SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Th Ankit Yadav BURJ KHALIFA The tallest building in the world Submitted To: Vidya Narayan

Upload: camila

Post on 23-Jan-2016

58 views

Category:

Documents


0 download

DESCRIPTION

Submitted To: Vidya Narayan. BURJ KHALIFA. The tallest building in the world. SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav. Introduction Why Burj Dubai becomes Burj Khalifa ?? Planning and construction Architecture Scope Project management - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

SUBMITTED BY:Bhinderjit SinghCharandeep KaurManpreet Kaur ThindAnkit Yadav

BURJ KHALIFA

The tallest building in the worldSubmitted To:Vidya Narayan

Page 2: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Introduction

• Why Burj Dubai becomes Burj Khalifa??

• Planning and construction

• Architecture

• Scope

• Project management

• Cost Management

• Time Management

• Factors Affecting time and cost

• Burj khalifa construction team

• Risk management

• Success/ Failure

• Software Used

• Facts and Figures

• Comparison between buildings

• References

Page 3: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Burj Khalifa, earlier known as Burj Dubai, located in Downtown Dubai UAE.

• Burj Khalifa is tallest man made structure in the world.• Burj Khalifa developed by the leading developer Emaar

Properties• Construction of the project began on 21st September

2004 and the building officially opened on 4 January 2010

• Burj Khalifa is as a living wonder, a stunning piece of art, and incomparable feat of engineering.

Page 4: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Why Burj Dubai becomes Burj Khalifa??

• Burj Dubai was officially renamed by Dubai’s ruler as the Burj Khalifa named after the UAE president Sheikh Khalifa Bin Zayed.

Page 5: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• The primary design concept of the tower is an organic form with tri-axial geometry and spiraling growth that can be easily seen in the final design

• The floor plan of the tower consists of a tri-axial, “Y” shaped plan, formed by having three separate wings connected to a central core

Page 6: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Over 45,000 m3 of concrete, weighing more than 110,000 tonnes were used to construct the concrete and steel foundation

• Burj Khalifa's construction will have used 330,000 m3 of concrete and 39,000 tonnes of steel rebar, and construction will have taken 22 million man-hours

• The amount of rebar used for the tower is 31,400 metric tons - laid end to end this would extend over a quarter of the way around the world.

Page 7: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Architecture

• The architecture features a triple-lobed footprint, an abstraction of the Hymenocallis flower

• The tower is composed of three elements arranged around a central core• The modular, Y-shaped structure, with setbacks along each of its three wings

provides an inherently stable configuration for the structure and provides good floor plates for residential

• The central core emerges at the top and culminates in a sculpted spire

Page 8: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Scope

• The project scope is the definition of what the project is supposed to accomplish and the budget of both time and money that has been created to achieve these objectives.”

• The initial planned costs of the Burj Khalifa project was $876 million dollars

• The initial planned height was 728 meters from the ground

Page 9: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

SCOPE CONTINUED..

9

Burj Khalifa (Burj Dubai) is the tallest man-made structure ever built.The mixed use development will include residential units, offices, hotels and residential apartments.

Burj Khalifa was planned by the Dubai government with the aim of becoming a hub for finance, trade and tourism in Middle East

Page 10: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

“Iron Triangle”, a criterion which measures the project based on three perspectives:COSTTIME

QUALITY

Page 11: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

11

The initial planned costs of the project was 876 million dollars. The final cost, however, was approximately 1.5 billion dollar

The final construction was 100 meters higher than the original design

Changes in interior design planning were another reason for the increase in costs

Page 12: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

TIME MANAGEMENT

12

Originally, the duration of project was set for forty-seven months, starting from February 2005 to December 2008

The Burj Khalifa project was completed nine months later, on September 2009.

Economical decline halted construction for four months in 2008.

Page 13: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Temperature rising over 45 degrees, wind, sun and gravity

• Rise in price of raw materials and special kind of reinforced

concrete for construction, special type of glass panels with

aluminium used to protect this structure from wind, dust and sun.

• Construction cost.

Page 14: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Cont’d….

• Emaar was also affected by the downturn in the real estate market in Dubai. In late 2008, the price of property at Burj Dubai slumped by about 50%-60%, while prices in the surrounding Downtown Burj Dubai fell by at least 22%• First of all, a rise in prices of raw materials had gone up significantly

due to the downturn of the global economy in 2008.• According to report of Global Informing (2008), the price of iron had

increased by 75% within a year. Other materials such as aluminum and cement also increased Increase of price of commodities caused a factor to increase construction cost.

Page 15: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Burj Khalifa

Construction team

• Burj Khalifa was truly an international collaboration between more than 30 on-site contracting companies from nations around the world.• At the peak of construction, over 12,000 workers and constructors

were on site every day, representing more than 100 nationalities.• Workers include mostly Indian, Pakistan and Srilankan

Page 16: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Change in Design

• The final construction was 100 meters higher than the original design• The changes were made in interior

design on the demand of Armani hotels

16

Page 17: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

17

Bad Employee Management

• In 2006, the project, which had till then been

progressing slightly ahead of schedule, fell behind

schedule. Workers from countries like India,

Pakistan, and Bangladesh, were used to construct

the towers and they complained that they were

being paid very low wages.

Page 18: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• The engineers of the tower worked the design of the structure to avoid the two major challenges; wind and gravity.

• The highest-risk part of the Burj Khalifa is its high speed elevators

• To ensure safety, the Burj Khalifa features a home automation system which consists of LCD panels that display detailed emergency information to specified groups of building occupants.

18

Page 19: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

Samsung engineering and Besix, introduced new technologies based on previous experiences with tall building construction.

Following technologies were used for building Burj Khalifa :

• The ETABS software developed by Computers & Structures Inc., of USA was used for the analysis and design.

• Prolog Manager is a Windows-based construction project management application

19

Page 20: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

From the point of quality : The project is successful

The net profit increased 10 times compared to 2009

20

Page 21: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Former names: Burj Dubai• Preceded by: Taipei 101• Location : Dubai, United Arab Emirates• Construction started: January 2004• Construction ended : 2010 • Opening: 4 January 2010• Cost : USD $ 1.5 billion• Building with most floors: 160

Page 22: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav

• Height Antenna spire : 829.84 m (2,723 ft) Roof : 828 m (2,717 ft) Top floor : 621.3 m (2,038 ft)• Architect : Adrian Smith • Developer : Emaar Properties• Structural engineer : Bill Baker

Cont’d….

Page 23: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav
Page 24: SUBMITTED BY: Bhinderjit Singh Charandeep Kaur Manpreet Kaur Thind Ankit Yadav