Page 1: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

Status of the James Webb Space Telescope

Integrated Science Instrument Module

Ray Lundquist, NASA GSFC

Page 2: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 2

Collaborators

Michael P. Drury

Jamie L. Dunn

Stuart D. Glazer

Matthew A. Greenhouse

Ed Greville

Gregory Henegar

Eric L. Johnson

John C. McCloskey

Raymond G. Ohl

Pam Davila

Robert A. Rashford

Gurnie C. Hobbs

Scott Lambros

Doug McGuffey

Mark F. Voyton

Vicki Balzano

Juli 6, 2012

Page 3: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 3

JWST Full Scale Model at the Baltimore Inner Harbor

Juli 6, 2012

Page 4: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 4

ISIM Subsystems

The Integrated Science Instrument Module contains Four Science Instruments

NIRCam; NIRSpec; MIRI; and FGS/NIRISS

And the supporting Infrastructure Primary Structure

ISIM Electronics Compartment (IEC)

Harness Radiator (HR)

ISIM Command and Data Handling (ICDH)

ISIM Remote Services Unit (IRSU)

Thermal Control System (TCS)

ISIM Flight Software (IFSW)

On-Board Script System

And Electrical Harnessing

Purge Lines and GSE Panel

ISIM Structure

Thermal Straps

NIRSpec

IEC

Radiator Baffle

Electrical Harness and

Harness Radiator

Kinematic Mount

MIRI

NIRCam

Harness Radiator

Juli 6, 2012

Page 5: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 5

Instruments are being tested and delivered

NIRCam starting vacuum testing

FGS completing vacuum testing and ready for delivery

MIRI Completed testing and delivered to Integration and Test

NIRSpec fully tested, but re-build is needed

Juli 6, 2012

Page 6: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 6

Instrument Status

Instrument Current Testing

Upcoming Test

Delivery Date

NIRCam Thermal/Cryo Vac Second thermal test and vibration at GSFC

November 12

NIRSpec Bench level assembly Full test program April 13

MIRI Post ship functional ISIM test program Delivered (May 12)

FGS/NIRISS Complete ISIM test program July 12

All NIR instrument detectors have a slow degradation process, called “hot pixels” which impacts sensitivity. Replacement detectors are being procured and will be replaced prior to the final ISIM system level test

Juli 6, 2012

Page 7: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 7

Structure

Structure delivered to I&T in 2011 after completing proof testing and cryo soak/cycle to survival temperatures

Fit check of MIRI STM and FGS ETU

Juli 6, 2012

Page 8: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 8

IEC Progress

IEC ready for acoustics test

Preparation for IEC thermal balance

test

Thermal balance and moisture capture test of the IEC vent

Juli 6, 2012

Page 9: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 9

Thermal Control System

NIRS-1ANIRS-1B

NIRS-2Assembly

NIRS-3Assembly

NIRS-4Assembly

NIRS-5Assembly

NIRSpec OA Strap - Example

Update to heat strap routing following the Return-to-Green effort

13 of 30 heat straps systems have been delivered to ISIM

Juli 6, 2012

Page 10: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 10

Electronics

ISIM remote services unit (IRSU) has been

delivered and are undergoing integration

verification testing

Both ISIM command data handling

(ICDH) units are delivered. They have completed

integration testing and are ready to

support ISIM integration and test

Juli 6, 2012

Page 11: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 11

Harnesses and Harness Radiator

Electrical harnessing All detector interface harnesses complete and delivered

Flight or test versions of all instrument interface cables have been completed. Final flight builds are continuing.

Aluminum Radiator Panels

Two-layer Aluminum meteoroid shields; outer layer is radiating surface

IEC (hot)

Sis – cold side

Meteoroid shield removed to show harness routing/clamps

No assembly picture yetAll piece parts received and

assembly has begun

Juli 6, 2012

Page 12: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 12

Software

ISIM Flight Software Core software build 12.6 is complete and

tested

Initial version of all Science Instrument software applications have been successfully integrated with the Core

Updated versions of instrument software expected with instrument delivery

Modification of detector read-out schemes under investigation to reduce/improve system noise

1553 CTPBus (HK)

SpW p2p BusSSR (BIC)

SpW FPEBus (BIC)

1553 ICEBus (HK)

Direct I/O(HK)

FPAP-1 FPAP-2 FPAP-3

Power PC Processor Serial I/O TimersVolatileMemory

Non-VolatileMemory

cPCI Local Bus

Physical Layer

OS Services

System Support Services

Command andTelemetry Services

Applications

Operating SystemVxWorks

H/WInit

BSP ISRNon Volatile

DriverTimer Driver

Serial I/ODriver

cPCIDriver

SI Command & Telem I/FSpaceWire

Spacecraft (CTP) I/F1553

Data Acquisition(SpaceWire SSR/I/F)

Data Acquisition(FPAP I/F)

Direct I/OI/F

Non-Volatile Load Time Management SchedulerResource Health

and SafetyICE Interface 1553

CommandManagement

TelemetryManagement

StoredCommanding

Telemetry Monitoringand Response

Memory/TableLoad and Dump

File Management(CFDP)

NIRSpec FPE Application SW

NIRSpec MSSApplication SW

Script Processor Data Acquisition

NIRSpec ICEApplication SW

NIRCamApplication SW

MIRI ICE/FPEApplication SW

MIRI CoolerApplication SW

TFIApplication SW

FGSApplication SW

Juli 6, 2012

Page 13: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 13

Test Systems

Optical simulator (OSIM) being installed in the test chamber

Juli 6, 2012

Page 14: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 14

Test Systems

ISIM level full system test configuration

Juli 6, 2012

Page 15: Status of the James Webb Space Telescope Integrated Science Instrument Module Ray Lundquist, NASA GSFC

8442-92 SPIE ISIM Status 15

Summary

ISIM subsystem development is progressing well

First cryo-vacuum test planned for March 13, without NIRSpec. Two cryo-thermal tests planned with NIRSpec

NIR detector replacement plans are being developed

Test equipment, facilities, and plans are in place for a successful ISIM test program

Juli 6, 2012