PART 3: PRELIMINARY TIME MANAGEMENT
Preliminary time management is a process of planning, controlling and executing the project so that the
project is managed in a proper effective way to get the desired outcome. We do have different methods
of implementing a certain project and for this particular project we are following the following tools and
techniques to execute the time management strategy.
ACTIVITY LIST AND ATTRIBUTES:
Activity List and attributes generally deals with the tasks that should be followed by each activities
resource requirements, constraints and the relationship between each activity. The sample of Activity
List and Attributes assisted from the WBS for the initiation and site Mobilization of the project has been
shown below.
Project Name: Borroloola Trade Training Centre
WBS Item Number: 1.1
WBS Item Name: Initiating
Predecessors: none
Successors: 1.2 Site constructions
Logical Relationship: Finish to Start
Leads and Lags: none
Resource Requirements: Contractor, stakeholders and project manager
Constraints: none
Assumptions: Mutual agreement and negotiation between stakeholder and contractor should be made in presence of an authorized body to
start the project.
WBS Item Number: 1.2
WBS Item Name: Site Construction
Predecessors: 1.1 Initiating
Successors: 1.2.1 Site Mobilization
Logical Relationships: Finish to Start
Leads and Lags: none
Resource Requirements: Project Manager, Civil Engineer, Mechanical Engineer, Architecture
Constraints: none
Assumptions: Construction should be on time within the stipulated Budget with a regular inspection.
MILESTONE LIST
The series of works as milestones has been given below projecting the completion dates:
-
7/21/2019 SUSHOVIT Project Time Management
2/4
Milestones Deliverables Completion date
Negotiation Stakeholder, Contractor, Project Manager 01-01-2016
Sign Agreement Stakeholder, Contractor, Project Manager 01-01-2016
Site Mobilization Project Manager and Administration Team 25-02-2016
Detail Design Design Team 05-05-2016
Site Clearance Construction Team/Quality Control Team 05-06-2016
Excavation Construction Team/Quality Control Team 05-07-2016
Installation works Construction Team/Quality Control Team 10-09-2016
Concrete works Construction Team/Quality Control Team 29-09-2016
Curing works Construction Team/Quality Control Team 10-10-2016
Backfill and Sanding
works
Construction Team/Quality Control Team 25-11-2016
Final Taking Over Quality Control Team/Stake holder 30-12-2016
Project Completed Project Manager, Contract Management Team, Stake
holder
01-01-2017
NETWORK DIAGRAM:
The following diagram shows the sequence of events and process to be followed for project scheduling.
It generally is the schematic display of logical relationships or sequencing of the project activities.
-
7/21/2019 SUSHOVIT Project Time Management
3/4
Repairing and taking over
Site Mobilization
Site Clearance
Project completed
Detail design Concrete Works
Reinforcing steel, M and E
Installation and formwork
Excavation Work Curing Works
ACTIVITY RESOURCE REQUIREMENT
The following table shows the list resources and times required to complete each activity listed.
Activity Skills
needed
Deliverables Working
days
Start date End date
Construction
Drawing and
site clearing
Civil
Engineer,
Architecture
DST 61 25/02/2016 25/04/2016
Demolish
and site
Clearing
Civil
Engineer
CST,QCT,CTT 22 26/04/2016 17/05/2016
Excavation Civil
Engineer,
Mechanical
Engineer
,Heavy
Equipment
Driver
CST,QCT,CTT 20 18/05/2016 06/06/2016
InstallationM and E
prior
concrete
Works
CivilEngineer,
Mechanical
Engineer,
Heavy
Equipment
driver
CST,QCT,CTT 43 07/06/2016 19/07/2016
Concrete Civil CST,QCT,CTT 52 20/07/2016 09/09/2016
1
2
3
5
6
8
47
9
-
7/21/2019 SUSHOVIT Project Time Management
4/4
Works Engineer,
Mechanical
Engineer,
Heavy
equipment
driver
Curing
Works
Civil
Engineer
QCT,CTT 41 09/10/2016 18/11/2016
Back Filling
And Sanding
Civil
Engineer,
Heavy
Equipment
Driver
CST,QCT 33 19/11/2016 21/12/2016
Repairing
Works and
taking over
Civil
Engineer,
Quality
Controller
CST,QCT 11 22/12/2016 1/1/2017
ACTIVITY DURATION
The Duration for each activity to be sequenced in a project has been briefly shown in the
Activity Resource Requirement list but the exact duration for different activity can be found by
the PERT weighted average formula given as follows:
PERT weighted average= (optimistic time+4*Most likely Time+ Pessimistic)/6
PROJECT SCHEDULE
For the Project schedule of each activity in the project, a Gantt chart has been made which has
been shown in the next part.