks,

    Routine check (Note one reading), Operation procedure

    of various equipment at generator desk like excitation s

    stem. AVR etc).

    Continue .....

    24

  • 8/6/2019 Syallabus of PGDC

    25/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (OPERATION)

    (Duration) : 5 Weeks

    4TH WEEK

    FORENOON AFTERNOON

    DAY 16 Working with Hydrogen Plant Operator(Shift handing / taking over, Operation of H2

    Plant, Filling operation of H2 cylinder,

    Analysis of H2and O2 concentration. Routine

    checks).

    Continue .....

    DAY - 17 Working Coal handling control room

    (Shift handing/taking over, Pre-checks of

    CRP equipment operation, Operation of

    Crusher, belt conveyor, tripper, flap gate,

    Unloading procedure of wagons, Magneticseparator and weighing arrangement, Routine

    checks, Bunker filling and level monitoring,

    Coordination with mines, unit incharge and

    shift incharge, Coal amt. recording,

    Reclaimer).

    Continue .....

    DAY 18 Working with Switchyard Control Room

    Engineer (Shift handover/takeover, Routine

    check, Load schedule for the month, week

    and day, Load sharing by Units,Charging/isolation of HT Bus, Reporting to

    in house and external agencies about load

    schedule. operation of Isolators and brokers).

    Continue .....

    DAY 19 Working with Cooling tower and cooling

    water pump operator (Shift handing

    over/taking over, Routine checks, Pre-start

    checks of CT and CW Systems,

    Starting/Isolation of cooling towers, CT .'

    Pumps, CW Pumps, Emergency operation,Lub oil system of C\V and CT Pumps.

    Continue .....

    DAY 20 Working with Performance Monitoring

    Cell (Collection of information from each

    section, Programme for calculation (show at

    least one day calculation of all parameter),

    Analysis of result and comments preparation,

    Daily plant meeting (input and output),

    Reporting to concern about plant

    performance).

    Continue .....

    25

  • 8/6/2019 Syallabus of PGDC

    26/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (OPERATION)

    (Duration) : 5 Weeks

    5THWEEK

    FORENOON AFTERNOON

    DAY - 21 Working with Shift chemist(Shift

    handing over / taking over, Routine

    activities, Collection of samples of

    (Coal:-oil, H2, Drum Water, Steam

    Condensate etc.) (note down pt. of

    sampling), Analysis of sample (Note

    down the value), Action suggested to

    bring the concentration normal.

    Continue .....

    DAY 22 Working with DM Plant chemist (Shift

    handing over and taking over, Routinechecks, Storage tank. for clarified and

    DM water, Starting and Isolation of DM

    Water pump Regeneration of Ion

    Exchange

    Continue .....

    DAY - 23 Working with Unit Incharge (Shift

    hand over/take over, Investigation and

    reporting of plant defects and

    abnormalities. Issue and canceling of

    PTW, Hot and Cold startup of unit,Decision during emergency,

    coordination and reporting of problem to

    higher Management, Main parameters,

    monitored (take one reading).

    Continue .....

    DAY - 24 Working with Shift Incharge (Shift

    handing over / take over, Receiving

    report from unit Incharge, Instruction to

    SCE regarding load sharing, Reporting

    to higher management, Main parametersmonitored (take one

    reading).

    Continue .....

    DAY 25 Working with Air-conditioning

    Operator

    (Shift hand over/take over. Routine

    checks (take one reading). Temperature

    Control, Humidity Control, Operation of

    AC Plant, Dust Control).

    Apprasial/Disussions

    26

  • 8/6/2019 Syallabus of PGDC

    27/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Erection, Commissioning & Construction Management

    (Duration) : 2 Weeks

    Erection, Commissioning1st Week

    FORENOON AFTERNOON

    DAY - 1 Preparation of commissioning, trial run

    of various equipments, commissioning

    of valves, air and gas tightness test of

    boiler.

    Chemical cleaning of Boiler

    preparation for boiler light up,

    thermal flow test of water walls and

    economisers, steam blowing.

    DAY - 2 Safety Valve setting, reliable run of

    boiler, Hydraulic test of boiler.

    Alkaline flushing and commission-

    ing regenerative system, acid

    cleaning of oil pipe lines, oilflushing procedure of lubricating

    oil and governing, system.

    DAY - 3 Turbine Lubricating oil flow testing,

    steam blowing, reheater safety Valve

    setting, vacuum tightness test ejector

    testing.

    Commissioning of governing

    system ATRS & ATT, and TSE.

    DAY - 4 Commissioning of generator and

    auxiliaries (Generator testing, rotorand stator cooling system, excitation

    system

    Commissioning of electrical system

    (Circuit breakers, isolators, CT andPT, rectifiers, switchgear DC

    system).

