subterranian gis substations

Upload: isaac-diaz

Post on 08-Aug-2018

241 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/22/2019 Subterranian GIS Substations

    1/62

    CopyrightSiemens AG

    Energy Sector / High Voltage Substations

    SubterranianGIS Substations

  • 8/22/2019 Subterranian GIS Substations

    2/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    1 Worldwide experience selected projects

    3 Planned projects and conceptual solutions

    2 Special requirements for underground S/S

    4 Discussion

    Presentation Roadmap

  • 8/22/2019 Subterranian GIS Substations

    3/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    1 Worldwide Experience Selected Projects

  • 8/22/2019 Subterranian GIS Substations

    4/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Difficult locations for substations and transformers

    S/S in French submarines Metro stationsHydropower stations Offshore wind parks

    Sophisticated Projects

  • 8/22/2019 Subterranian GIS Substations

    5/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: SwitzerlandClient: Stadtwerke St. GallenScope: 5 bays 110 kV GIS type 8DN9

    15 bays MV, 24 kV NX Plus

    2 x 25 MVA transformers

    The substation is located in a stadium.It was a big challenge to coordinate theimplementation of the substation with theongoing work on site.Transformer openings are closed withprefabricated concrete slab, which can beremoved with reasonable effort.

    St. Gallen Breitfeld

    Switzerland, St. Gallen - Breitfeld

  • 8/22/2019 Subterranian GIS Substations

    6/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: SwitzerlandClient: Stadtwerke St. GallenScope: 6 bays 110 kV GIS type 8DN9

    2 x 40 MVA power transformers

    110/10 kV each17 bays MV, 10 kV GIS

    The Substation is integrated in a buildingcomplex and installed underground inlevel-3 and level-4. More than 250 t ofmaterials and equipment had to be cranedin to a point 15 m below ground level.In the building above is accommodated abank and the Switzerland institution for

    material testing

    St. Gallen Schochengasse

    Switzerland, St. Gallen - Schochengasse

  • 8/22/2019 Subterranian GIS Substations

    7/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Preparations for

    offloading a 40 MVA

    transformer

    Transformer is lifted into

    the foreseen opening

    Transformer placed on

    the rails and ready to be

    pulled to final position

    Schochengasse 110/10 kV SubstationProject Execution - Heavy Equipment Installation

  • 8/22/2019 Subterranian GIS Substations

    8/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    PavingPaving

    Schochengasse 110/10 kV SubstationClosing Transformer Opening Outside

  • 8/22/2019 Subterranian GIS Substations

    9/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    ceiling

    Removable slabRemovable slab

    Schochengasse 110/10 kV SubstationClosing Transformer Opening Inside

  • 8/22/2019 Subterranian GIS Substations

    10/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Data protection

    Faraday Cage

    People protection

    Schochengasse 110/10 kV Substation EMIProtection

  • 8/22/2019 Subterranian GIS Substations

    11/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Solutions Water CO2 Halon

    Nitrogen Inergen

    Schochengasse 110/10 kV SubstationTransformer - Fire Extinguishing System

  • 8/22/2019 Subterranian GIS Substations

    12/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Fire Safe

    Schochengasse 110/10 kV SubstationTransformer Separated

  • 8/22/2019 Subterranian GIS Substations

    13/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Activation controlfrom the entrancefour floors higher

    Activation controlfrom the entrancefour floors higher

    Schochengasse 110/10 kV SubstationSmoke Extraction System

  • 8/22/2019 Subterranian GIS Substations

    14/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Exhaust airExhaust air

    EmergencyexitEmergencyexit

    LadderLadder

    Schochengasse 110/10 kV SubstationUtility Shafts and Emergency Exit

  • 8/22/2019 Subterranian GIS Substations

    15/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Drainage systemin cable basement

    Schochengasse 110/10 kV SubstationSprinkler System in Cable Basement

  • 8/22/2019 Subterranian GIS Substations

    16/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Fresh air below transformer Fresh air under the ceiling

    Schochengasse 110/10 kV SubstationHVAC Dust Protection

  • 8/22/2019 Subterranian GIS Substations

    17/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Increased safetyIncreased safety

    Schochengasse 110/10 kV SubstationTransformer - Encapsulated Termination

  • 8/22/2019 Subterranian GIS Substations

    18/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: SwitzerlandClient: Stadtwerke Winterthur

    The location is between school playground

    and a motorway about 4m above. Thesubstation is used to equalize the heightdifference and to detain the noise from thecars.

    The 2 storey building with cable basementhas an even access for transformers. Theother side is covered by the rising plot.

