Page 1: SUMMARY OF CONSTRUCTION PROJECTS...SUMMARY OF CONSTRUCTION PROJECTS LONOKE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project Totals

Program Management LonokeFebruary 10, 2021

Page 2: SUMMARY OF CONSTRUCTION PROJECTS...SUMMARY OF CONSTRUCTION PROJECTS LONOKE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project Totals

SUMMARY OF CONSTRUCTION PROJECTS

LONOKE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

Estimated or

- PE OnlyNorth Terminal – Tennessee Line P.E. 40

Addt'l Rte.-Sec.: Various

$269,42141 Completed - $1,885,947001726*

- PE OnlyHwy. 67 – Hwy. 25 P.E. 5

Addt'l Rte.-Sec.: Cleburne 5-15; White 5-13/14

- 12 Programmed - - 001748*

Safety ImprovementsNo. Little Rock – St. Francis Co. Ln. (Sel. Secs.)

(Cable Median Barrier) (S)

16.7240

Addt'l Rte.-Sec.: Monroe 40-43; Prairie 40-42; Pulaski 40-33

$2,430,62841 Completed Feb. 2013 Sep. 2013 41.68 $6,076,570012177

Safety ImprovementsCabot – Bald Knob (Sel. Secs.) (Cable Median Barrier) (S) 9.3767

Addt'l Rte.-Sec.: White 67-12/13

$1,354,88311 Completed Apr. 2013 Aug. 2013 39.19 $5,645,347012179

Safety ImprovementsDistricts 2, 6, 7 & 8 Pavement Friction Impvts. (Sel. Secs.) (S) 0.775

Addt'l Rte.-Sec.: Various

$339,87412 Completed Jan. 2018 Oct. 2018 6.10 $2,692,508012296

- Structures & ApproachesCypress Bayou Strs. & Apprs. (S) 67

Addt'l Rte.-Sec.: White 67-12

$1 - $5 M11 Scheduled Sep. 2022 - $5 - $10 M012328

- Bridge RehabilitationDistricts 1, 2 & 6 Bridge Preservation (2021) (S) 5

Addt'l Rte.-Sec.: Various

< $1 M12 Scheduled May. 2021 - $1 - $5 M012375*

Interchange ImprovementsI-40/Hwy. 89 Intchg. (Lonoke) (S) 1.0840

Addt'l Rte.-Sec.: Lonoke New

$7,888,41041 Completed Jan. 2013 Dec. 2014 1.08 $7,888,410060897

Major WideningHwy. 89 – Hwy. 319 (S) 5.495 $30 - $40 M12 Programmed 5.49 $30 - $40 M060906

ShouldersHwy. 89 & Hwy. 89 Spur Shldrs. Const. (Lonoke Co.) (S) 7.5489

Addt'l Rte.-Sec.: Lonoke 89-1S

$1 - $5 M1 Programmed 7.54 $1 - $5 M061056*

- Interchange ImprovementsHwy. 67 Interchange (N. of Cabot) (S) 67 $25,525,89411 Sub. Completed Dec. 2016 Mar. 2019 - $25,525,894061102

Major WideningI-40 – South (Carlisle) (S) 0.4213 $1,693,33310 Completed Oct. 2011 Jul. 2012 0.42 $1,693,333061215

Safety ImprovementsHwy. 67 Cable Median Barrier (Jacksonville-Cabot) (S) 0.7467

Addt'l Rte.-Sec.: Pulaski 67-10

$189,00211 Completed Feb. 2011 Jun. 2011 4.90 $1,260,016061219

- Roadside AppurtenancesKerr Park Trail (S) $93,039Completed Oct. 2009 Jul. 2014 - $93,039061221*

- PE OnlyRedmond Rd. – Cabot (Widening) P.E. 67

Addt'l Rte.-Sec.: Pulaski 67-10

- 11 Programmed - - 061261*

- Safety ImprovementsHwy. 367/Locust St. Signal (Cabot) (S) 367

Addt'l Rte.-Sec.: Lonoke CS

$203,52514 Completed Sep. 2010 Apr. 2011 - $203,525061268

- Roadside AppurtenancesLonoke SRTS I (2010) $85,775Completed Jun. 2012 Nov. 2012 - $85,775061289*

- Roadside AppurtenancesWard SRTS I (2010) $86,126Completed May. 2012 Jun. 2013 - $86,126061290*

Program Management LonokeFebruary 10, 2021

* Job not shown on county map.