    DAY 5 C&I Commissioning activities

    (Minimum instrumentation s required

    for major C&I commissioning,

    commissioning of control of valve,

    tuning of control valves).

    Discussion/Appraisal

    27

  • 8/6/2019 Syallabus of PGDC

    28/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Erection, Commissioning & Construction Management

    (Duration) : 2 WeekConstruction Management

    2

    nd

    WeekFORENOON AFTERNOONDAY - 1 Construction, Site Organisation and

    Administration Estimating, Costing

    and Bidding

    Construction Contracts &

    Contracting Construction Materials

    and Construction Project

    Management Techniques

    DAY - 2 Tendering, Bidding, Contract Laws &

    Claims Management Risk

    Management Project Risk

    Management

    Construction site Personnel

    Management Manpower Planning

    Techniques Labour Laws for

    Construction

    DAY - 3 Site Management, Construction

    Finance Management, and Cost

    Accounting

    Materials and Logistics

    Management, Project Management

    DAY - 4 Introduction to Construction Safety,

    Common Safety Hazards, Laws on

    Construction Safety, Health andWelfare, Safety Practices and

    Standards

    Introduction to Equipment and

    Machines used in power plant

    construction, Planning andSelection, Case Studies on

    Construction Equipment

    Planning and Selection

    DAY 5 Construction Equipment Maintenance,

    Case Studies on Construction

    Equipment Maintenance

    Management Information Systems

    in construction management,

    Construction Quality Management,

    Productivity, Safety and Quality

    28

  • 8/6/2019 Syallabus of PGDC

    29/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Performance and Efficiency Calculation

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Introduction, Need for performance

    monitoring, objective, controllable and

    un-controllable factors, basic

    requirements.

    Factors influencing performance of

    Boilers and Optimisation (Fuel

    properties, excess air, fineness of

    PF etc.)

    DAY - 2 Performance Monitoring of Boiler

    Auxiliaries (Pulverisers, Factors,

    sampling of pulverised coal, classifier

    adjustments, mill rejects, causes and

    remedies) Air Heaters (effect of AHoutlet temperature, Performance tests)

    Fans (Performance, curves, optimum

    operation point.)

    Boiler efficiency calculation

    (Direct method calculation,

    limitations in adopting direct

    method, (Losses method, Other

    standard method.)

    DAY - 3 Factors influencing performance of

    turbine( Steam pressure, temperature

    and

    Back pressure, cylinder efficiency,

    deposits on turbine blades, blade

    roughness, effect of tubes) TurbineLosses..

    Factors affecting performance of

    condenser and feed heater ( TTD,

    CW inlet, temperature, CW flow,

    heat transfer across tubes) Heaters

    (air accumulation, steam side/

    water side fouling, drainage, Effectof attemperation in reheaters). Heat

    balancing.

    DAY - 4 Turbine heat rate calculations (Method

    parameters required).

    Optimisation of auxiliary power

    consumption (Scope, variable

    speed drives, operation of un-

    necessary running auxiliaries).

    DAY 5 Logging and recording (Scope of

    logging and recording, use ofDAS/DDC in performancemonitoring).

    Discussion and appraisal.

    29

  • 8/6/2019 Syallabus of PGDC

    30/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Chemistry ,Metallurgy, NDT and Welding

    Duration : 2 Week

    Chemistry

    1/2 Week

    FORENOON AFTERNOON

    DAY - 1 Basic chemistry (Atomic structure,

    elements, compounds, mixtures,

    solutions, ionization, salts acids alkali

    pH values).

    Pre and post treatment of water.

    DAY - 2 Chemical control and treatment of

    Boiler feed water and steam. Coolingwater treatment

    Classification of coal & oil, their

    sampling and analysis

    DAY - 3 Corrosion theory and deposition

    30

  • 8/6/2019 Syallabus of PGDC

    31/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Chemistry ,Metallurgy, NDT and Welding

    Duration : 2 WeekMetallurgy

    1 Week

    FORENOON AFTERNOONDAY - 1 Introduction to Metallurgy and its

    relevance in power industry crystal

    structure - space lattices - crystal lattice

    imperfections - crystal structure under

    stress.

    Elastic and Plastic deformations,

    strain hardening and fracture

    Mechanical properties of materials -

    Testing of materials.

    DAY - 2 Steel making - MicrostructureComposition/property relationship of steel

    - effects of - alloying - power plant steels.

    Heat treatment and surface hardeningof steel failure mechanism - typical

    such situations in a power plant.

    DAY - 3 Non-ferrous metals and alloy's:

    Application of Non ferrous metals and

    alloys in PP condenser components -

    conductors slot wedges in generator rotor -

    pipe to pipe couplings - bearings. Copper,

    Aluminum, Nickel, Magnesium. Titanium

    and their alloys in properties of theses

    alloys failure mechanism.

