Sustainable Integrated MSW
Management including DSS
Dr Indrani Chandrasekharan
Former Adviser, Planning Commission
Wastech International Summit & Expo
‘4 R’s – A Way to Sustainability’
21-22 November 2014; Gandhinagar, Gujarat, India
![Page 2: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/2.jpg)
Current Status of MSW • 62 million tonnes of MSW generated annually by
377 Million people in urban areas, more than 80% is disposed of at dump yards in an unhygienic manner
• Waste is projected to be 165 million tonnes by 2031 and 436 million tonnes by 2050.
• The 62 million tonnes annual gen. of MSW if dumped without treatment; will need 3,40,000 cu.M of landfill space everyday. Considering the projected waste generation of 165 million tonnes by 2031, the land for landfill for 20 years (10 M high pile) could be as high as 66,000 ha. (1240 ha per year) of precious land, which India cannot afford to waste.
2 Dr Indrani Chandrasekharan
![Page 3: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/3.jpg)
Current Status of MSW
• As per CPCB report 2012-13 municipal areas in the country generate 1,33,760 metric tonnes per day of MSW, of which only 91,152 TPD waste is collected and 25,884 TPD treated. The MSW, therefore, dumped in low lying urban areas is a whopping 1,07,876 TPD.
• The untapped waste has a potential of generating 329 MW of power from 32,890 TPD of combustible wastes including Refused Derived Fuel (RDF), 1.3 Million cubic meter of bio gas per day or 72 MW of electricity from bio gas and 5.4 Million metric tonnes of compost annually to support agriculture
3 Dr Indrani Chandrasekharan
![Page 4: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/4.jpg)
Sustainable ISWM ---Data on MSW
• Data is the basic requirement to develop an sustainable
Integrated Solid Waste Management (ISWM) Plan.
• There are conflicting data about the quantum of waste
actually generated in urban areas in the country. (62
Million Tonnes,( CPCB) 70 Million Tonnes (MoUD)
As per CPCB (2012), municipal authorities have so far only
set up:-
• 279 compost plants,
• 172 bio methanation plants,
• 29 RDF plants and
• 8 Waste to Energy (W to E) plants in the country.
4 Dr Indrani Chandrasekharan
![Page 5: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/5.jpg)
Sustainable ISWM
1. Optimum utilization of all components of MSW in a cost effective manner,
2. minimization of waste going to landfill ,
3. Separate collection and transportation of inert wastes such as street sweepings , silt from surface drains and C&D wastes and
4. Keeping biodegradable and recyclable wastes separate to facilitate smooth processing of MSW.
5 Dr Indrani Chandrasekharan
![Page 6: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/6.jpg)
15-12-2014 6
![Page 7: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/7.jpg)
Status of MSWM
7
![Page 8: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/8.jpg)
Components of a Sustainable ISWM plan
• Approach:-Integrated Approach towards MSW Mg.
• System:-Centralised and Decentralized processing of
different components of waste.
• Technology:-Selection of appropriate technologies
for processing of MSW waste.
• mode of service delivery—PPP, etc
• Financing
8 Dr Indrani Chandrasekharan
![Page 9: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/9.jpg)
Integrated MSW Management
• An integrated MSW management approach
must address all essential activities viz; door to door collection, segregation, secondary storage, transportation, Transfer stations, processing and disposal of MSW simultaneously in a coordinated manner.
• Improve MSW collection System • Strengthen plastic wastes management system • Set up Waste Storage Depots / Transfer Stations
9 Dr Indrani Chandrasekharan
![Page 10: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/10.jpg)
System:-Centralized / decentralized processing
• utilize all components of waste at a decentralized
level to minimize cost of collection and
transportation to centralized processing facilities.
• Centralized plants be setup only when suitable lands
is not available /or there is opposition to setting up
such facilities. Where setting up of centralized
facilities become inevitable, these should be
sufficiently large and private sector should be
encouraged to design, construct, finance, operate
and maintain such facilities
10 Dr Indrani Chandrasekharan
![Page 11: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/11.jpg)
Decentralized v/s Centralized processing
Experts feel that decentralized approach is appropriate
for :- segregation at source,
transportation,
pre-processing of wastes,
biomethanation,
Conventional and vermi composting.
