Page 1: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 2: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

OUTLINE

Background Requirements Test results Future tests

Please note information is limited until Hitachi present results in SC conference in September this year

Page 3: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

Background and ObjectivesWall plug to RF efficiency

Pushing modulator designers to decreaseRise time and fall time

Wasted energy!

Recent ongoing program to increase klystron efficiency

from ~44% to >>65%Reduces power requirements and cost of modulators

What about solenoid power consumption ?

Page 4: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 5: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

Collaboration between CERN, KEK and Japanese Industry (Hitatchi)Plus input from SLAC and CPI

Page 6: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 7: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 8: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 9: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 10: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 11: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 12: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 13: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 14: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 15: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 16: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 17: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements
Page 18: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

Acceptance test completed successfully at Hitachi15 February 2019

Page 19: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

Normal conducting Bucking coil to be installed before klystron assembly(Given to CERN for tests by CPI)

Page 20: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

• Magnet now at CERN• Will confirm magnetic

measurements in coming weeks• Waiting for ‘warm’ counter coil

• Collaboration with Scandiova• Removal of ‘warm’ solenoid

power supplies from Xbox2 modulator

• Integration of SC magnet interlocks and power supplies

• Integration of klystron with SC magnet and modulator

Full results will be presented in SC magnet conference in September

Page 21: Status of our X-band klystrons€¦ · Bucking coil to be installed before klystron assembly (Given to CERN for tests by CPI) • Magnet now at CERN • Will confirm magnetic measurements

14 - 15 September 2019

Thank you for your attention