    Non metallic materials : Use of

    plastics and rubber in PP

    Thermoplastics thermo sets rubbers

    their properties. Application, coatings,

    adhesive, linings, insulation seals,

    sealants, gaskets etc. Application of

    ceramics in Power Plant Insulation

    Refractory properties.

    DAY - 4 Material selection for Design Material

    requirement, specification and relevant

    standards fro boiler, turbine, generator

    components Piping and Valves :

    Appreciation of component, fabrication

    metal forming, casting forging, pipe

    bending, tube manufacture.

    Protective surface treatment. (Metal

    cleaning protective Metal coating,

    Fabrication of precoated metals).

    DAY 5 Defect analysis and life assessment. Lowtemperature behavior. high temperature

    behavior - defect assessment of

    solidification crack austenite stainless steel

    welds, cracking in CrMoV weldment etc.

    Thermal fatigue - various tests - Defects

    assessment route and calculation of

    damage. Remaining life assessment

    beyond design life of boilers, turbine

    rotors, generator rotors etc.

    Group discussion and appraisal

    31

  • 8/6/2019 Syallabus of PGDC

    32/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Chemistry ,Metallurgy, NDT and Welding

    Duration : 2 Week

    NDT & WELDING1/2 Week

    FORENOON AFTERNOON

    DAY - 1 Introduction to welding and types of

    welding.

    Description of welding methods

    generally used in thermal power

    station.

    DAY - 2 Welding machines, types of electrodes,

    precautions during welding process,

    welding defects.

    Purpose of NDT and types of

    defects cover by NDT.

    DAY - 3 NDT Methods used in power station

    (Principle, equipments, utilization,merits and de-merits).

    32

  • 8/6/2019 Syallabus of PGDC

    33/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Gas turbine & combined cycle power plant

    (Duration) : 1 Week

    1st

    week

    FORENOON AFTERNOON

    DAY - 1 Gas Turbine and Combined cyclepower plant-introduction, basic cyclesand types of CCGT

    Fuels for gas turbine plants,physical and chemical propertiesof fuels and their analyses

    DAY - 2 Description and construction details ofCompressorsDescription and construction details of

    Combustors

    Gas turbine construction details-blade materials and its selection,cooling arrangement

    DAY - 3 Gas turbine support system, inlet /exhaust systems, lube oil system, fireprotection system, governing system

    Waste heat recovery steamgenerator - Description andconstruction details.Cogeneration plants.

    DAY - 4 Emission control main emissionproducts, its effects and control.

    Operation of Gas Turbine andCCGT plant- Pre checks, Startupand shutting down procedureincluding normal operation.

    DAY 5 Efficiency and performancemonitoring, optimization of CCGT,performance testing.

    Combined cycle power plantmaintenance- planning forschedule maintenance, variouschecks, case study.

    33

  • 8/6/2019 Syallabus of PGDC

    34/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Advanced Steam Generation Technology- Supercritical and FBC

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Introduction to supercritical

    technology, advantages-World

    scenario in supercritical technology.

    Arrangement of super critical

    boilers and their types. Comparison

    between spiral water wall

    circulating and vertical tubing.

    DAY - 2 Special alloys for super critical boilers

    and welding techniques.

    Differences between Supercritical

    and subcritical Technology

    DAY - 3 Introduction to FBC TechnologyAdvantages, Scope, Fuel flexibility etc

    Classification of FBC technology

    boilers.

    DAY - 4 Description of various components ofCFBC Boiler

    Environmental benefits

    DAY 5 Limitations, major concerns in the O&M ofFBC Boilers Visit to Supercritical/FBC Boilers

    .

    .

    .

    34

  • 8/6/2019 Syallabus of PGDC

    35/61

  • 8/6/2019 Syallabus of PGDC

    36/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    SECOND

    SEMESTER

    PGDC IN TPPE

    36

  • 8/6/2019 Syallabus of PGDC

    37/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Plant Protection

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Introduction (Terminology,

    Requirements of protective system,

    Historical developments) Protective

    Relays (Types and their applications,

    Construction, Maintenance

    requirements, Setting and testing).

    Methods of system earthing and the

    fault conditions, Lighting / Surge

    Instrument transformers.

    DAY - 2 General Protection (Neutral earthing.Stator and rotor earth faults, Sustained

    external faults, Instability, Protective

    systems used above).

    Transformer Protection (Variousprotections, Protective systems for

    Transformers, UATs & STs).

    DAY - 3 Motors (Faults and protection

    systems).

    Automatic Voltage (Requirements,

    types and function mechanical,

    electronic amplifier magnetic

    amplifier regulators, construction,

    maintenance and testing).