Centralized approach is recommended for :-
incineration, pyrolysis, gasification, RDF production,
mechanical composting , C&D waste processing and
managing sanitary landfills.
11
Dr Indrani Chandrasekharan
![Page 12: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/12.jpg)
Decentralized v/s Centralized processing of MSW
• decentralized processing of Biodegradable waste.
• Centralized compost or biomethanation plants should be setup where suitable lands or small entrepreneurs for setting up decentralized facilities are not available.
• For combustible waste, centralized W to E facilities sufficiently large to handle at least 500 TPD of combustible waste be setup and private sector be encouraged to invest in such projects on design, Build, finance, operate and transfer basis (DBFOT).
12
15-12-2014
![Page 13: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/13.jpg)
Centralized and Decentralized Approaches for MSW -Management
13
Issues
Type Selection Criteria
Decentralized • Land for composting/bio gas are available in local area
• Availability of informal workers for processing of waste
• High degree of organic content in waste
• Markets for compost/bio gas is available
•Possible to manage health risks adequately
•Operational expenditure is generally low
Centralized • Land is not available close to the community for decentralized model
•Significant economies of scale makes the project viable \
• Composition of waste allows high value extraction through use of technology, e.g., waste-to-energy plants
15-12-2014
![Page 14: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/14.jpg)
9/11/2014 14
Municipal Solid Waste
Thermal Process * Bio-chemical Conversion Land Filling
Composting Biomethanation Gasification Incineration Pyrolysis
Stream Turbine
Electric Generate
Power
Anaerobic Digestion
Bio-Gas
Thermal Energy
Bio-Degradable
Combustible Inerts
Bio-Fertilizer
As per MSW Rules, 2000 biodegradables cannot be land filled, so, no combustible gas collection is considered
* RDF enhances the efficiency of thermal processes
C & D Wastes
Alternate Building Material
Options available for MSW treatment and utilization
![Page 15: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/15.jpg)
Technology Options for Treatment & Disposal of MSW
• Bio-Chemical Waste to Energy Technologies
• Thermo-Chemical Waste to Energy Technologies
• Common Regional Sanitary Landfill Facility
15 15-12-2014
![Page 16: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/16.jpg)
Technological Options
• Under Indian conditions technologies identified for processing of MSW are :-
�Biomethanation for wet biodegradable wastes
�Conventional microbial windrow/mechanized/ vermi composting for wet biodegradable wastes
�Preparation of briquette/ pellets/ fluff as Refuse Derived Fuel (RDF) from dry high-calorific value combustible wastes
� Incineration / Gasification / Pyrolysis for dry high-calorific value combustible wastes
�Plastic wastes to fuel oil
16 15-12-2014
![Page 17: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/17.jpg)
Technological Models Proposed
• Based on the range of population and quantity and composition /quality (% biodegradable) of wastes generated a combination of technologies has been recommended. In addition, the cost of setting up of processing plants ,expected quantities of value added products and by-products were also considered.
• Based on these five criteria Choice of suitable technologies for various classes of cities as per census, 2011 have been made.
17 15-12-2014
![Page 18: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/18.jpg)
15-12-2014 18
![Page 19: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/19.jpg)
15-12-2014 19
![Page 20: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/20.jpg)
20
Justification for population cut-off at 5,000: Villages and peri-urban centres having population > 5,000 and more than 75% male population involved in non-agricultural activities are classified as “urban centres” as per the Census of India.
Start
YES
NO Currently not
considered
Less than
1 Lakh
For Process
Flow Diagram
Refer to Figure
1
1 Lakh to 10 Lakh
+
Hill Town
For Process
Flow Diagram
Refer to
Figure 2
1 Million
to
2 Million
For Process
Flow Diagram
Refer to Figure
3
For Process
Flow Diagram
Refer to Figure
4
Above
2 Million
Is Urban
Population Greater than
5,000?