Page 3: SUMMARY OF CONSTRUCTION PROJECTS...SUMMARY OF CONSTRUCTION PROJECTS LONOKE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project Totals

SUMMARY OF CONSTRUCTION PROJECTS

LONOKE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

Estimated or

ResurfacingFour Mile Cr. – North & South (Overlay) (S) 2.005 $325,36812 Completed Apr. 2011 Oct. 2011 2.00 $325,368061305

ResurfacingHwy. 294 – East (Lonoke) (Overlay) (S) 3.0070

Addt'l Rte.-Sec.: Lonoke 70-15

$672,68314 Completed Apr. 2011 Oct. 2011 3.00 $672,683061308

- EnhancementCabot Hwy. 89 Streetscaping (ATEP-11) (S) $724,771Completed Mar. 2014 Apr. 2015 - $724,771061320*

- EnhancementKohen's Park Trail (Lonoke Co.) (S) < $1 MProgrammed - < $1 M061339*

Safety ImprovementsHwy. 367/Hwy. 38 Signal & Inters. Impvts. (Cabot) (S) 0.3438

Addt'l Rte.-Sec.: Lonoke 367-14

$663,3730 Completed Feb. 2014 Oct. 2014 0.34 $663,373061384

ResurfacingLonoke – West (Overlay) (S) 7.2170 $1,005,47814 Completed Apr. 2013 Aug. 2013 7.21 $1,005,478061396

ResurfacingHwy. 165 – Hwy. 70 (Overlay) (S) 10.9315 $1,469,81110 Completed Jun. 2013 Oct. 2013 10.93 $1,469,811061406

- Roadside AppurtenancesCabot SRTS I (2012) $366,401Completed Aug. 2014 Aug. 2015 - $366,401061410*

RehabilitationHwy. 67 Interim Pvmnt. Impvts. (Jacksonville-Cabot) (S) 0.7167

Addt'l Rte.-Sec.: Pulaski 67-10

$315,12011 Completed Jun. 2014 Mar. 2015 6.69 $2,864,728061424

ResurfacingHwy. 70 – I-40 (Overlay) (S) 2.7615 $464,12911 Completed Feb. 2014 May. 2014 2.76 $464,129061427

- RR Crossing

Safety Improvements

Hwy. 319 RR Sig. Upgrade & Traffic Sig. (Ward) (S) 319

Addt'l Rte.-Sec.: Lonoke 367-14, CS

$1,017,9451 Under Construction Nov. 2020 Late 2023 - $1,017,945061457

ResurfacingFuntastic Dr./Odom Blvd. East & West (Hwy. 321) (Cabot) (S) 0.19321 $127,4191 Completed Aug. 2016 Oct. 2016 0.19 $127,419061461

ResurfacingFurlow – North (Overlay) (S) 8.4389

Addt'l Rte.-Sec.: Lonoke 236-1

$1,393,1861 Completed Mar. 2016 Dec. 2016 8.43 $1,393,186061463

- Structure & ApproachesHwy. 161 Str. & Apprs. (Pulaski & Lonoke Cos.) (S) 161

Addt'l Rte.-Sec.: Pulaski 161-5

- 5 Programmed - - 061472

- Structure & ApproachesHwy. 165 Str. & Apprs. (Lonoke Co.) (S) 165 - 8 Programmed - - 061473

- EnhancementWard Sidewalks (Ph. III) (SRTS-15) (S) < $1 MProgrammed - < $1 M061480*

- EnhancementHwy. 89 Streetscaping (Ph. 2) (Cabot) (TAP-15) (S) $362,248Under Construction Jul. 2017 - $362,248061487*

