Steps to create

MASTER PLAN

Page 2: Steps to Create Master Plan -ppt

Step 1

Complete verified Data survey of site from Planning Engineer as per standard templates made by CMMS Team, under supervision of Site Manager which is sent to head office-CMMS team.

• Data include Locations with required details and Assets (Details & Specs).

S t e p s t o C r e a t e M A S T E R P L A N

Page 3: Steps to Create Master Plan -ppt

Step 2

Primary Locations are uploaded into Maximo as hierarchical structure (Tree Structure).

S t e p s t o C r e a t e M A S T E R P L A N

Page 4: Steps to Create Master Plan -ppt

Step 3

Assets are numbered and attached with their respective hierarchical system locations.

S t e p s t o C r e a t e M A S T E R P L A N

Page 5: Steps to Create Master Plan -ppt

Step 4

Respective System Asset Groups are created for same type of assets against same main locations.

S t e p s t o C r e a t e M A S T E R P L A N

Page 6: Steps to Create Master Plan -ppt

Step 5

Verify Job Plans by Technical Dept. with their PMIs, Labors, Estimated Time, Material, equipment) with confirmation from Site Manager.

S t e p s t o C r e a t e M A S T E R P L A N

Page 7: Steps to Create Master Plan -ppt

Step 6

PM records are created on the basis of asset groups by CMMS Team.

S t e p s t o C r e a t e M A S T E R P L A N

Page 8: Steps to Create Master Plan -ppt

Step 7

As per initial approval from operation manager, frequencies are updated for each Asset Group with related PM Record.

S t e p s t o C r e a t e M A S T E R P L A N

Page 9: Steps to Create Master Plan -ppt

Step 8

Utilizing the forecasting utility of Maximo, the PMs are forecasted for the 11 months (Excluding December).

S t e p s t o C r e a t e M A S T E R P L A N

Page 10: Steps to Create Master Plan -ppt

Step 9

A report is extracted from Maximo after forecasting and mapped in excel.

S t e p s t o C r e a t e M A S T E R P L A N

Page 11: Steps to Create Master Plan -ppt

Step 10

Master Plan projection will be send to HR for Manpower tuning to get their confirmation.

S t e p s t o C r e a t e M A S T E R P L A N

Page 12: Steps to Create Master Plan -ppt

Step 11

Master Plan has been issued.

S t e p s t o C r e a t e M A S T E R P L A N

Page 13: Steps to Create Master Plan -ppt

Step 12

This mapping is distributed to respective sites and related people and departments for confirmation.

S t e p s t o C r e a t e M A S T E R P L A N

CMMS

Site Manager

Operation Manager

IT Manager

Quality Manager

Page 14: Steps to Create Master Plan -ppt

Step 13

Any change from site or operation manager is updated accordingly based on Change Workflow.

S t e p s t o C r e a t e M A S T E R P L A N

Page 15: Steps to Create Master Plan -ppt

Step 14

After Final Approval on Master Plan ( from Operation Manager & Site Manager), Master Plan will start executed on weekly basis under responsibility of Planning Engineer under supervision and follow up from CMMS Team.

S t e p s t o C r e a t e M A S T E R P L A N

Page 16: Steps to Create Master Plan -ppt