Status of Torino-Dubna Production [email protected] CERN -CMS week 14-3-2005 Completion in may 2005. Production stopped since 2 weeks, motoreductor needs replacement (2 people from Torino will go to Dubna on Monday). Plates for n.chambers completed to do MB1-S 66 - MB4(9,11) 11 - MB2-S 62 4 MB4(10) 6 5 MB3-S 66 - MB4(4) 11 - MB4(8,12) 8 3 MB4-S 21 13 Aachen + Legnaro production ended

Upload: others

Post on 12-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of Torino-Dubna Production

[email protected] -CMS week 14-3-2005

Completion in may 2005. Production stopped since 2 weeks, motoreductor

needs replacement (2 people from Torino will go to Dubna on Monday).

Plates for n.chambers

completed to do

MB1-S 66 -

MB4(9,11) 11 -

MB2-S 62 4

MB4(10) 6 5

MB3-S 66 -

MB4(4) 11 -

MB4(8,12) 8 3

MB4-S 21 13

Aachen+Legnaro production ended

Page 2: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of Torino-Dubna Production

[email protected] -CMS week 14-3-2005

Same problem occurred in november 2004 on the other

motoreductor.

Page 3: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of MB4 Production

[email protected] -CMS week 14-3-2005

First 3 chambers transported succesfully to CERN on 15-2-2005

Both tables operational:

Table 1 : SL assembly and chamber assembly

Table 2 : Sl assembly only (presently working at 1SL/week)

I-Beam tool 1

I-Beam tool 2

Page 4: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Chamber Glueing I

[email protected] -CMS week 14-3-2005

0

-443,4

538

-886,9

076

-1330,3

614

-1773,8

152

-2217,2

69

0

416,8

424

833,6

848

1250,5

272

1667,3

696

2084,2

12

2501,0

544

2917,8

968

3334,7

392

3751,5

816

-0,6

-0,4

-0,2

0

0,2

0,4

0,6

0,8

1

z

y

x

HC 02 surface A

0,8-1

0,6-0,8

0,4-0,6

0,2-0,4

0-0,2

-0,2-0

-0,4--0,2

-0,6--0,4

0

416,8

424

833,6

848

1250,5

272

1667,3

696

2084,2

12

2501,0

544

2917,8

968

3334,7

392

3751,5

816

0

-443,4

538

-886,9

076

-1330,3

614

-1773,8

152

-2217,2

69

-0,8

-0,6

-0,4

-0,2

0

0,2

0,4

0,6

z

x

y

HC 02 surface B

0,4-0,6

0,2-0,4

0-0,2

-0,2-0

-0,4--0,2

-0,6--0,4

-0,8--0,6

• measure HC surfaces

• place Sl on table, HC and spacers on SL and use a 200μm wire to find

correct spacers

Worst case example

Page 5: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Chamber Glueing II

[email protected] -CMS week 14-3-2005

1. Use glueing

machine to

deposit glue on

SL (~6 litres,

glue tube

thickness

~3mm)

2. place HC

3. deposit glue

on HC (same

procedure of

step 1)

4. Place SL, and

place a second

HC on top as

weight.

Time needed to glue one chamber: 1.5 days

Page 6: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of MB4 Production

[email protected] -CMS week 14-3-2005

Since 7th march two more people, are partecipating to chamber

assembly, thus providing the necessary help to reach the requested

rate of 3 chambers/month.

Starting from April we will aim to this target rate, but we still

have the problem of wire making, since the technician who should do

this job in Legnaro has not yet arrived.

HVB status: 300 new HVB delivered, enough for 6 chambers. 4

Chambers built so far with old HVB, we will need more HVB in one

month from now.

Page 7: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of MB4 Production

[email protected] -CMS week 14-3-2005

3Chambers @ CERN

6Completed Chambers

15Tested SL

18Assembled SL

19Mechanically finished

SL

Page 8: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Next deliveries

[email protected] -CMS week 14-3-2005

• 1st week of april 4 chambers to CERN (wheel YB+2 completed)

• 1st week of may 4 chambers to CERN (wheel YB+1 completed)

• 1st week of june 3 chambers to CERN (3 chambers for YB0)

Page 9: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Cosmic Test Stand

[email protected] -CMS week 14-3-2005

A B C

Scintillators:

16 (100*10*1 cm3) + 4 (200*20*1 cm3)

trg

Trigger timing resolution and spatial

uniformity: ~ 1 nsTrigger rate: ~ 55 Hz

4 CAEN V767 TDCs (1/2 ch or 1 SL)

Page 10: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Measurements

[email protected] -CMS week 14-3-2005

5 chambers (10 SLs) tested up to now:- check HV stability (SY1527 HV system)

- noise (random triggers)

- time boxes (visual check for bad HV contacts)

- MT (L/R) (preliminary)

- cell by cell efficiency (preliminary)

Running conditions:

(to be optimized)

HV 1800(S)/3600(A)/1200(C)

Thr=15 mV

p=10 mbar

Page 11: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Noise

[email protected] -CMS week 14-3-2005

Page 12: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Bad Cells

[email protected] -CMS week 14-3-2005

000008 (CH003)

000009 (CH005)

2 (110,350 Hz)

0

0

0

1 (140 Hz)

1 (380 Hz)

0

0

N.of cells with

noise > 100 Hz

1

0

0

0

1

2

1

1

Disconnected/

dead cells

1011 (CH005)

1010 (CH004)

0007 (CH004)

0005 (CH001)

0004 (CH003)

0003 (CH001)

3002 (CH002)

0001 (CH002)

N.cells with bad

HV connections

(cathodes)

SL n. (CH.

n.)

To be repaired

at CERN when

HVB will be

changed

~ 0,15 %

Page 13: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

MT

[email protected] -CMS week 14-3-2005 No 2 cutBest 4-hit fit track used, if in one column.

7 ns

Page 14: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Status of MB4 Production

[email protected] -CMS week 14-3-2005

MT123 R-L

MT234 R-L

Page 15: Status of Torino-Dubna Productionweb.physik.rwth-aachen.de/~reithler/talks_DT_050314CMSweek/DT_… · Status of Torino-Dubna Production CERN -CMS week 14-3-2005 amedeo.staiano@to.infn.it

Efficiency (preliminary)

[email protected] -CMS week 14-3-2005