Project Targets – Business Overview
• Su-Tas faced with strong competition in the region
• Preliminary project scope/estimates began in 2005
• Infrastructure in Istanbul projected to grow – Third Bridge – Northern Marmara
connection roadway – City Growth/Expansion – New Airport Project
Project Targets – Production Requirements
• Establish a more modern facility – Produce Concrete and Asphalt materials – Increase productivity from 450 TPH to 1,000 TPH – Increased Product shape/quality
• Washed Aggregates
– Improved Safety – Environmentally Responsible
• Dust Suppression • Noise Pollution • Reclamation • Landscaping • Water Recovery
Equipment Selection & Considerations
• (2) 3352 Jaw Crushers
• (2) K400+Cone Crushers
• (3) 4500 VSI Impactors
• (5) Horizontal Screens
• Fully Automated
• Product Support by Dizel Turbo – Local Parts Inventory
– Local Service Support
• Installation, Plant Commissioning