1 ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade [CINEL] ESLS Meeting 2013 KIT – ANKA 21 st – 22 nd November Status of the ESRF operation & upgrade J. Jacob on behalf of the Accelerator & Source Division Thanks to J.-L. Revol and P. Raimondi for providing many of the slides

Upload: others

Post on 31-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

1ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade

[CINEL]

ESLS Meeting 2013KIT – ANKA

21st – 22nd November

Status of the ESRF operation & upgrade

J. Jacobon behalf of the

Accelerator & Source Division

Thanks to J.-L. Revol and P. Raimondi for providing many of the slides

Page 2: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Third generation light sourceLocation: Grenoble, FranceCooperation: 19 countriesAnnual budget: 100 million €Staff: 600Start User Mode 1994

Energy 6.04 GeV

Multibunch current 200 mA

Horizontal emittance 4 nm

Vertical emittance 4 pm

844 m circumference storage ring DBA lattice, 32 straight sections

42 Beamlines (including 12 on Bending Magnet BL)

The European Synchrotron Radiation Facility

10 Hz Booster

Synchrotron

200 MeVElectron

Linac

Availability: 98.83 %Mean Time Between Failures: 77.7 hours

Average over the last 4 years

• More than 6000 annual user visits• 1800 publications every year

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 2

Page 3: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

90%

91%

92%

93%

94%

95%

96%

97%

98%

99%

100%

2008 2009 2010 2011 2012 2013

98,30%99,04% 98,78% 98,91% 98,58% 98,69%

1,70%0,96% 1,22% 1,09% 1,42% 1,31%

Perc

enta

ge o

f ava

ilabi

lity

Years

Accelerator Availability

ESRF record

In progress

Always greater than 98.5 % !

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 3

Operation performance

Page 4: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

0

20

40

60

80

100

64,5

75,8

67,5

107,8

60,0

69,4

1,1 0,7 0,8 1,2 0,9 0,9

Hou

rsMean Time Between Failures

Mean timeper failure

ESRF record

In progress

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 4

Operation performance

Page 5: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Operation performance

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 5

Page 6: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

@ Phase I (from 2009 to 2015)

Eight new beamlines Extension of the experimental hall Refurbishment of many existing beamlines Developments in synchrotron radiation

instrumentation Upgrade of the X ray source for

availability, stability, capacity and brilliance

The Upgrade Programme

@ Phase II (from 2015 to 2019)

Four new beamlines Developments in instrumentation and support facilities Increase the brilliance and the coherence of the source implementation of a low emittance lattice horizontal emittance reduced from 4nm to 150pm

• Project endorsed by ESRF council in November 2012• Technical Design Study (TDS) by June 2014

New buildings available

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 6

ID16

Page 7: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

7ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade

Accelerator Upgrade Phase I

• Upgrade of BPM electronics• Improvement of the beam position stability• Coupling reduction

• 6 m long straight sections• Cryogenic in-vacuum undulators• 7 m straight sections

• New RF SSA Transmitters

• New RF Cavities

• Top-up operation

• Studies for the reduction of the horizontal emittance

Done Done (z = 4 pm)

Two CPMUs installed Done (cell 23 in winter 2012)

4 in operation on booster 2 in operation on SR cell 23

2 in operation on 7 m cell 231 more beginning of 2013

Done (8 operational)

Ongoing project

TDS in progress

7 metre ID23

7 metre ID23

Done

CPMU

Single cell HOM damped cavity

SSA

Standard cell

6 metre straight

Page 8: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Top up project (phase 1)Tested in September 2013 with users to determine the optimum injection rate: • Every 10 to 20 min = good

compromise between small heat load variation

and minimum injection disturbance

Phase 1 project for end 2015• Linac and Injection/Extraction

refurbishment: in progress• Fast booster injection kicker: in project• Resonant cleaning in the booster: in

progress• Ramped booster power supplies (4 Hz):

in project• RF solid state amplifiers in the booster:

since March 2012• 2 4 five-cell cavities in project

16 bunch filling (life = 12 h)with artificial vertical beam blow up to increase lifetime

At ESRF: Top up largely beneficial for time structured fillings with high current per bunch, penalised by short lifetime

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 8

Top up every 10 min, 20 min, 30 min

Page 9: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

917th ESLS RF, Berlin, 18-19 September 2013 J. Jacob: Status of the ESRF RF upgrade

Booster

RF upgrade phase 1Storage Ring

Cell 5Cav 1 & 2

Cell 7Cav 3 & 4

Teststand

Klys1 Klys2

SY Cav 1 & 2

150 kW

150 kW

150 kW

150 kW

pulsed

Replacement of Booster Klystron by: 4 X 150 kW SSAs from ELTA / AREVA: In operation since March 2012