    DAY - 4 Bus bar Protection (Continuity of

    supply, Discrimination, Circulating

    current systems, Special features

    relating to different voltage - Pilot

    wire, carrier current, systems).

    protection, PLCC Tele

    Communication).

    Feeder Protection (Continuity of

    discrimination, Outline of Pilot

    wire, carrier current, protection,

    PLCC Tele communication).

    DAY 5 Visit to Power Station and Lab.

    demonstration.

    Group discussion and appraisal.

    37

  • 8/6/2019 Syallabus of PGDC

    38/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Energy Audit(Duration): week

    FORENOON AFTERNOON

    DAY-1 Need for Energy Audit and AuditProcedures. Energy Audit Macro Level & Micro Level.

    Energy Management System, EnergyAuditing and their implementationtechniques for power industries.

    DAY-2 Energy Saving methods withtypical examples and exercisesfor power stations

    Ways to minimize losses in powertransmission & distribution system

    DAY-3 Energy Losses An Integratedoptimal strategy for reduction ofT&D Losses.

    38

  • 8/6/2019 Syallabus of PGDC

    39/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Maintenance Planning & Cost Control

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Aims and objective of maintenance

    efficient service, high plant

    availability, maintenance learningengineer's duties.

    Integration of maintenance with

    requirements, plant reliability,

    plant and daily work programs.

    DAY - 2 Preventive maintenance of running

    units.

    Planning of major plant overhauls

    shutdowns.

    DAY - 3 Planning techniques critical path

    analysis, charting system etc.

    Purchasing and stores control-

    standards, cost codes. Control of

    stores and store records.

    DAY - 4 Cost control. Direct costs, indirect

    costs, outage costs, budgeting and

    costing work, budgetary control.

    Contract procedures (Conditions of

    contract, capital applications and

    procedure, project evaluation,

    interest and depreciation charges).

    DAY 5 Role and application of Information

    Technology in maintenance planning.

    Group discussion and Appraisal

    39

  • 8/6/2019 Syallabus of PGDC

    40/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Nuclear Power Plant Familiarization

    (Duration) : 1 Weeks1ST WEEK

    FORENOON AFTERNOONDAY - 1 Introduction of nuclear energy, energy

    from nuclear fusion, plasma, energyfrom nuclear fission

    The fission process and fissionproducts, radioactivity, radioactivematerials

    DAY - 2 Regulation for governing theproduction of power from nuclear fuel& safety aspect. National policyregarding Nuclear power generation.

    Nuclear reactor and power plant-Reactor, general components ofnuclear reactor.

    DAY - 3 Pressurized water reactor (PWR),boiling water reactors (BWR) &Canadian deuterium uranium reactor(CANDU)-mass and heat balance,working principle and constructiondetails

    Gas-cooled reactor, liquid metalcooled reactor - mass and heatbalance, working principle andconstruction details, material forGas-cooled reactor, liquid metalcooled reactor, advantages and

    limitation. Sodiumgraphite reactorSGR, fast reactors.

    DAY - 4 Organic cooled and moderatorsreactor, Breeder reactors workingprinciple and construction details,material for reactor

    Nuclear materials-nuclear fuel,coolant, moderating and reflectingmaterials, shielding materials.

    DAY 5 Nuclear waste & its disposal-types ofnuclear waste ,effect of nuclearradiation

    Appraisal

    40

  • 8/6/2019 Syallabus of PGDC

    41/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Renewable Energy and Hydro Power Plants

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Energy Sector Reforms, RegulationsEnvironment and RE

    Wind Energy Systems

    DAY - 2 Solar thermal power systems Direct energy Conversation - SolarPhotovoltaic, Fuel Cells.

    DAY - 3 Biomass Energy Systems. Introduction of small, mini andhydro power generations

    DAY - 4 Basic features of hydro Turbines Hydrology and estimation of waterpotential

    DAY 5 Site selection and Layout of Hydropower plants

    Description of Hydro TurbineInterlocks and protection

    41

  • 8/6/2019 Syallabus of PGDC

    42/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Maintenance Practice & Inspection

    (Duration) : 4Weeks1ST WEEK

    FORENOON AFTERNOON

    DAY - 1 Checking of Boiler tubes for external

    damage due to erosion or cutting.

    Method to overcome, e.g.

    strengthening of tubes in the flow

    channels.

    Hydraulic test, allowable rate of

    pressure drop. Checking of welds

    pin holes.

    DAY - 2 External cleaning of boiler surface and

    water washing. Use of sky climber,

    Different types of tube failures creep

    overheating

    Measurement of tube wall

    thickness, Checking of flue gas

    path for direct corrosion or erosion

    and leakage.

    DAY - 3 Checking of isolating and regulating

    dampers for leakage, proper alignment,

    adjustment for both under cold and hotoperation conditions.

