suds management at glenconway windfarm · toolbox talks •every tuesday
TRANSCRIPT
SuDs
• Gael Force Renewables Ltd was formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target onshore Wind Farm opportunities in GB & ROI.
SuDs
Gael Force Renewables – What We Do:
• 150 years of Civil Engineering Experience
• Gael Force offer full Design and Build Services
• Early client and designer involvement so that innovative, safe, buildable solutions are developed. • At Gael Force we implement lessons learnt to ensure our teams constantly progress, develop and
refine skills, methodologies and work sequences
• Full time on site Environmental Professionals
SuDS
Monitoring Effectiveness
• Water Quality testing (internal & external) • External inspections by Designers • Internal weekly inspections by
Environmental Representative • SEARS (Safety Environmental Awareness
Reporting Scheme). Positive and Negative issues raised by everyone on site.
SuDS
Water Quality Testing
• External water quality testing was carried out every two weeks at 5 locations for Phase 1 and 8 locations for Phase 1 & 2
• Testing covered 21 chemical parameters and biological (macro invertebrate) monitoring
• Internal samples took place daily for phase 1 and weekly for phase 2. Parameters included turbidity, dissolved oxygen, pH, temp & EC.
SuDS
Environmental Awareness
• Water Quality results are displayed on site
• Correlation between turbidity and rainfall is also presented on graphs.
SuDS
Toolbox Talks
• Every Tuesday morning
• Covers key issues such as waste, energy, water pollution
• All site staff shared the responsibility
SuDS
Environmental Coaching
Environmental Sessions to date:-
SuDS (McCloys) Peat Stability / Peat Slides (BLP) Archaeology (Gahan & Long) Flora and Fauna (Blackstaff)
SuDS
Conclusion
• SuDS design must account for inclement weather conditions
• SuDS design must be site specific • SuDS features must be installed prior to works
starting • Very beneficial to have an on site environmental
representative • Water Quality monitoring is important during
construction – even visual inspection of water courses
• Maintenance of SuDs Features is critical
Construction Context
• 3.67km carriageway realignment and upgrade: include earthworks, drainage and culverts, utility works, surfacing & underpass construction
• Existing drainage mitigation inadequate
• Filter drains & 4 balancing ponds with reed beds
Key Environmental Aim
‘Protecting the Pow Water tributaries during construction’
Challenges & Uncertainties
• Geology & soils
Earthworks intensive
EIA stated ‘potentially increased sedimentation’
True nature of soils
• Temporal Constraints
Not scheduled in programme of works
Resources to complete with immediate effect
Costs
Usual Suspects
Exposed soils: ensuring capping/seeding is completed ASAP
Stockpiles: limiting, stabilising
Washing & washout facilities
Haul roads: wheel wash operative (spatial constraints)
Dewatering: sumps, releasing at suitable times
Inclement weather: be prepared
Water Management Strategy Liaise with local SEPA representative
Alum sulphate required: minimal dosing policy
Tiered, impermeable treatment zones
Maintenance plan: Daily checks
pH (6-8) & turbidity (<10ntu) testing
Controlled release
Permanent Pond Installation
• Isolated pond • Limited opportunity for
treatment • Use of existing vegetation
• Lined sediment forebay • Aquatic bench in
permanent pool; ecology, amenity & safety
Native Species Planting Pond Edge Mix
Yellow Flag Iris
Water Avens
Benefits of bio-retention and enhanced biodiversity
Meadowsweet
Learning Points Detailed pre-construction review of EIA
Robust planning, management & maintenance required
Micro-managed retention & release
Maximise use of sub-catchments in design