Page 1: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Study of Failed Project

Naila GhaniKhunsa IqbalZahra BadarWajiha FarooqNarmeen Haroon

MS – TOTAL QUALITY M ANAGEMENTINSTITUTE OF QUALITY AND TECHNOLOGY MANAGEMENTUNIVERSITY OF THE PUNJAB, LAHORE, PAKISTAN.

Page 2: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Millennium Dome:

Page 3: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

The Millennium Dome, colloquially referred to simply as The Dome.

Page 4: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Origination:

• the project concept was expanded and championed by Labour party Prime Minister Tony Blair when he took office in 1997.

• The event was designed to draw tourists into London during the Millennium year and was intended to be a celebration of mankind’s achievements.

Page 5: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

 "a triumph of confidence over cynicism, boldness over blandness, excellence over mediocrity".

Page 6: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

In 1997 the Labor government of Tony Blair formed the New Millennium Experience Company Ltd. (NMEC)

Page 7: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Finance Management:

Government decides to support the project with public money after being unable to raise private capital.

Page 8: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Total expenditure:

• the total cost of The Dome at the liquidation of the New Millennium Experience Company in 2002 was £789 million,

• of which £628 million was covered by National Lottery grants • and £189 million through sales of tickets etc.

Page 9: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
Page 10: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

initial reaction from the press was poor. Lack of content, lack of clear themes and lack of creativity were common criticisms.

Page 11: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

• For budgeting purposes government officials had projected 12M visitors. In reality only 6 1/2M people attended.

Page 12: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

• The NMEC is a company which has been under considerable pressure. Any company which had just completed a massive capital project and had then opened a huge and novel visitor attraction would be.

Page 13: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

LONDON ARENA

Page 14: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

the venue's new owners, spent 600 million pounds ($1.2 billion) to renovate the site, adding a 20,000-seat concert arena

Page 15: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Contributing factors as reported in the press:• Lack of vision.• Poor execution• Failure to manage expectations • Failure to plan properly for the post event disposition of the venue.

Page 16: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Causes of difficulties:

The main cause of the financial difficulties is the failure to achieve the visitor numbers and the income required.

Right from the start the idea was driven by politicians, not the commercial or business sector.

Its designers created an impressive pack and only when this was launched they started asking the market how they want it.

Page 17: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

a table linking these factors with the factors studied in class.

no Factors contributed towards failure Falls in category of phase

1 Less creativity conception

2 Poor prioritization planning

3 Over expectations definition

4 Wrong forecasting definition

5 Changing responsibilities planning

6 Poor marketing strategies execution

7 Over use of resources execution

Page 18: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
Page 19: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

Definition phase is the most important phase.You are doing project to attract customers so find out their requirements before starting the project and not after.

Page 20: STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME

it was all……….

Thanks for your attention……..!