Major WideningHwy. 367 – Hwy. 89 (Cabot) (S) 3.23321 $24,171,5721 Under Construction Jul. 2019 Early 2022 3.23 $24,171,572061509

ResurfacingHwy. 5 – White Co. Line (S) 9.51367 $1,873,47614 Completed Feb. 2017 Oct. 2017 9.51 $1,873,476061512

ResurfacingHwy. 321 North & South (Cabot) (S) 1.3089 $370,6141 Completed Feb. 2017 Nov. 2017 1.30 $370,614061516

ResurfacingHwy. 13 – Screeton (S) 2.9770

Addt'l Rte.-Sec.: Prairie 70-16

$664,40615 Completed Jan. 2017 Nov. 2017 4.35 $973,121061529

- EnhancementFirst St. Sidewalks (Cabot) (S) $164,460Under Construction Oct. 2017 - $164,460061548*

ReconstructionHwy. 89 – White Co. Line (S) 6.3867 $50 - $75 M11 Programmed 6.38 $50 - $75 M061549

Program Management LonokeFebruary 10, 2021

* Job not shown on county map.

Page 4: SUMMARY OF CONSTRUCTION PROJECTS...SUMMARY OF CONSTRUCTION PROJECTS LONOKE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project Totals

SUMMARY OF CONSTRUCTION PROJECTS

LONOKE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

Estimated or

- EnhancementLonoke School Sidewalks (TAP-17) (S) $344,203Completed Oct. 2019 Jul. 2020 - $344,203061564*

- EnhancementLonoke Rail – Trail (RTP-17) (S) $97,917Completed Nov. 2018 Jun. 2019 - $97,917061567*

SealingDistrict 6 Sealing Program (2018) (S) 4.4031

Addt'l Rte.-Sec.: Various

$54,9922 Under Construction 89.67 $1,120,712061575*

- Safety ImprovementsCabot Traffic Ops. Impvts. (S) 89 $369,8641 Under Construction Dec. 2020 - $369,864061576

ResurfacingHwy. 367 – White Co. Line (Sel. Secs.) (S) 7.015 $1 - $5 M12 Scheduled 2022 7.01 $1 - $5 M061591

Structure & ApproachesMill Creek Str. & Apprs. (S) 0.0238 $1 - $5 M0 Scheduled Apr. 2021 0.02 $1 - $5 M061609

Structure & ApproachesI-40 Str. & Apprs. (Hwy. 15) (S) 0.4015 $5 - $10 M11 Scheduled Feb. 2021 0.40 $5 - $10 M061610

- Structures & ApproachesI-40 Strs. & Apprs. (Hwys. 13 & 31) (S) 13

Addt'l Rte.-Sec.: Lonoke 31-3

$1 - $5 M10 Scheduled Apr. 2022 - $1 - $5 M061613

- EnhancementCabot Central Elementary SRTS Sidewalks (S) New $165,928Under Construction May. 2019 - $165,928061617*

PE OnlyHwy. 5 – Hwy. 89 (Cabot) P.E. 3.2467 - 11 Programmed 3.24 - 061631*

ResurfacingPulaski Co. Line – Monroe Co. Line (Sel. Secs.) (S) 19.8370

Addt'l Rte.-Sec.: Lonoke 70-15; Prairie 70-16

$4,791,96914 Under Construction Nov. 2020 Late 2021 37.65 $9,098,216061634

ResurfacingHwy. 161 – Hwy. 31 (S) 11.1740

Addt'l Rte.-Sec.: Pulaski 40-33

$5 - $10 M41 Scheduled Jun. 2021 18.60 $10 - $15 M061685

ResurfacingHwy. 31 – Prairie Co. Line (S) 10.5740 $5 - $10 M41 Scheduled 2021 10.57 $5 - $10 M061687

- EnhancementLincoln St. Sidewalk (Lonoke) (S) < $1 MProgrammed - < $1 M061697*

- EnhancementCabot Central Elementary SRTS Sidewalks Ph. 2 (S) < $1 MProgrammed - < $1 M061703*

