Page 1: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

Step IV Construction

North Side Walls and End Walls20-27 May 2015

Stephen Plate, Brookhaven National Laboratory

Page 2: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

2

Anchoring the upper shield plate to the framework at the west end

Page 3: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

3

Installing one of four L-mounting brackets to the side walls at the west end.Brackets support the Virostek plates at each end and provide a continuous flux path into the side walls while accomodating tolerances.

Page 4: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

4

West end,lower wall plate

Adjustable cams react thrust loads from end walls

Crossbar support brackets under mezzanine

Crossbars react north and south sides against each other to reduce tension loads on floor anchors

Page 5: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

5

View from northwest corner of mezzanine

Page 6: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

6

View from east mezzanine

Upper center section installed for fit-check only at this time

Page 7: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

7

Installing first crossbar

transfer drill at assembly;each of 7 crossbars is unique.

Page 8: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

8

Present Status• east and west end walls were installed, then

removed to give access for installation of the spectrometer waveguides as planned

• all crossbars are now installed• yet to be installed are the draw wires for

measuring deflection under magnetic forces

draw wire stanchions

Page 9: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

Step V Design

Page 10: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

10Viewed from north side

(3) one-piece center plates

2 removable sectionsfor RF maintenance

Page 11: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

11

Step IV leg spacingDownstreamPRY expansion

Page 12: Step IV Construction North Side Walls and End Walls 20-27 May 2015 Stephen Plate, Brookhaven National Laboratory

12

Step V Status

• 12 detail drawings essentially complete, but will need:– positions of crossbars (J. Tarrant input)– access holes fro RF couplers

• 1 detail drawing needs to be completed• 6 assembly drawings need to be completed– assy drawings will not hold up the fabrication

• Steel plates from Japan arrive Phila., PA around 11 July