    PA, ID & FD fan check for inlet

    dampers bearing alignment, vibrat-

    ion both radial and axial shift ofmagnetic centre of motor and rotor,

    fan blade conditions mode of

    repairs, hard facing

    DAY - 4 Checking of boiler mountings and their

    adjustments (a) Gauges glasses, (b)

    Safety valves, their checking and

    settings of safety valves for blow

    down and dropping

    Checking the burner nozzle for

    burnout and reasons for the same

    and its metallurgy

    DAY 5 Check the flow distribution in burners

    adjustment of orifices or valves check

    the burner flow direction and its

    adjustment, checking of burner

    chamber, dampers breakage of linksand proper gauge operation

    Check the rollers or ball wear of

    coal mill also Ball ring segment

    wear. Keeping of capacity and hour

    of operation. Check roller thrust

    bearings and ring, seals

    42

  • 8/6/2019 Syallabus of PGDC

    43/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Maintenance Practice & Inspection

    (Duration): 4Weeks2ND WEEK

    FORENOON AFTERNOON

    DAY - 1 Check the adjustment of roller of ball

    pressure check for leakage of coal and

    air around journal assembly main shaft

    and possible contamination of

    lubricating oil method for reservation

    Check the gear-box worm and

    worm wheel driver for wear and

    backlash allowable limits. Check

    classifier vane angular position

    proper operation and coal fineness

    DAY - 2 Air heater maintenance/trouble

    shooting causes and remedies

    Soot Blowers Maintenance/Trouble

    shooting causes and remedies

    DAY - 3 Safety valve maintenance and its float

    procedures, trouble shooting/causes

    remedies

    Procedure for alkali boil out and

    acid cleaning preservation and

    flushing, Procedure for flushing

    and preservation both wet and dry

    DAY - 4 Internal checking of drum and druminternals, Checking of at temperature

    including spray nozzle and shock linen

    Boiler bottom air seal, proper andfree movement and expansion of

    boiler setting when hot. Normal

    water level and flow in bottom seal.

    Adjustment and prevention of dust

    accumulation in the seal chamber

    DAY 5 Maintenance of clinker grinder, bottom

    ash hoppers maintenance of De-

    watering pump slurry pumps and slurry

    line

    Furnace tightness checking, Bench

    mark for draught loss for different

    gas flow

    43

  • 8/6/2019 Syallabus of PGDC

    44/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Maintenance Practice & Inspection

    (Duration) : 4Weeks

    3RD WEEK

    FORENOON AFTERNOON

    DAY - 1 Checking of tubes for any obstruction

    land test or temperature rise and drop

    test.

    Procedure of welding of tubes in

    membrane walls and tubes of

    different composition

    DAY - 2 Mechanical portion of governing

    system and its maintenance

    Checking of over speed ring and

    eccentricity pick up for correct

    operation.

    DAY - 3 Checking of turbovisory instrument

    particularly total expansion and

    differential expansion

    Turbine rotor and blade

    maintenance and inspection checks,

    Checking of turbine cylinders for

    cracks deformation.

    DAY - 4 Checking the rotor position with

    respect to clearance in HP IP and LP

    wheel clearance and also thrust bearing

    and its wear. Checking the condition of babbit metal for scoring pitting,

    chipping of or lack of bondage

    between the babbit and the shell.

    Main oil pump cleaning/flushing of

    main oil tank, pipes, cleaning of

    filters oil coolers, mtce. , of jacking

    oil pumps.

    DAY 5 Overhauling of control valves, ESVs

    and IVs, Maintenance and inspection

    of oil system turbine oil coolers,

    Maintenance of condensate side and

    steam side tubes

    Condenser tube maintenance, off

    lead and off load cleaning

    procedure

    44

  • 8/6/2019 Syallabus of PGDC

    45/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Maintenance Practice & Inspection

    (Duration): 4Weeks

    4TH WEEK

    FORENOON AFTERNOON

    DAY - 1 Maintenance of main ejectors and

    starting ejectors Trouble shooting

    causes remedies, Checking of axial

    shift indicating system for Clean oil

    nozzle and strainers.

    Checking of bearing clearances and

    allowable limits. Checking of

    cylinders parting surface, for

    proper matching, its grinding for

    the purpose.

    DAY - 2 Checking of gland and seal strips, their

    clearances with allowing limits.

    Checking the coupling alignment

    of HP IP and LP rotors andgenerator and their. Setting.

    Checking and setting of bearings

    on foundation. Checking of shaft

    sinking due to I vacuum pulling.

    DAY - 3 Generator Maintenance : A Stator -

    Checking overhang winding, clamp

    and shields, loss wedges and

    overheating.

