Subsea Processing System Integration Engineering. 07121-1901 Project Management Plan Rev 1. Project Plan. Project Team Organisation. GE Oil & Gas Business Program Manager Amin Radi (GR). GE DW1901 Team. Project Director Chris Wolfe (GR). Technology Leader Dan Friedemann (VG) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Subsea Processing System Integration Engineering

Subsea Processing System Integration Engineering07121-1901Project Management Plan Rev 1

Page 2: Subsea Processing System Integration Engineering

Project Management PlanFebruary 11, 2009

Project Plan

Microsoft Project Document

ID WBS Task Name PredecessorsDuration Start Finish

1 1 Task 1: Develop Integrated Process Simulator 57 wks Fri 1/2/09 Thu 2/4/10

2 1.1 Literature & Prior Work Survey (includes equipment vendor survey)7.9 wks Fri 1/2/09 Thu 2/26/09

12 1.2 Component Modeling 42.44 wks Thu 2/5/09 Tue 12/1/09

22 1.3 Integrated Process Simulator 57 wks Fri 1/2/09 Thu 2/4/10

35 1.4 Develop SSP Evaluation Methodology (Developed in parallel with Level 4)31 2.2 wks Fri 5/8/09 Fri 5/22/09

38 1.5 Milestone 1 Report-out: Simulator Prototype Presentation 37 0 wks Fri 5/22/09 Fri 5/22/09

39 2 Task 2: Laboratory Test and Mobilization 41.1 wks Fri 1/2/09 Fri 10/16/09

91 3 Task 3: Execute the Lab Scale Test Matrix 39 37 wks Fri 10/16/09 Fri 7/2/10

92 3.1 Validate/Develop Component Level Models 5 wks Fri 10/16/09 Fri 11/20/09

97 3.2 Validate SSP Simulator 30 wks Fri 11/6/09 Fri 6/4/10

98 3.2.1 Execute Test Matrix 94 14 wks Fri 11/6/09 Fri 2/12/10

99 3.2.2 Conduct Data Reduction 98 1 mon Fri 2/12/10 Fri 3/12/10

100 3.2.3 Analyze Data 99 1 mon Fri 3/12/10 Fri 4/9/10

101 3.2.4 Adjust Prototype Simulator 100 2 mons Fri 4/9/10 Fri 6/4/10

102 3.3 Write Technical Report 92,971 mon Fri 6/4/10 Fri 7/2/10

103 3.4 Database Raw and Analyzed Data 100 3 days Fri 4/9/10 Wed 4/14/10

104 3.5 Deliverable 1: SSP Simulator 0 wks Fri 10/16/09 Fri 10/16/09

113 3.6 Deliverable 3: Test Matrix Results Reporting 32 wks Fri 11/20/09 Fri 7/2/10

114 3.6.1 Test Report 32 wks Fri 11/20/09 Fri 7/2/10

121 3.6.2 Database of Raw & Analyzed Data 103 0 days Wed 4/14/10 Wed 4/14/10

122 3.7 Milestone 3 Report-out (Deliverables 1 & 3) 104,1130 wks Fri 7/2/10 Fri 7/2/10

123 4 Task 4: Technology Transfer 71.1 wks Fri 2/20/09 Fri 7/2/10

124 4.1 Develop Technology Transfer Plan w/ RPSEA 150 2 wks Fri 2/20/09 Thu 3/5/09

125 4.2 Conduct Training on Simulator Use (start after project Milestone 3)131 0 days Fri 7/2/10 Fri 7/2/10

126 4.3 Disseminate Project Results (start after milestone 3) 131 0 days Fri 7/2/10 Fri 7/2/10

127 5 Task 5: Program Mangement 87.2 wks Fri 1/2/09 Fri 9/3/10

128 5.1 Milestone 0: Project Kick-off 0 days Fri 1/2/09 Fri 1/2/09

129 5.2 Milestone 1: Task 1 (Develop Integrated Process Simulator) Complete37 0 days Fri 5/22/09 Fri 5/22/09

130 5.3 Milestone 2: Task 2 (Lab Test & Mobilization) Complete 79 0 wks Fri 10/16/09 Fri 10/16/09

131 5.4 Milestone 3: Project Completion 124,1130 days Fri 7/2/10 Fri 7/2/10

132 5.5 Monthly Reports 76.5 wks Fri 1/2/09 Tue 6/22/10

150 5.7 Technical Kick-Off Meeting 0.2 wks Thu 2/19/09 Thu 2/19/09

151 5.6 Quarterly reviews 77.8 wks Tue 3/10/09 Fri 9/3/10

5/22

Flow Loop Manager,Flow Loop Tech,Kristian SveenKristian Sveen,JD Williams

JD WilliamsJD Williams

10/16

4/147/2

Dave Anderson7/27/2

1/25/22

10/167/2

DecJanFebMarAprMayJun Jul AugSepOct NovDecJanFebMar AprMayJun Jul AugSepOct NovDecJan4th Quarter 1st Quarter 2nd Quarter3rd Quarter 4th Quarter 1st Quarter 2nd Quarter3rd Quarter 4th Quarter 1st Quarter

2008 2009 2010 2011

Page 3: Subsea Processing System Integration Engineering

Project Management PlanFebruary 11, 2009

 

 

 

 

Project Team Organisation

Weekly team meetings; quarterly RPSEA meetings

Project DirectorChris Wolfe (GR)

GE Oil & Gas Business Program Manager

Amin Radi (GR)

Technology LeaderDan Friedemann (VG)Project Technical Quality

Principal InvestigatorDavid Anderson (GR)

Multi-Phase Flow Loop Lead

Kristian Sveen (VG)Test Facility Preparation

& Test Execution

Separation Modeling Lead Inge Wold (VG)

Simulator LeadMahadevan Balasubramaniam (GR)

Component model/Simulator Development

 

 

  Statistical Analysis Lead James D Williams (GR)Probabilistic Performance

Evaluation; Experimental Design & Analysis

Software EngineerRoger Shisler (GR)

External Input for Component LibraryEquipment Suppliers

Simulator End-Users/Beta UsersOperators/Equipment Suppliers

GE DW1901 Team

Flow Loop Operation Flow Loop Team (VG)

GR: Global Research – NiskayunaVG: VetcoGray - Oslo

Page 4: Subsea Processing System Integration Engineering

Project Management PlanFebruary 11, 2009

Baseline Project Cost

 

 

 

 

$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

$1,200,000

$1,400,000

$1,600,000

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep Oct

Nov

Dec Ja

n

Feb

Mar

Apr

May

Jun

Cum

mul

ativ

e Sp

end

[$]

Task 5 Program ManagementTask 4 Technology TransferTask 3 Test MatrixTask 2 Laboratory MobilisationTask 1 Process Simulator

Total Project Cost: $1,511,448RPSEA Funding: $1,200,000GE Cost Share: $311,448

Page 5: Subsea Processing System Integration Engineering

Project Management PlanFebruary 11, 2009

Technology Transfer Plan - Preliminary

 

 

 

 

Simulator technology transfer via demonstrations at:Quarterly RPSEA meetingCustomer workshops at GE – “Session T”

- Annual events with GE O&G customersConference presentations

- Target conferences to be determined

Start with simulator prototype – June Quarterly meeting

Develop detailed plan with RPSEA