Inspection Report
Rig C
Date of Inspection: Friday 19th July 2013
-
8/12/2019 Survey Report Rig C (3)
2/30
Inspected & Prepared by:
Mr Ho Heen Wu
Qualifications: Marine Chief Engineer, 1st Class M.O.T. Competency
Past Experiences: Chief Engineer Technical Superintendent Senior Technical Superintendent Head of Technical Department/Senior Technical Manager (19 bulk
carriers) Head of Technical Department/Senior Technical Manager (23 container
vessels)
Mr Lim Chin Hong
Qualifications: Marine Chief Engineer, 1st Class M.O.T. Competency Diploma of Management
Past Experiences: Chief Engineer, Foreign Going Vessels Guarantee Engineer Engineering Manager Managing Director
Awards & Affiliations: Council Member: Royal Institute of Naval Architects & Institute of Marine Engineering,
Science & Technology (South East Asian branch).
Assitants:Mr Wilson Lim - BSc BiotechnologyMr Hanafi - Welding superintendent/welder 6G
-
8/12/2019 Survey Report Rig C (3)
3/30
General Info
Vessel Type: Midwater Floater / Semi-submersible drill rig
Year Built: 1976, upgraded 1996,
Flag: Panama
Lightship Weight: 10,000 tonnes
Length: 355ft / 108mBreadth: 220ft / 67m
Depth: 120ft / 37m
Draft: 70ft / 21m
Transit Draft: ~ 20ft / 7m
Height of Derrick From Platform: 185ft / 56m
-----------------------------------------------------------------------------------------------------------------------------
Condition Report
General Condition
- Sub-average condition,- Rust has penetrated most of the top deck surface- Some outdoor equipment are wrapped neatly in thick canvas, reduces weathering- Others are left exposed to harsh sea conditions.- 2 elevator units inside each main leg
- GA not available- Sounding test approx 500 litres of diesel in day tanks- 40 tonnes of engine oil remaining in tanks
-
8/12/2019 Survey Report Rig C (3)
4/30
Derrick- Overall structure shape is good- Superficial rust spots present
-
8/12/2019 Survey Report Rig C (3)
5/30
Drawworks- Intact in good condition, covered in canvas- Did not run operational test
Rotary Table / Bushings- Rotary table covered underneath wooden panels- Bushings kept in workshop
-
8/12/2019 Survey Report Rig C (3)
6/30
Top Drive & Traveling Blocks- Top drive not on rig- Traveling block are intact, hanging uncovered on derrick rails
BOP System- Not found on rig
Compensators - Present, in good condition
-
8/12/2019 Survey Report Rig C (3)
7/30
Anchor Winches- 4 units total- Covered partially under canvas- Poor but working condition- Each winch operates two warping heads- Warping heads in poor condition
-
8/12/2019 Survey Report Rig C (3)
8/30
Anchors- All 8 anchors are being used
Anchor Chasers- Chasers N/A
-
8/12/2019 Survey Report Rig C (3)
9/30
Main Deck Cranes- One unit- Old design, 1960's built- Good physical condition, should work fine.- Reportedly been used recently- Control room in good order.- 56tonnes @ 40ft
-
8/12/2019 Survey Report Rig C (3)
10/30
Secondary Cranes- One unit intact, good condition.- 52 tonnes @ 30ft
Lightweight Deck Davits- 2tonne max
-
8/12/2019 Survey Report Rig C (3)
11/30
Lifeboats & Davit system- 3 main boats in good order- Davit seems worn & rusted
Helideck & Refueling system- Deck in good condition- Water puddle indicates less than flat surface- Refueling system intact
-
8/12/2019 Survey Report Rig C (3)
12/30
Mud Pumps- 3 units- Good condition
-
8/12/2019 Survey Report Rig C (3)
13/30
Main Engine- 4 units @ 1.5 megawatts per unit- Good condition- Good, more modern design- Some spare cylinders
-
8/12/2019 Survey Report Rig C (3)
14/30
Backup Emergency Generator
- 1 Unit, cummins- Excellent condition- Newer design
Thrusters & DP system- 4 Thrusters- For propulsion only, no DP system- Unable to view as elevator to pontoon offline
Fuel Pumps
-
8/12/2019 Survey Report Rig C (3)
15/30
Shale Shakers- All 4 units not on rig
Lathe Machine & Milling Stand
- 1 unit each- Great condition
-
8/12/2019 Survey Report Rig C (3)
16/30
Air-Conditioning Compressors
Drill string compensator's Air Compressors- 4 units, in good condition
-
8/12/2019 Survey Report Rig C (3)
17/30
Cement Tanks- 4 units
-----------------------------------------------------------------------------------------------------------------------------
Equipment & Spares
Parts Warehouse- Locked, no access
Workshop- Painting equipment, several units- Welding genset, 2 units- Heavy tools- High pressure water jet- Welding rods
-
8/12/2019 Survey Report Rig C (3)
18/30
-
8/12/2019 Survey Report Rig C (3)
19/30
Spare Winches
Spare Electric Motors
-
8/12/2019 Survey Report Rig C (3)
20/30
Chain blocks
Forklift- 1 unit- 3 tonne lift- Poor condition
-
8/12/2019 Survey Report Rig C (3)
21/30
Spare Cables, hoses & wire ropes- Good condition- Kept sheltered- Several spools each
-
8/12/2019 Survey Report Rig C (3)
22/30
-
8/12/2019 Survey Report Rig C (3)
23/30
-
8/12/2019 Survey Report Rig C (3)
24/30
Iron Roughneck- One unit- Good condition
-
8/12/2019 Survey Report Rig C (3)
25/30
Fire Extinguishers - Intact, expired
Accomodation Units- Hundreds of mattresses & pillows- Desks & swivel chairs- Computers & flatscreen monitors in good shape- Desktop printers & print stations- Heavy duty washing machine & dryers- Pantry with stoves, ovens, refrigerator units & utensils
-
8/12/2019 Survey Report Rig C (3)
26/30
-
8/12/2019 Survey Report Rig C (3)
27/30
-
8/12/2019 Survey Report Rig C (3)
28/30
Recreational Units- No TV- Library of books- Gym room in bad shape.
-
8/12/2019 Survey Report Rig C (3)
29/30
MISC Items & Pictures
-
8/12/2019 Survey Report Rig C (3)
30/30