    Rotor checking of shaft earthing

    arrangement. hydrogen seal and

    leakages (purge test) loss wedges,

    end ring for cracks, overheating.

    Insulation resistance and windingresistance.

    DAY - 4 Transformer maintenance - insulation

    testing drying out routine maintenance.

    HT Switchgear testing - routine

    and type tests.

    DAY 5 Motor Insulation checking, terminal

    checking, phasing out. motor drying.

    Cable jointing, material and

    techniques

    45

  • 8/6/2019 Syallabus of PGDC

    46/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Design Analysis(Duration): 1 week

    1st WEEK

    FORENOON

    AFTERNOON

    DAY-1 Process designing, Equipment and

    System Design criteria

    Pressure Vessel design

    DAY-2 Heat Exchanger Design, Rotating

    equipment design

    Steam Generator Design

    DAY-3 Steam turbine design consideration Piping layout& Piping Design, Design of

    Ash handling systems and equipment

    DAY-4 Electrical System Design Design of HT/LT motors

    DAY-5 Design of transformers Instrumentation System Design

    46

  • 8/6/2019 Syallabus of PGDC

    47/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Load Dispatch

    (Duration) : 1 Week

    FORENOON AFTERNOON

    DAY - 1 Objective, functions and structure of

    Load dispatching stations An

    overview.

    Location of load dispatch stations

    area, state and regional and their

    functions Voltage and frequency

    control. Trends in design and

    engineering of load dispatch /

    systems.

    DAY - 2 MW and AVAR sharing between

    stations and systems voltage control-Concept of base load and peak load

    operations - Economic dispatch

    aspects.

    Load forecasting - Short tern and

    long term.

    DAY - 3 Application of computers - DAS,

    RTUs and SCADA.

    HVDC systems and SVC

    operation.

    DAY - 4 Networking and protocol for data

    exchange latest developments.

    PC based power system study

    package.

    DAY 5 Visit to load dispatch centre. Group discussion and appraisal.

    47

  • 8/6/2019 Syallabus of PGDC

    48/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Power Reforms and Regulations(Duration): 1 week

    1st WEEK

    FORENOON

    AFTERNOON

    DAY-1 Power sector reforms-the Indianperspective, Indian Electricity Act2003

    National electricity policy, energyconservation act

    DAY-2 Power sector reforms inGeneration, Transmission

    Distribution Reforms

    DAY-3 CERC-Functions andresponsibilities Case studies on Open Access system-long term and short term

    DAY-4 National Tariff policy/ Multi yeartariff/ABT

    APDRP/RGGVY Scheme

    DAY-5 Power Trading and Sharing Case studies on tariff discovery throughcompetitive bidding, quality of power

    48

  • 8/6/2019 Syallabus of PGDC

    49/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Control & Instrumentation

    (Duration) : 2 Weeks

    1st WEEK

    FORENOON AFTERNOON

    DAY - 1 Concept and .layout of Control and

    Instrumentation in Thermal Power

    Plant.

    Pressure Measurement and

    measuring instruments.

    DAY - 2 Temperature measurement andmeasuring Instruments.

    Flow measurement and measuringInstruments.

    DAY - 3 Level Measurement and measuring

    Instruments.

    Practical demonstration on pressure

    and flow measurements.

    DAY - 4 Practical demonstration on level and

    temperature measurements.

    Protection and interlocks of Boiler,

    turbine and their auxiliaries.

    DAY 5 Introduction to auto control. Auto control loops used in thermal

    stations.

    49

  • 8/6/2019 Syallabus of PGDC

    50/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Control & Instrumentation

    (Duration) : 2 Weeks2nd WEEK

    FORENOON AFTERNOON

    DAY - 1 Turbovisory instrumentation (Parameters

    limits, Basic concepts of measuring

    devices).

    Commissioning of control loops

    demonstration.

    DAY - 2 ATRS. Visit to control and instrument at

    control/control stations in the

    stations.

    DAY - 3 Analytical Instrumentation for (Boiler

    Water, Steam, Flue Gas, H2/02/C02).

    Practical demonstration and

    analytical instruments. (Correct :

    sampling and testing).

    DAY - 4 Introduction to DOC and DAS in

    Thermal

    Power Station.

    Continued ...

    DAY 5 Introduction to new/latest technology in

    Control and Instrumentation in modernthermal power station.

    Group discussion (Performance)

    50

  • 8/6/2019 Syallabus of PGDC

    51/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : IT Application in Power Sector & GIS

    (Duration) : 2 Weeks

    1st week

    FORENOON AFTERNOON

    DAY - 1 Core of Information Technology (IT)Information Technology OverviewData Structures

    Development of ComputerTechnologyCommunication & NetworkingData Processing Techniques

    DAY - 2 Hands-on practice on Windows, MS-Office and Typical Application Packages.