10 Hz pulses / 30 % average/peak power

1 common 280 V dc / 400 kW power supply

3.2 F anti-flicker & smoothing capacitor banks: Wall plug power: 400 kW instead of 1.2MW

3 X 150 kW SSA from ELTA Powering 3 new HOM damped

cavities on the storage ring

1st SSA to power 1 cavity since August 2013

2 SSAs / 2 cavities active in normal operation since October 2013

3rd SSA+Cavity: January 2014

150 kW150 kW

Cell 23, length 5 m 7 m

prototype HOM damped cavities … 2 cavities tested with beam

in 2011-2013 on cell 25 with klystron transmitter TRA3

150 kW

… 3 prototype HOM damped cavities August 2013: 2 cavities in

new 7 m section/cell 23

December 2013: installation of 3rd cavity

Page 10: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

1017th ESLS RF, Berlin, 18-19 September 2013 J. Jacob: Status of the ESRF RF upgrade

HOM damped cavities for upgrade phases 1 & 2

3 functional cavities in house from RI, CINEL and SDMS

12 additional cavities in procurement in the frame of phase 1 : proposals for the next cavities

in house order to be placed coming

weeks delivery scheduled end 2015

-------

15 cavities: 14 for the ring and 1 spare

Phase 1 (existing lattice): 14 HOM damped

cavities + 2 five-cell cavities for more stability & more robust RF working points

Phase 2 (low emittance ring):• 14 HOM damped

cavities mandatory for stability !

Page 11: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Strategy – RF transmitters

• 150 kW SOLEIL – ELTA SSAs with coaxial combiners: 4 units on the booster (March 2012) 3 units on the SR will (last one in operation from

January 2014) to feed 3 new cavities

• Remaining HOM damped cavities could be started with power from existing klystron transmitters

• Ongoing ESRF in house development of SSAs Successful test of first 12 kW prototype SSA using a

cavity combiner (funded by EU under FP7/ESFRI/CRISP)

Next step: 75 … 100 kW prototype

• Gradual implementation of more SSAs envisaged in longer term

1117th ESLS RF, Berlin, 18-19 September 2013 J. Jacob: Status of the ESRF RF upgrade

352 MHz 1.3 MW Klystron

Thales TH 2089

Page 12: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Accelerator Upgrade Phase II

• Reduce the horizontal equilibrium emittance from 4 nm to 150 pm• Maintain the existing ID straights and beamlines• Maintain the existing bending magnet beamlines• Preserve the time structure operation and a multibunch current of 200 mA• Keep the present injector complex• Reuse, as much as possible, existing hardware• Minimize the energy lost in synchrotron radiation • Minimize operation costs, mainly wall-plug power• Limit the downtime for installation and commissioning to about one year.

A recurrent request from ESRF beamlines: reduction of the horizontal emittance … … with the strong constraint of re-using the same tunnel and infrastructure

Thanks to the worldwide efforts made to develop an Ultimate Storage Ring,the ESRF is re-addressing the question, with the following requirements:

Present DBA lattice

Future7 bend lattice

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 12

Page 13: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Low Emittance Rings Trend

APS II

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 13

Page 14: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Bleu: Dipoles Red: Quadrupoles Green: sextupoles

The ESRF low emittance lattice

Present ESRF latticeDouble Bend Achromat

x = 4 nm.rad

Proposed hybrid 7 Bend Lattice x = 150 pm.rad

@ 7 bending magnets D1to7 reduce the horizontal emittance

@ Space between D1-D2 and D6-D7β-functions and dispersion allowed to grow

chromaticity correction with efficient sextupoles

@ Dipoles D1, D2, D6, D7 longitudinally varying field to further

reduce emittance

@ Central part alternating combined dipole-quadrupolesD3-4-5high-gradient focusing quadrupoles

@ D4 end (0.34T) and D5 entrance (0.85T) Source points for BM beamlines Alternative under study: replace BM

sources by short wigglers for simpler dip/quad design

Ongoing optimization of the Lattice !D1 D2 D6 D7D3 D4 D5

20

20

60

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 14

40

0

10

0

[m]

[m]

Page 15: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

The ESRF low emittance lattice

@ 2 quadrupoles on each side of the straight section

provide in the middle (last version S25):x = 4.80 mz= 2.58 m

@ Special injection cell with a larger x

• Same total cell phase advances, same sextupole configuration ⇒ Minimum symmetry breaking

• 2 kickers at phase advance• No sextupole inside the injection bump ⇒ no

perturbation of the stored beam

@ ID’s at same location frf = + 150 kHz

@ Dynamic aperture large enough to: Use the same injector complex

( implementation of frf = + 150 kHz)

Injection section

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 15

Proposed hybrid 7 Bend Lattice x = 150 pm.rad

Page 16: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Brilliance at lower horizontal emittance

E = 6.04 GeVI = 200 mA

Hor. Emittance [nm] 4 0.15

Vert. Emittance [pm] 3 2

Energy spread [%] 0.1 0.09

x[m]/z [m] 37/3 4.3 / 2.6

1015

1016

1017

1018

1019

1020

1021

1022

1023

Bril

lianc

e [P

h/s/

0.1%

bw/m

m2 /m

r2 ]