15-12-2014
![Page 21: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/21.jpg)
21
General Framework for Integrated Municipal Solid Waste Management Scheme
Compostable materials
Purchase by kabadiwalas
Feedstock to processing facility (Centralized and / or Decentralized)
Biomethanation
Single or Regional Sanitary Landfilling Facility
Special wastes to
be handled as per SPCB
direction
Secondary storage &
transfer station
Door-to-door collection
Domestic and commercial
waste segregation
Plastics to liquid
fuel
Thermal route W to
E
RDF making
Vermi / Conventional Composting
Rejects
Street
sweeping & silt from drains
Construction
and demolition
wastes
Alternate building material
Vermi / Conventional Composting
Bulk
source of recyclabl
e
Decentralized
processing (Biomethan
ation Plant)
Energ
Manure
Hotel, vegetable market,
restaurant, abattoir
Secondary storage & transfer station
Secondary storage & transfer station
Collection of selected
materials by rag-pickers
Recycling industries
Bulk wet
food waste
15-12-2014
![Page 22: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/22.jpg)
The Proposed Models
• The Integrated MSW management flow diagram for a class of city depicts the four necessary streams of waste collection namely,
• 1) street sweepings, scattered wastes and silt from drains
• 2) construction and demolition (C & D) wastes
• 3) single source bulk wastes collected from market yards, restaurants and canteens, slaughter houses, etc.,
• 4) wet bio-degradable & recyclable fraction from households, institutions & commercial establishments.
22 E
![Page 23: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/23.jpg)
23
Fig-1 Population above 2 Million-
15-12-2014
![Page 24: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/24.jpg)
24
Fig-2 Population of 1 to 2 Million
15-12-2014
![Page 25: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/25.jpg)
25
Fig-3 Population of 1 L to 10 L and hill Stations
Compostable materials
Purchase by kabadiwalas
Feedstock to processing facility (Centralized and / or Decentralized)
Biomethanation
Single or Regional Sanitary Landfilling Facility
Special wastes to
be handled as per SPCB
direction
Secondary storage &
transfer station
Door-to-door collection
Domestic and commercial
waste segregation
Plastics to liquid
fuel
RDF making
Vermi / Conventional Composting
Rejects
Street
sweeping & silt from drains
Construction
and demolition
wastes
Alternate building material
Vermi / Conventional Composting
Bulk
source of recyclabl
e
Decentralized
processing (Biomethan
ation Plant)
Energ y
Manure
Hotel, vegetable market,
restaurant, abattoir
Secondary storage & transfer station
Secondary storage & transfer station
Collection of selected
materials by rag-pickers
Recycling industries
Bulk wet
food waste
15-12-2014
![Page 26: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/26.jpg)
15-12-2014 26
Fig-4 Population of 1 lakh and less
![Page 27: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/27.jpg)
Category Technological Options Justification
15,000 to 50,000
Biomethanation, Vermi / conventional Composting
Biomethanation and / or vermi / conv.composting are ideal for treatment of organic matter. Smaller quantity hence other technologies not feasible.
50,000 to 1 Lakh
Biomethanation, Vermi / Con.Composting RDF as feed stock to Power Plant or
Cement Industry
Biomethanation and / or vermi / conv.composting are ideal for treatment of org. matter. Small quantity of recyclables be converted to RDF as feed stock for power/ cement plant, Plastic to fuel oil
1 Lakh to 1 Million
Integrated Waste Processing Biomethanation and / or vermi / conv. composting + RDF as Feed Stock to power / Cement plant. Plastic to Fuel Oil
Biomethanation and / or vermi / conv.Composting. Waste Quantity not adequate for setting up power plant. Advisable to make RDF as a feed stock for Power / Cement plant. Plastic to fuel oil
1 Million to 2 Milllion
Integrated Waste Processing Biomethanation and / or vermi / conventional composting + RDF.
W to E Plant to be established where wastes exceeds 500 TPD Options: Gasification and Pyrolysis, Incineration and Mass Burning. Plastic to Fuel Oil
Biomethanation and / or vermi / conventional composting tech. ideal for treatment of organic matter. Can set up W to E plant if the quantities o f wastes exceed 500 TPD. Advisable to make RDF if the quantity is less than 500 TPD and use as a feed stock for Power plant / Cement Industry. Plastic to fuel oil
More than 2 Million
Inte. Waste Processing Biomethanation and /or vermi / conv.composting + RDF.