    4 Exercises of Hour duration to be done

    in this session.

    Computer Networks Resource

    Sharing Network Topologies

    Network Hardware Wired vs.

    Wireless Networks Wi-fi &

    Bluetooth Communications

    Limitations - Client/Server

    Architecture - LAN, WAN, TCP/IP -

    Network Security.

    DAY - 3 Hands-on practice on troubleshooting andgeneral maintenance of Computers and

    Peripherals. Disk Cleanup

    Defragmentation Detecting and Clearing

    Software Virus & Spyware Preventive

    Maintenance Procedures

    Network and Internet based

    Communications Domains DNS,

    SLIP, PPP, FDDI - Browsers, Servers,

    Search Engines Email - File

    Transfer Protocol (FTP) - Telnet -

    Internet Relay Chat - Instant

    Messaging Cyber Laws

    DAY - 4 Hands-on practice on Windows 2000 or

    higher network O/S ConfiguringWorkgroups Configuring TCP/IP -

    File/Folder Sharing, Printer Sharing and

    Internet Sharing.

    Internet Management - Security

    Concepts, Information Privacy andCopyright issues Web Hosting -

    Commerce on Internet - Governance

    on Internet Management

    Information Systems.

    DAY 5 Hand-on practice on implementing aNetwork based Management Information

    System using MS-Access

    Project Management Software MS-

    Project / Primavera.

    .

    51

  • 8/6/2019 Syallabus of PGDC

    52/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : IT Application in Power Sector & GIS

    (Duration) : 2 Weeks

    2nd week

    FORENOON AFTERNOON

    DAY - 1 Concept of Geographical InformationSystem (GIS)Basics of GeographyHardware & Software Requirement

    Fundamentals of GIS and MappingData VisualisationThematic Map Preparation

    DAY - 2 Concepts of Remote Sensing Technology(RS)Basics of Remote SensingElectromagnetic Energy

    Elements of Remote SensingFundamentals of Photogrammetry

    DAY - 3 Concepts of Global Positioning System(GPS)Basics of GPS

    Concepts of Global PositioningSystem (GPS)Working with GPS/DGPS

    DAY - 4 Applications of GIS/RS in Power Generation

    Applications of GIS/RS in Power Transmission and Distribution

    DAY 5 Working with ARC-FM & CYMDIST

    software

    Working on various softwares for

    distribution network planning and

    analysis

    .

    52

  • 8/6/2019 Syallabus of PGDC

    53/61

  • 8/6/2019 Syallabus of PGDC

    54/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Duration:4 Weeks1ST WEEK

    FORENOON AFTERNOON

    DAY - 1 Boiler Maintenance (Acquaintancewith various tools and tackles, Lifting

    and material handling equipments,

    consumables and spares).

    Turbine stop valves and controlvalve mtc., Turbine governing

    system setting, Gland sealing

    system inspection, Deaerator

    maintenance.

    Overhauling of oil system, oil

    coolers, testing for leakage,

    flushing of main oil tanks etc

    DAY - 2 Boiler Drum (Drum internal and

    mounting inspection) Firing Floor(Oil guns, igniter, air, fans, scanner air

    fans, Air heater, soot blowers, wind

    box, burner, tilt and coal feeder).

    Turbine Basement/ 0 meter

    (condenser tube cleaning, CWPump Maintenance)

    DAY - 3 Furnace (Boiler tube leakage

    attending during shut down), edge

    preparation and welding, post heating

    etc. , Weld defects testing by NDTmethod, stress relieving, Coal Mills

    (Preventive maintenance andoverhauling activities, Inspection of

    classifier blades. Inspection of bull ring

    segment replacement. Thrust bearing

    and gear box replacement).

    Turbine Basement/ 0 meter

    (BFP maintenance, inspection of

    bearing, inspection of balancing

    system, inspection of mechanicalsystem, Hydraulic coupling scoop

    mechanisms, Adjustments of lubeoil pressure and filter cleaning ,

    BFP alignment). HP-LP Hearers

    Detection of tube leakage and

    plugging, Alternating water box

    leakage).

    DAY - 4 ID, FD & PA Fans (Preventive

    maintenance and overhauling

    activities, Vibration points).

    ESP and Ash Handling System (ESPmaintenance fly ash maintenance,

    clinker grinder, bottom ash, slurry

    pumps etc.)

    HP-LP Heaters (Oil Pumps

    maintenance Centrifuge bowl

    cleaning), CT Fans

    (Preventive maintenance of CTFans and Gear box, Trays and

    Nozzle cleaning, Fan blades angle

    adjustment

    DAY 5 Turbine Maintenance Stores

    (Acquaintance with various tools and

    tackles, Lifting and equipments,

    consumables and spares).