3 4 5 6 7 8 91 keV

2 3 4 5 6 7 8 910 keV

2 3 4 5 6 7 8 9100 keV

Photon Energy

1.6 m W150

4 m Helical U88

3.2 m U42

4.8 m U35

4 m CPMU18

Present lattice (plain) New lattice (dashed )

0.85 T bending magnet

4 m CPMU14

x 30

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 16

Page 17: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Coherence at lower horizontal emittance

Hor. Emittance [nm] 4 0.15

Vert. Emittance [pm] 3 2

Energy spread [%] 0.1 0.09

x[m]/z [m] 37/3 4.3 / 2.6

10-5

10-4

10-3

10-2

10-1

100

Coh

eren

t Fra

ctio

n []

3 4 5 6 7 8 91 keV

2 3 4 5 6 7 8 910 keV

2 3 4 5 6 7 8 9100 keV

Photon Energy [keV]

4 m helical U88

4 .8 m U35

4 m CPMU18

Present lattice (Plain)New lattice (dashed)

E = 6.04 GeVI = 200 mA

x 30x 4

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 17

Page 18: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

18ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade

• Low emittance ring: same operation modes as existing machine

(preliminary) Multibunch 16-bunches 4-bunchesTotal current [mA] 200 90 40Nb. Bunches 868 16 4Bunch length [ps] 23 61 73Lifetime [h] 12 2 1.5

Lifetime & longitudinal stability

Top up developed in phase 1 will be mandatory for phase 2

• New lattice twice as sensitive to HOM driven LCBI as existing machine:

HOM damped cavities developed in phase 1 are mandatory for phase 2

Page 19: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Technical challenge: magnet system

High gradient quadrupoles 100 Tm-1

• Spec:100 T/m x 335 mm• Bore radius: 11 mm • Mechanical length: 360 mm• 1-2 kW Quadrupole

Around 60Tm-1

Combined dipole quadrupoles0.85 T / 45 Tm-1 & 0.34 T / 50 Tm-1

Sextupoles200 mm2B/dx2 = 3000 Tm-2

Permanent magnet (Sm2Co17) dipoleslongitudinal gradient 0.16 0.6 T, magnetic gap 22 mm,2 metre long, 5 moduleswith a small tuning coil ± 2 %

D1

D2

D6

D7

D3D4

D5

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 19

Page 20: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Magnet design status

• Dipole, quadrupole, sextupole and octupole are well advanced• Combined dipole-quadrupole in progress• Prototyping will start soon

PM dipole module High gradient quadrupole OctupoleSextupole

Technical challenge: magnet system

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 20

Page 21: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Technical challenges: compactness

7 bend lattice

@ Energy efficient source: 30% less power consumption of the SR:• Increase efficiency of the production of magnetic field• RF systems tailored to the reduced losses per turn from 5.4 to about

3.6 MeV/turn, including 0.5 MeV ID radiation

@ Vacuum: • Low vacuum conductance due to reduced aperture of the chambers• Main chambers presumably made from stainless steel with NEG coating

with localised pumping • Lumped absorbers to collect the radiation from dipole magnets

@ Mechanical design very challenging due to the compactness• only 3.4 metre of drift tube per cell instead of today’s 8m

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 21

Page 22: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Implementation

Present DBA lattice

Future7 bend lattice

Use the hall later for long beamlines and support facilities

@ Extension of the experimental hall to provide • 2500 m2 of preparation and storage area

@ Dismount and reconstruct the whole storage ring in about9 months - in 3 sliding parallel working areas

+ 3 months start up and commissioning

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 22

Page 23: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Road map

Budget: 100 M€ Implementation of the new storage ring lattice10 M€ Extension for the experimental hall20 M€ Four state of the art beamlines20 M€ Instrumentation and support facilities

Schedule:◊ Nov 2012 White paper

Nov 2012- June 2014 Technical Design Study◊ Nov 2014 Council decision

Jan 2015 – Aug 2018 Detailed design and procurement◊ End 2016 Preparation and storage building

Aug 2018– Aug 2019 Shutdown for installation and commissioning◊ Autumn 2019 Back to operation

TDS in progress Done

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 23

• First APAC Meeting held on 5-6 September 2013.

• Very positive and constructive event

• 3 APAC Meetings foreseen in 2014 (first on January 23-24)

Page 24: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

Present DBA lattice

Future7 bend lattice

Conclusion

Thanks to: • the large expertise gained during ESRF UP phase 1 • and the worldwide efforts to develop Diffraction Limited Storage Rings,

ESRF Upgrade Phase II will be an excellent opportunity to:• drastically increase the brightness of our Light Source before 2020and also:• improve and expand the science reach of the SR-based light sources• enable new technologies• provide important know-how to continue the push for higher performances in SR-

based Light Sources

ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 24

Page 25: Status of the ESRF operation & upgrade - KIT · 2013-12-05 · ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade 1 [CINEL] ESLS Meeting 2013 KIT – ANKA

25ESLS, Karlsruhe/KIT, 21-22 November 2013 J. Jacob: Status of the ESRF upgrade

Thank you !!