ResurfacingWard – Faulkner Co. Line (S) 10.85319 $1 - $5 M2 Scheduled Apr. 2021 10.85 $1 - $5 M061721

ResurfacingPine Terrace Dr. – Lincoln St. (Cabot) (S) 1.9289 < $1 M1 Scheduled Feb. 2021 1.92 < $1 MA60003

ResurfacingLonoke Overlay (Sel. Secs.) (S) 2.80CS $284,782Completed Jul. 2014 Nov. 2014 2.80 $284,782C43001*

ResurfacingKeo Pecan St. Recsont. & Overlay (S) 0.98 $144,839Completed Apr. 2015 Jul. 2015 0.98 $144,839C43002*

ResurfacingCarlisle & Humnoke Overlay (Sel. Secs.) (S) 3.42CS $368,065Completed Feb. 2017 May. 2017 3.42 $368,065C43003*

- ResurfacingAustin Overlay (Sel. Secs.) (S) CR $561,523Completed Aug. 2017 Feb. 2018 - $561,523C43004*

ResurfacingEngland Overlay (Sel. Secs.) (S) 1.95CS $344,170Completed Apr. 2018 Sep. 2018 1.95 $344,170C43006*

ResurfacingAllport Overlay (Sel. Secs.) (S) 1.70CS $208,285Completed Feb. 2019 Jul. 2019 1.70 $208,285C43007*

- ResurfacingCabot & Maumelle Overlay (S) CS

Addt'l Rte.-Sec.: Pulaski CS

$628,597Completed Sep. 2014 Dec. 2014 - $991,896C76015*

ResurfacingWard and McRae Overlay (Sel. Secs.) (S) 2.55 $234,382Completed Apr. 2015 Jul. 2015 4.37 $468,764C76019*

Program Management LonokeFebruary 10, 2021

* Job not shown on county map.

Page 5: SUMMARY OF CONSTRUCTION PROJECTS...SUMMARY OF CONSTRUCTION PROJECTS LONOKE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project Totals

SUMMARY OF CONSTRUCTION PROJECTS

LONOKE COUNTYCounty Totals

CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date

Project Totals

CostLength (Mi)

Sub. Comp.

Estimated or

Major WideningVandenberg Blvd. – Hwy. 5 (Widening) (S) 0.5467

Addt'l Rte.-Sec.: Pulaski 67-10

$9,511,72511 Completed Dec. 2016 May. 2019 4.60 $79,264,377CA0605

Major WideningJacksonville - Cabot (Widening & lntchng. lmpvts.) (Sel. Secs.) (F) 3.2467

Addt'l Rte.-Sec.: Pulaski 67-10

$100 - $125 M11 Scheduled Nov. 2021 5.23 $175 - $200 MCA0613

ResurfacingHwy. 89-Hwy. 31(S) 6.18236 < $1 M1 Programmed 6.18 < $1 MR60102

- PE OnlyHwy. 63 – East City Limits England (PE) 165

Addt'l Rte.-Sec.: Arkansas 165-6; Prairie 165-7

- 8 Programmed - - RX0022*

ResurfacingCo. Rd. 63-Hwy. 294 (Surfacing) (S) 1.95CR $200,203Completed Jul. 2014 Nov. 2014 1.95 $200,203SA4340*

ResurfacingLonoke County Overlay No. 14 (Sel. Secs.) (S) 4.27CR $456,676Completed Jul. 2015 Nov. 2015 4.27 $456,676SA4341*

ResurfacingHwy. 165-Hwy. 31 Overlay (Sel. Secs.) (S) 4.16CR $536,307Completed Jun. 2016 Oct. 2016 4.16 $536,307SA4342*

- ResurfacingHwy. 5 - Hwy. 319 (Overlay) (S) CR $573,634Completed Jul. 2017 Feb. 2018 - $573,634SA4343*

ResurfacingCo. Rd. 348 Overlay (S) 2.13CR $656,692Completed Jun. 2019 Oct. 2019 2.13 $656,692SA4344*

$242,566,132177.54Totals For All Projects In Lonoke County