    110/20 kV Substation -Wlflingen

    Switzerland, Winterthur - Wlfingen

  • 8/22/2019 Subterranian GIS Substations

    19/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    WlfingenGround Plan

  • 8/22/2019 Subterranian GIS Substations

    20/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Sound absorber

    WlfingenNoise Limits Outside

  • 8/22/2019 Subterranian GIS Substations

    21/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    WlfingenPlayground Outside the Substation

  • 8/22/2019 Subterranian GIS Substations

    22/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Side effect:heating systemcools transformer

    WlfingenTransformer Cooling Devices

  • 8/22/2019 Subterranian GIS Substations

    23/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    WlfingenControl Room Special Design

  • 8/22/2019 Subterranian GIS Substations

    24/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    WlfingenIntuitive Guiding

  • 8/22/2019 Subterranian GIS Substations

    25/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: AustraliaClient: TransGridScope: 25 x bays GIS type 8DN8/145 kV

    4 x bays GIS type 8DQ1/362 kV330/132 kV transformer

    The substation is integrated in a buildingcomplex in Sydney and is installed across2 above ground and 3 basement floorlevels

    110/330 kV Substation -Haymarket

    Australia, Sydney - Haymarket

  • 8/22/2019 Subterranian GIS Substations

    26/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Haymarket 110/330 kV SubstationProject Execution - Deep Excavation

  • 8/22/2019 Subterranian GIS Substations

    27/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    app. 10 m,2 storey design

    above ground

    app. 22 m3 storey designbelow ground

    foot print app. 30x60 m

    Haymarket 110/330 kV Substation

  • 8/22/2019 Subterranian GIS Substations

    28/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Haymarket 110/330 kV SubstationMain Equipment @ Basement 2

  • 8/22/2019 Subterranian GIS Substations

    29/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Haymarket 110/330 kV SubstationSubstation Model

  • 8/22/2019 Subterranian GIS Substations

    30/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Substation control & metering room

    cable and auxiliary supply basementwith SF6 collection plenum

    110 kV GIS 8DN8:25 bays (15 cable feeders),double bus bar

    330 kV GIS totransformerconnection:GIB, 100% SF6 gas

    Gas insulated transformer:330 kV 400 MVA SF6 single phasetransformers, no. 3 transformers intotal

    330 kV GIS 8DQ1:4 bays, ring bus bar

    Haymarket 110/330 kV SubstationArrangement of Equipment

  • 8/22/2019 Subterranian GIS Substations

    31/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Floor Plan Basement 2 (Equipment Floor)

    Haymarket 110/330 kV SubstationSF6 Gas Management

  • 8/22/2019 Subterranian GIS Substations

    32/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Secondary SF6 plenum

    Floor Plan Basement 3 (Cable Basement and SF6 Plenum)

    Primary SF6 plenum

    Haymarket 110/330 kV SubstationSF6 Gas Management

  • 8/22/2019 Subterranian GIS Substations

    33/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Mainly under grounded substation in an urban environment

    Main electrical equipment with gaseous insulation, thusavoiding fire hazards

    Compactness due to latest GIS technology

    Sophisticated SF6 gas monitoring with slow and fast gas leakdetection

    Integrated control system enabling unmanned substationoperation

    Haymarket 110/330 kV SubstationKey Features

  • 8/22/2019 Subterranian GIS Substations

    34/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: MexicoClient: CFEScope: 6 x bays GIS type 8DN9

    2 x power transformer 100 MVA

    Substation in a park in the middle ofcommercial district.

    Access ramp, AC openings and stairs arehidden behind landscaping.

    132 kV SubstationFaro - Monterrey

    Mexico, Monterrey - Faro

  • 8/22/2019 Subterranian GIS Substations

    35/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: USAClient: City of Anaheim CAScope: 8 x bays GIS Type 8DN9 / 69 kV

    2 x 69/12 kV 50 MVA

    transformers20 x 12 kV panels

    69/12 kV Park SubstationCity of Anaheim

    United States, City of Anaheim Park Substation

  • 8/22/2019 Subterranian GIS Substations

    36/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Park SubstationCovered by the Roosevelt Park

  • 8/22/2019 Subterranian GIS Substations

    37/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Park SubstationS/S Entrance Design

  • 8/22/2019 Subterranian GIS Substations

    38/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Park SubstationS/S Emergency Exit

  • 8/22/2019 Subterranian GIS Substations

    39/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: SpainClient: CFEScope: 245KV, GIS 12 bays 8DN9

    One of three Siemens undergroundsubstations in multistory buildings inMadrid.

    Access via crane and open able duct

    245 kV SubstationManuel Becerra

    Spain, Madrid Manuela Becerra

  • 8/22/2019 Subterranian GIS Substations

    40/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Country: SwitzerlandClient: Stadtwerke Winterthur

    Underground substation under a

    schoolyard in Winterthur.

    Started May 2008

    110/10 kV SubstationToessfeld

    Switzerland, Winterthur - Toessfeld

  • 8/22/2019 Subterranian GIS Substations

    41/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    ToessfeldSection View of the Fully Undergrounded Substation

  • 8/22/2019 Subterranian GIS Substations

    42/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    ToessfeldSection View

  • 8/22/2019 Subterranian GIS Substations

    43/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Less effort withsingle storeyundergroundbuildings.

