Supply Measure ProjectsSouth Australia
Diane FavierMurray-Darling Basin Policy and Strategy
Department for Environment and Water
June 2018
![Page 2: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/2.jpg)
Supply Measures
• Proponent for five projects• Co-proponent for seven projects
– The Living Murray projects– Enhanced Environmental Water Delivery
project
![Page 3: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/3.jpg)
South East Flows
Chowilla Floodplain
Riverland Floodplain
SARFIIP
Riverine Recovery Project
Flows for the Future
SA River Murray
Constraints
Six projects located in SA
![Page 4: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/4.jpg)
Chowilla Floodplain TLM• Regulating structure and other works on
Chowilla Creek and wetlands (Ramsar site)• Water up to 4,000 ha at flows of 10,000 ML/day • Objectives
– maintain high-value wetlands – maintain the current area of river red gum forest (largest remaining in the Lower
Murray region)– maintain at least 20 per cent of the original area of black box vegetation
• Completed in 2014 and being operated• Community and Indigenous groups input to
management
![Page 5: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/5.jpg)
SLIDES FROM RC Main regulator – Chowilla Creek
![Page 6: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/6.jpg)
Chowilla The Living Murray projectBefore operation
![Page 7: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/7.jpg)
Chowilla The Living Murray projectAfter operation
![Page 8: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/8.jpg)
BEFORE
AFTER
Chowilla Floodplain
![Page 9: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/9.jpg)
Riverine Recovery Project (RRP)• Regulating structures, fishways and operational
changes to return wetlands to more natural wetting and drying
• Water savings transferred to CEWH• Will be completed by end June 2019 • Objectives
– improved management of weir pools, anabranches, floodplains & wetlands– more diverse habitats and productive and diverse plants and animals– reduced impacts of carp
• Landholders, community and Indigenous groups engaged in design and management
![Page 10: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/10.jpg)
Sample of wetland sites
![Page 11: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/11.jpg)
South Australian Riverland Floodplains Integrated Infrastructure Program (SARFIIP)
• Regulating structures, levee banks, and saline groundwater management schemes
• Water at low flows of 10,000-15,000 ML/day• Objectives
– Improve health of the diverse range of terrestrial and aquatic habitats, including Black Box, River Red Gum, Lignum communities and wetlands
• Construction began in 2016 (end date of 2020)• Community and Indigenous groups input to
design and implementation
![Page 12: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/12.jpg)
Pike – Margaret Dowling Regulator
![Page 13: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/13.jpg)
Pike floodplain inundation map
![Page 14: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/14.jpg)
Flows for the Future (F4F)• Supply and install low flow devices on dams
and watercourse diversions in Eastern Mount Lofty Ranges
• Objectives– Reinstate more natural flow patterns– Increase flow to Lower Lakes and Coorong
• Commenced in 2017 (end date of 30 June 2022)• Initial consultation in 2011• Ongoing direct engagement with landholders
![Page 15: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/15.jpg)
Example low flow device
![Page 16: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/16.jpg)
South East Flows Restoration Project
• Extension of the South East drainage system to supply water to South East wetlands and the Coorong South Lagoon
• Objectives– assist salinity management in Coorong South Lagoon,– enhance wetlands in the Upper South East – reduce drainage outflow at Kingston beach
• Construction began in 2017 (end date of 2018)• Community and Indigenous groups input to
design and implementation
![Page 17: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/17.jpg)
![Page 18: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/18.jpg)
Taratap drain before Taratap drain after
Blackford diversion site before Blackford diversion site after
Reference location for before and after
![Page 19: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/19.jpg)
SA River Murray Constraints• Works & measures to enable managed higher
flow events – up to 80,000 ML/day– e.g. crossings, flood proofing assets, easements– 80,000 ML/day at the border inundates 116,117 ha
• Links with NSW and Victorian projects• Objectives
– improve wetland and floodplain health with more frequent over-bank flows between 40,000 to 80,000 ML/day
– reduce inundation risks on low lying areas from natural and managed flows
• Continue to work with private landholders, councils and public land managers
![Page 20: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/20.jpg)
Enhanced Environmental Water Delivery Project (EEWD)• SA, Victoria and NSW • Step-change in forecasting, planning and
coordination of environmental water use• Objective
– optimise benefits from available environmental water– coordinate managed flows and natural inflows & optimise watering with
constraints addressed
• Business case approved• Engage with water holders and managers as well
as communities and Indigenous groups
![Page 21: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/21.jpg)
Enhanced Environmental Water Delivery method
Jun Nov
Low
er
floo
dpla
inIn
ch
anne
l
Jul Aug Sept Oct
Regulated flow boundary (constraint)
River operator
s
Targeted trigger
Flow trigger
![Page 22: Supply Measure Projects South Australia · project. South East Flows. Chowilla Floodplain. Riverland Floodplain. SARFIIP. Riverine Recovery Project. Flows for the Future. SA River](https://reader034.vdocuments.mx/reader034/viewer/2022052009/601ee44ff5c7d04ebf09f40f/html5/thumbnails/22.jpg)
Websites for more information• www.mdba.gov.au/basin-plan-roll-out/managing-
constraints• https://www.environment.sa.gov.au/topics/river-
murray/basin-plan/adjustment-to-the-sustainable-diversion-limit