    Water treatment plant and

    Hydrogen plant (Maintenance of

    raw water pump and DM pump.

    Maintenance of H2 for

    compressors).

    Module : ROJ (Maintenance)

    54

  • 8/6/2019 Syallabus of PGDC

    55/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Duration: 4 Weeks2nd WEEK

    FORENOON AFTERNOON

    DAY - 1 Coal Handling Plant (Crushermaintenance Conveyor maintenance.

    Feeder maintenance).

    Coal Handling Plant (Tripper

    maintenance, Stacker cum Reclaimer

    maintenance

    Exposure to maintenance andtesting requirements for Drives

    DAY - 2 Oil Handling Plant (Oill heaters

    maintenance, Oil pumps rotary and

    reciprocating pump etc.,

    Filters/strainers maintenance).

    Exposure to maintenance and

    testing requirements for TSE

    DAY - 3 Familiarisation of organisation

    procedures for routine and preventive

    maintenance, breakdown and

    emergency repairs and Instrument lab.

    set up for calibration and repairs.

    Exposure to maintenance and

    testing requirements for

    Temperature Instrument

    DAY - 4 Exposure to maintenance and testing

    requirements of pressure, flow and

    level instruments at site and in lab.

    . Exposure to maintenance and

    testing requirements for DDC,

    DAS etc.

    DAY 5 Transformers Electric Generator

    55

  • 8/6/2019 Syallabus of PGDC

    56/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (Maintenance)

    Duration: 4 Weeks3rd

    WEEK

    FORENOON AFTERNOON

    DAY - 1 Circuit Breakers . Continue

    DAY - 2 Electric Motors . Continue

    DAY - 3 Electro Static Precipitator . Continue

    DAY - 4 Cables

    DAY 5 Relays and Soleenoid . Continue

    56

  • 8/6/2019 Syallabus of PGDC

    57/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : ROJ (Maintenance)

    Duration: 4 Weeks4th WEEK

    FORENOON AFTERNOON

    DAY - 1 Cranes Lift

    DAY - 2 Air Conditioning System Diesel Set

    DAY - 3 HT/LT Supply Circuits HT/LT Supply Circuits

    DAY - 4 AC/DC Lighting Circuits Batteries

    DAY 5 Viva Voce Viva Voce

    57

  • 8/6/2019 Syallabus of PGDC

    58/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Visit to Manufacturing Units/TPS

    Duration: 2 Weeks

    1ST WEEK

    DAY - 1 Monday - Travelling

    DAY - 2 Tuesday Visit to BHEL, Hardwar/ Visit to Chandrapur TPS,

    MSEB

    DAY - 3 Wednesday Travelling

    DAY - 4 Thursday Visit to BHEL, Hyderabdad

    DAY 5 Friday - Visit to BHEL, Bangalore

    DAY - 6 Saturday - Travelling

    Note:- The tour programme can be adjusted by the Institute depending their convenience.

    58

  • 8/6/2019 Syallabus of PGDC

    59/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    Module : Visit to Manufacturing Units/TPS

    (Duration) : 2 Weeks2ND WEEK

    DAY - 1 Monday Visit to Neyveli/Vijaywada TPS

    DAY - 2 Tuesday Travelling

    DAY - 3 Wednesday Visit to BHEL, Trichy/ Visit to Trombay, TPS

    DAY - 4 Thursday Visit to BHEL, Bhopal / Visit to Uran Gas Based

    PS, MSEB

    DAY 5 Friday - Travelling

    DAY - 6 Saturday Visit to BHEL, Ranipet/ Visit to DESU Gas Turbine

    Project

    59

  • 8/6/2019 Syallabus of PGDC

    60/61

  • 8/6/2019 Syallabus of PGDC

    61/61

    NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING

    2ND WEEK

    FORENOON AFTERNOON

    DAY - 1 Milling Plant Operation and raising

    pressure as per Boiler loadrequirements

    (Operation of second set of auxiliaries

    and load sharing, Change over of

    controls from manuals to auto).

    Discussion on: (Milling Plant,

    Burner, Optimum Sec. Air andDrum Level control, Burner

    Mechanism and attemperators).

    DAY - 2 Raising load in TG (Operation of

    second set of auxiliaries and load

    sharing, Checking of protections,

    Changeover of controls from manual

    to auto).

    Unit shutting down procedures.

    DAY - 3 Shutting down unit from full load to 30

    MW and again raising load to full load

    condition.

    Unit start up from hot and warm

    conditions.

    DAY - 4 Tripping unit from full load on some

    protection and start up again from hot

    condition.,

    Emergency problems in unit

    (Boiler. Turbine and Generator).

    DAY 5 Operation unit under emergencysituation.

    Summing up programme/Appraisal.