CONSTRUCTION COST ESTIMATE FORPROJECT : SSMB-298-3450-2012
TTG PROJECT TEAM
Tim Beverage - Spring 2013
Tyler Shisler – Spring 2014
Garrett Goebel – Spring 2014
PROJECT OVERVIEW
THIS CONSTRUCTION ESTIMATE ENCOMPASES THE COST FOR ALL CONSTRUCTION MATERIALS, LABOR, AND EQUIPMENT PER THE CONTRACT DRAWINGS FROM DIV. 1 THROUGH DIV. 34.
ADDITIONALLY IT INCLUDES AN ESTIMATE FOR AN ALTERNATE WALL CONSTRUCTION.
TTG
PANEL COST Vs. 12”CMU COSTTTG
PRECAST PANELCOST: $152,376.50
TIME: ~ 5 DAYS TO INSTALL
DIFFERENCE:
$ 50,516.37
~25 DAYS
12” CMU WALLCOST: $101,860.13
TIME: 30 DAYS INSTALL
DIFFERENCE:
$ 50,516.37
~25 DAYS
STRUCTURAL COST
Wall Construction
Material Cost: $187,198.74
Labor Cost: $30,019.44
Equipment Cost: $174.48
Percentage of Total Project Cost: 33.57%
TTG
STRUCTURAL COST
Floor Construction
Material Cost: $13,496.46
Labor Cost: $3,559.17
Equipment Cost: $58.19
Percentage of Total Project Cost: 2.48%
TTG
STRUCTURAL COST
Roof Construction
Material Cost: $79,009.24
Labor Cost: $17,852.56
Equipment Cost: $3,811.73
Percentage of Total Project Cost: 15.77%
TTG
STRUCTURAL COST
Thermal Construction
Material Cost: $17,432.34
Labor Cost: $6,521.26
Equipment Cost: $0.00
Percentage of Total Project Cost: 3.67%
TTG
HVAC COST ESTIMATE
HVAC Construction
Material Cost: $11,705.50
Labor Cost: $2,376.90
Equipment Cost: $0.00
Percentage of Total Project Cost: 2.35%
TTG
PLUMBING COST ESTIMATE
Plumbing Line Construction
Material Cost: $21,879.53
Labor Cost: $18,877.44
Equipment Cost: $0.00
Percentage of Total Project Cost: 4.76%
TTG
Fire Cost
Plumbing Fixtures/ Appliance Construction
Material Cost: $16,423.00
Labor Cost: $1,697.50
Equipment Cost: $0.00
Percentage of Total Project Cost: 2.8%
TTG PLUMBING COST ESTIMATE
ELECTRICAL COST ESTIMATION
Electrical Construction
Material Cost: $21,015.03
Labor Cost: $23,764.24
Equipment Cost: $0.00
Percentage of Total Project Cost: 8.46%
TTG
FIRE COST ESTIMATION
Fire Protection
Material Cost: $447.00
Labor Cost: $0.00
Equipment Cost: $0.00
Percentage of Total Project Cost: .0007%
TTG
ALL OTHER DIVISONS COST ESTIMATE
All Other Construction
Material Cost: $126,557.51
Labor Cost: $54,884.78
Equipment Cost: $38,898.31
Percentage of Total Project Cost: 34.07%
TTG
Total Project O&P, Completion
DateTOTAL PROJECT COST:
$647,518.79OVERHEAD RATE:
9.765% or $63,230.21PROFIT RATE:
5.0% or $32,375.94
TOTAL COST WITH O&P:$743,124.94
DURATION:~ 6.90 MONTHS
Start: 12/17/2012
Complete:~07/10/2013
TTG