W to E Plant be Established for Power Gen. or RDF be fed to Cement plants Options: Gasification and Pyrolysis, Incineration and Mass Burning. Plastic to Fuel Oil
Biomethanation and / or vermin / conventional composting technologies are appropriate for treatment of organic matter. It is ideal to set up large W to E plants as the quantities exceed 500 TPD. Plastic to fuel oil
HillTowns Biomethanation and / or vermi / conventional composting / RDF as feed stock. Plastic to Fuel Oil
Biomethanation and / or vermi / conventional composting tech. ideal for treatment of org. matter . Quantity of recyclable wastes is higher in hills an d can be converted to RDF for use as feed stock for power or cement industry. Plastic to fuel oil.
15-12-2014 27
![Page 28: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/28.jpg)
The Proposed Models
28
Type of processing plant Indicative number of
plants
Waste to be treated (in TPD)
Cumulative power/ energy
generation
Cumulative estimated compost
generation
Recyclable waste available to recycling industries through rag pickers
17,000
Biomethanation plants (decentralized/ 1 to 20 TPD capacity
7,935 18,590 72 MW 1,260 TPD
Vermi compost/compost plants (decentralized as well as centralized plants) +RDF separation
7,935 59,020 Nil 14,755 TPD
Power plants based on combustible/ RDF produce @ 1 plant per 500 TPD RDF
66 32,890 329 MW
Establishment of MSW based power plants by 2030
172 85,514 855 MW
Establishment of MSW based power plants by 2050
447 2,22,336 2,223 MW
Estimated Waste to Energy Processing Facilities
For more details see page 54 of the report 15-12-2014
![Page 29: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/29.jpg)
15-12-2014 29
Sanitary landfill is an essential component of waste
management chain where inert wastes such as street
sweepings, silt from the surface drains and residual
waste from the processing plants are to be disposed.
The percentage of inerts and residual waste currently
required to be disposed off in sanitary landfills in the
country is around 25% of the MSW generation – which
will progressively reduce with improvement in waste
management system. Landfill requires professional
management ,heavy machinery and regular monitoring
to safeguard the environment.
Common Regional Sanitary landfills
![Page 30: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/30.jpg)
Recommendation:-Policy
30
1. A national policy on “Recycling, Resource Conservation and Preventive Environmental Management” be notified,
2. A performance based viability gap funding for waste processing projects be made available.
3. A performance based incentives in the field of environment and waste management for rewarding excellence be initiated and implemented.
4. An action plan to implement specific recommendations made for waste sector in the National Environment Policy needs to be prepared and persued.
15-12-2014
![Page 31: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/31.jpg)
Recommendations :- R & D for Appropriate Technologies
31
�Indian Institute of Technologies (IITs) and leading
scientific institutions be encouraged to take up research projects and programs in MSWM sector, including recycling processes
�At least four institutions be identified one each in north, south, east and west where Centre of Excellence can be set up with Government of India and CSR support.
15-12-2014
![Page 32: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/32.jpg)
Decision Support System for Sustainable ISW Management
(DSS –ISWM)
Dr Indrani Chandrasekharan
Formerly Adviser, Planning Commission,
and
Senior Partner, ERC Consultants, New Delhi
![Page 33: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/33.jpg)
DSS for ISWM
• Decision Support Systems (DSS) are a specific class of
computerized information system that supports
decision making activities in a structured and logical
way based on scientific facts. It compiles useful
information from raw data, documents ,personal
knowledge and/or business models to identify and
solve problems and suggest appropriate decisions.
• The biggest benefit being reduction in time taken in
decision making.
• Adoption of sustainable process, technology and
smart review
![Page 34: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/34.jpg)
DSS for ISWM
• The DSS for Sustainable ISWM has to be designed to aid solid waste planners in evaluating the cost and environmental aspects of integrated municipal solid waste management strategies.
