Street Landscaping
Streets, Trees and Gardens Pre-Defects Liability Period
Inspection Checklist
F7.1 Infrastructure Technical Specifications
Version : October 2012 Page 1 of 1 For further information about this form, email [email protected]
STREET TREES & GARDENS – PRE-DEFECTS LIABILITY PERIOD INSPECTION
Pre-Meeting Tasks
Organisation Action Required Yes No N/A Contractor 1) Complete all work indicated on drawings 2) Trees staked, tied and mulched 3) Mow grass 4) Gardens planted, barked and weed-free 5) Irrigation installed to specification
SITE MEETING
In Attendance
Council Officer ________________________________________________
Council Officer ________________________________________________
Contractor ________________________________________________
Consultant ________________________________________________
1) Inspect site 2) Plans and specifications complied with 3) Check mowing 4) Acceptable standard agreed upon
DEFECTS LIABILITY PERIOD
6 months 1 year (delete as required)
Start of Defects Liability Period __________________ End of Defects Liability Period ________________
Items to be Provided/Corrected
No Action Required Party to Party to Acceptance Action Accept Approved Date
______________________________ _________________________ _________________________ Council Developer Date
Street Landscaping
Final Inspection Street Trees and Gardens
Checklist
F7.2 Infrastructure Technical Specifications
Version : October 2012 Page 1 of 1 For further information about this form, email [email protected]
FINAL INSPECTION - STREET TREES & GARDENS
Pre-Meeting Tasks
Organisation Action Required Yes No N/A
Contractor 1) Make sure site complies with standards as agreed at pre-maintenance inspection
2) Trees staked, tied and mulched 3) Dead and damaged trees replaced 4) Mow grass 5) Gardens planted, barked and weed-free 6) Irrigation In working order SITE MEETING
In Attendance
Council Offficer ________________________________________________
Council Officer ________________________________________________
Contractor ________________________________________________
Consultant ________________________________________________
1) Inspect site 2) Trees staked, tied and mulched 3) Gardens barked and weed-free 4) Gardens and planting meet agreed standards 5) Dead and damaged plants replaced
HAND-OVER
1) Gardens and street trees now acceptable for hand-over to Council for ongoing maintenance
Council to take over maintenance as from: _____________________________________________________
Items to be Provided/Corrected
No Action Required Party to Party to Acceptance Action Accept Approved Date