stefan moeller xes [email protected] fac review – april 16, 2006 x-ray endstation...

18
Stefan Moeller XES Status [email protected] d.edu FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller

Post on 20-Dec-2015

222 views

Category:

Documents


1 download

TRANSCRIPT

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

X-Ray Endstation Systems (XES) Status

Stefan Moeller

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Outline

Recent Developments

Status

Milestones

Plan for rest of FY07

Summary

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Recent Developments:

Effects of new LCLS baseline scheduleProvide a basic AMO instrument for 4a (3/09)

Add enhanced functionality for 4b (3/10)Provide controls infrastructure to enable operation of NEH for 4aPhase controls capabilities e.g. data storage, high level applicationsDelay systems/procurements related to Tunnel and Far Hall

PPS, ControlsXES Laser system delayedCornell Detector schedule not affected

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

LCLS XES 1.6/2.6

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Status: AMO Instrument

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

AMO Instrument

Scientific goals defined Physics Requirements finalized (PRD 12/06) Instrument components are identified (SCR 12/06) Working towards Preliminary Design Review (5/07) AMO controls requirements defined (CDR 4/07) ESDs of components in 5/07New baseline plan was reviewed with AMO science group

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Hutch 2 Layout

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

AMO Instrumentation Overview

Differential pumpingFocusing opticsHigh field physics chamberDiagnostics ChamberMolecule/Cluster Imaging ApparatusHigh Field LaserControls

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

AMO Plan

PDR in 5/07

FDR 10/07

Start procurements 6/07

Receive 3/08

Installation 5/08

Basic experimental capabilities ready for first light (8/08)

Full AMO apparatus complete 3/10

AMO Controls on same schedule

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Cornell 2D Detector

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Cornell 2D DetectorOver half way through the project (Start 1/05)LDAC Review #4 for CY06 (Feb. 05-06, 2007) Good review, on scheduleNext review in fall 07 (mid term review)Submitted full-lot 190x190 pixel ASIC and diodeReceive full lot prototype in 09/07Design full scale read out (FPGA), data transfer and storageDesigns on tiling and packaging are being developed

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Cornell 2D Detector

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Controls

2x per week meetings of the XES/LUSI Controls group

CDR 4/07 AMO experimental controls

AMO control hard ware components defined

Data acquisition and detector controlsSLAC in house CE module solution

Data storageSCCS BaBar model

see talk by B. Sass

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

XES/LUSI Architecture

Robert C. SassXES Conceptual Design Review

April 10 2007 5

SCCS

XES Hutch

DetectorInstrument(s)

Hutch IOCs &Instruments

X-Ray Transport to Diagnostics & Next Hutch

EthernetFast DAQData

DetectorControl

Anywhere

LCLS DataRetrieval

eXperimental End Station System Overview

EPICS Archive

MPG/LCLS Event Generator

Linac & LCLS Control GUI

MCC Main Control Room

Linac/LCLSInjector

Linac

InjectorUndulator

X-RayBeam

EVR Hardware Triggers

XESprivatesubnet

DataAcquisition

Subsystem(s)

XES Controller

Experimenter

LCLSAnalysis / Viewing

SLAC WAN

EventReceiver

Channel AccessGateway

Visual Data Monitor

120Hz IOC

120 Hz ArchiveEngine

120

Hz

Bea

m L

ine

Dat

a

120 Hz Beam Line & Timestamp Data (dedicated Ethernet)

XTOD

SLAC WAN

Mac

hin

e P

rote

ctio

n (

MP

S)

EELOG

EELOG

Beam LineProcessor

OtherDatabases

DAQArchive

SlowInstrument

Archive

XESData

Cache

FastInstrument

Archive

ExperimentSpecific IOCs &

InstrumentsMPS

MPS

DigitizedData

Channel Access

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Other XES activities

Biweekly meeting of the LUSI-LCLS interface working group

Rebaseline of XES schedule to be finalized soon

PPS stopper design is progressing

Safety review process has started with SOC

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

XES L3 Milestones

Level 3

FY07LDAC Mid-Project Review 2D Detector 4/07CT: Network Final Design Review 5/07CT: AMO Exp. Control Final Design Review 9/07

FY08Ready for Installation in NEH 10/072D Detector Production Start 12/07XES Laser Final Design Review 2/08Electron Dump Stopper certified 2/08Start XES Commissioning 3/08Award XES Laser System 4/08CT: AMO Exp. Control Complete 7/08AMO Mech./Vacuum Installation complete 9/08

FY09CT: Complete Network Installation 10/08XES Laser Operating in NEH 12/08Complete Acceptance Tests of Detectors 1/09

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

6 Month Look AheadXES Management:

Finalize Rebaseline ScheduleXES Controls: (LCLS Controls)

Start Preliminary Design phaseXES Laser: (LCLS Lasers)

Delayed: Specify Laser, Diagnostics and TransportAMOS

PDR 5/07FDR 11/07Start procurements 6/07

PPS Stoppers and Shielding: (delayed)PRD PPS in signing stageESD and Design of Photon stoppersElectron beam dump stoppers

Cornell Detector:Bump bonding ASIC to diodeDelivery of full lot proto to SLAC (9/07)Design read out electronic and data handling

Stefan Moeller

XES Status [email protected]

FAC Review – April 16, 2006

Summary

XES is responding to new LCLS baseline plan

Controls design for XES has started, tight schedule

On track for delivering a basic AMO station for experiments for first light

2D Detector program at Cornell is on schedule

Started Safety Review process for x-ray areas