    Ongoing project inSwitzerland:Monitored withWebcam

    ShoringShoring

    SlopeSlope

    ToessfeldSite Mobilization and Supervision

  • 8/22/2019 Subterranian GIS Substations

    44/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    2 Special requirements for underground S/S

    1. Soil + Ground Water

    2. Fire Fighting

    3. HVAC

    4. Emissions

    5. Access

  • 8/22/2019 Subterranian GIS Substations

    45/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Ground water tableSoil pressure

    Crucial for design andcost

    Soil and Ground Water

  • 8/22/2019 Subterranian GIS Substations

    46/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    /$

    Ground WaterCost Impact

  • 8/22/2019 Subterranian GIS Substations

    47/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Passive Fire Fighting

    No flammable material.

    2 separated ventilationsystems for transformersand building

    Active Fire Fighting

    Fire extinguish system

    HSE Regulations

    Emergency exit

    No toxic materials (PVC)

    Fire Protection ConceptFire Fighting

  • 8/22/2019 Subterranian GIS Substations

    48/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Ventilation

    Transformer separated fromother devices.

    More space needed.

    Humidity Avoid humidity by minimizing

    air exchange

    HVAC

  • 8/22/2019 Subterranian GIS Substations

    49/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Noise

    Inconvenient sound of HVAC-units and transformers

    Electromagnetic

    Too small vertical clearance topublic places or EDP

    Emmissions

  • 8/22/2019 Subterranian GIS Substations

    50/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Heavy Equipment

    If possible transformers onground floor

    Aesthetic

    Architectural design ofvisible parts

    Access

  • 8/22/2019 Subterranian GIS Substations

    51/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    3 Planned Projects and Conceptual Solutions

    Planned Projects and Conceptual Solutions

  • 8/22/2019 Subterranian GIS Substations

    52/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Section 1

    Conceptual Solution Semi Underground

  • 8/22/2019 Subterranian GIS Substations

    53/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Section 2

    Conceptual Solution Semi Underground

  • 8/22/2019 Subterranian GIS Substations

    54/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    If the space between ground surface and water table is limited, the cable basement can be avoided.

    Sample: U/G S/S Round House West Area P1,Toronto Hydro/Canada

    Cable Basement & Cable Entry

    Sample: Chorzow S/S, Poland

    HV cables in horizontal position terminated

    LV cables in cable tray above LCC cubicels

    LV cable entry to LCC cubicles from the top

  • 8/22/2019 Subterranian GIS Substations

    55/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    In construction and technical design

    8DN8-72.5 kV corresponds to switchgear

    8DN8-145 kV, but is smaller

    Bay Width: 800 mm

    Conventional air-isolated type

    How to cope with the problem of limited space?

    Nx+C (11 kV GIS)

    Use equipment with reduced space requirements

    8DN8-72.5 (66 kV GIS)

    Bay Width: 640 mm

    Conceptual Solutions 66/11 kV GIS

  • 8/22/2019 Subterranian GIS Substations

    56/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    3 Possible Layouts

    Underground S/S

    Semi underground S/S

    On top building

    Hide as much as possible

    2 levelsDesign necessary

    Design Concept

  • 8/22/2019 Subterranian GIS Substations

    57/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Possible Urban Situation

    Substation surrounded by buildings

    Park area, trees, plants, green

    City square, plaza or parking area

    Urban Situation Architectural Concept

  • 8/22/2019 Subterranian GIS Substations

    58/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Design Solution on Top of Public Squares

  • 8/22/2019 Subterranian GIS Substations

    59/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Waterfall Entrance

    In park design water isan essential element.

    HVAC - Acoustic Solutions for Parks and Sqares

  • 8/22/2019 Subterranian GIS Substations

    60/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Cost impact (underground S/S in relation to conventional S/S)

    Conventional S/S Underground S/S

    12%100%Total costs

    010lot1Services (design, installation and testing)

    3407lot1Mechanical, electrical, plumbing (MEP) works

    22lot1Landscaping

    42517lot1Civil & structural works

    33lot1Excavation

    02lot1Earthing and lightning protection

    08lot1LV cables and cable routing

    016lot1SCS & CRP

    06lot1LV service equipment

    02lot1HV cables 66 & 11 kV c/w acc.

    015Nos3Transformer 40 MVA and NER

    04bays2811 kV switchgear

    014bays1366 kV DBB GIS

    TotalCosts of new items

    in %Additionalcosts in %

    %

    Commercial Aspects (Preliminary Approach)

  • 8/22/2019 Subterranian GIS Substations

    61/62

    Energy Sector / High Voltage Substations

    CopyrightSiemens AG

    Estimated execution time: 20 months per substation (subject to transformer delivery)

    Project Execution Schedule

  • 8/22/2019 Subterranian GIS Substations

    62/62

    CopyrightSiemens AG

    Thank you foryour attention !