• The tool should enable users to simulate existing MSW management practices and conduct scenario analyses of new strategies based on cost and environmental objectives.
• The DSS –ISWM should include multiple design options for waste collection, transfer, materials recovery, composting, waste-to-energy, and landfill disposal.
![Page 35: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/35.jpg)
DSS for ISWM
• The DSS-IMSW should enable identifying and evaluating cost and environmental aspects associated with specific waste management strategies or existing systems.
• It should also identify costs and environmental aspects of proposed strategies such as those designed to meet recycling and waste diversion goals, quantify potential environmental benefits associated with recycling, identify strategies for optimizing energy recovery from MSW, and evaluate options for reducing greenhouse gases, air pollutants, and environmental releases to water-bodies or ecosystems
![Page 36: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/36.jpg)
DSS for ISWM
• A review of the municipal solid waste management and planning literature reveals except for complex mathematical models elsewhere and DSS for sanitary landfills for India, a comprehensive DSS-IMSW is non existent. Discussions with practising waste management professionals indicated a general interest in, but lack of practical applications of, mathematical modelling techniques.
• The creation of knowledge-based systems to interface with individual MSW management and planning models, or assist with model selection and integration is need of the hour.
![Page 37: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/37.jpg)
DSS for ISWM
To demonstrate the validity of the suggested decision support approach;
• A prototype decision support system needs to be developed to assist with the preliminary planning of ISW management systems.
• This planning tool should combine knowledge-based system components with spread sheet, optimization and stimulation models to assist with: waste forecasting; technology evaluation; recycling and composting programme design; facility sizing; location and investment timing; waste allocation; and MSW management system analysis using stimulation
![Page 38: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/38.jpg)
Status of DSS for ISWM
Around the world including India significant attempts have been made to apply the concept and models in different sectors of MSWM and at several locations.
The approach made so far by many researchers in DSS modelling is to isolate a few key factors that have a significant influence on the DSS.
A holistic approach with a thorough understanding of the complex elements involved in MSWM is absolutely essential for designing and executing a sustainable DSS-ISWM model.
![Page 39: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/39.jpg)
Elements in the construction of a S -DSS for ISWM
• Municipal Solid Wastes (Management and Handling) Rules, 2000 of Government of India puts the whole process of MSWM under six broad parameters and suggest compliance criteria for each of them.
• Schedule II defines these parameters as: collection, segregation, storage, transportation, processing and disposal; and prescribes procedures for compliance of each parameter.
• Schedule III of the said rule gives specifications for landfill and demands compliance in terms of site selection, facilities at the sites, specifications for landfilling, pollution prevention, water quality monitoring, ambient air quality monitoring, plantation at site, closure of landfill site and post closure care.
• Similarly, Schedule IV provides standards for composting, treated leachate and incineration.
![Page 40: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/40.jpg)
A Decision Support System (DSS) for IMSW
Components of the MSW DSS include:-
- Process models
- Mass flow models
- Optimization routine
- User interface
Shantanu Roy, EMC 40
![Page 41: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/41.jpg)
A Decision Support System (DSS) for IMSW
• Type of questions answered
What are the cost and environmental benefits of the system
Selected.
Which plan, strategy fits
What are trade offs current systems and recommended
Shantanu Roy, EMC 41
![Page 42: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/42.jpg)
A Decision Support System (DSS) for MSW
42
++++++++++
State of Art Computing
Technology
Planning for
Sustainable and Integrated
Solid Waste Management
and Decisions making.
Sound
Science
![Page 43: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/43.jpg)
A Decision Support System (DSS) for MSW
Decisions being evaluated
43
![Page 44: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/44.jpg)
Shantanu Roy, EMC 44
12th May, 2014
![Page 46: Sustainable Integrated MSW Management including DSS Speaker PPTS/Day 2/Session 2x... · 2014-12-15 · Integrated Solid Waste Management (ISWM) Plan. • There are conflicting data](https://reader033.vdocuments.mx/reader033/viewer/2022050203/5f56d6e55a35dd4aeb13a2b6/html5/thumbnails/46.jpg)
Shantanu Roy, EMC 46