stage gate approach towards project management training event on ppp programming and process...

26
Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko AJ Ramstedt Senior Project Adviser Financial Partnerships Unit

Upload: shayne-mars

Post on 31-Mar-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage Gate approach towards project management

Training event on PPP programming and process management 27 May 2008

Twinning Project CZ/2005/IB/FI/04

Mikko AJ RamstedtSenior Project Adviser

Financial Partnerships Unit

Page 2: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Introduction

• Background

• Stage Gate approach

• The need for Process discipline

• PPP vs. conventional projects

• Resource planning

Page 3: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Background

• Why is PPP different?– Contracted outputs

• Fixed• Performance & availability requirements

– Concession• Longevity• Contractually defined obligations – limited flexibility• Mutual liability• Incentives

Page 4: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Background

• PPP programming and process management– 6 stage process:

• Conception• Development• Procurement• Construction• Operation• Handback

– Each element has a number of sub-stages

Page 5: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Background

• PPP process– Resource intensive (at all levels)– ‘Front loaded’ inputs– Long lasting consequences

• Accountable bodies need an effective way of tracking projects and monitoring risks.

Page 6: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Principles

• Self-assessment tool• Expert independent review• Guard central government investment

– Mandatory for Scottish Government Departments & Agencies & PPP projects receiving central funding or requiring central approval.

• Maintain local accountability• Accumulation of sector specific & market

experience

Page 7: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Purpose

• Establish clear and transparent criteria for project evaluation

• Audit projects at key stages• Consistency of review / control• Reassurance to public sponsors• Reassurance to market: minimum standards • Develop best practice• Share lessons learnt

Quality Assurance

Page 8: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Context 1

Top 10 risks that have materialised during

PPP procurements:

• Land acquisition

• Site ownership

• Planning permission

• Lack of consensus among stakeholders

Page 9: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Context 2

• Affordability

• Lack of competition

• Project scope unstable

• Unsecure bid price

• Commercial agreement

• Due diligence “unforeseens”

Page 10: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko
Page 11: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach

Process - at each review:1. Submission2. Clarifications & Independent review against

set criteria 3. Independent recommendations

• Essential vs. desirable

4. Response / action to recommendations5. Central Government review of actions taken

• No action –> HOLD / STOP• Positive action –> GO

Page 12: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Outline Business Case

Sound fit between need, policy and project scope:

• Clear demonstration of need, full options appraisal, comprehensive VfM assessment over procurement routes, project is affordable within relevant sensitivities and key deliverability issues have been identified.

Page 13: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Gate 1 - Pre-OJEU notice

Readiness to go to market:

• Governance• Scope• Stakeholders• Competition• Procurement Risks• VfM Assessment

Page 14: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Gate 2 - Pre-Invitation to Participate in Dialogue

Readiness to go to start dialogue and conductnegotiations which will secure high quality, sustainablebids, with minimal bidder qualifications:

• Affordability• VFM• Commercial Issues• Deliverability• Data Room and background Information

Page 15: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Gate 3 - Pre-Invitation to Submit Final Tenders

Is there sufficient technical and commercial certainty to end competition?

• Affordability• VfM• Risk transfer• Commercial / Legal Funding issues• Technical solution• Deliverability

Page 16: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Gate 4 - Pre-Preferred Bidder appointment

Ensure projects have minimised opportunitiesfor ‘deal creep’ and reallocation of risk:

• Affordability• Financial / Risk issues• Commercial / Legal issues• Technical issues• Deliverability

Page 17: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Gate 5 - Pre-Financial Close

To assist Authorities in considering whatneeds to be put in place in terms of staffing andresources ahead of the construction and operationalstages of their PPP projects, to support and managetheir PPP contract going forward:

• Contract management & Governance• Payment Mechanism• Stakeholder management

Page 18: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Focus

Post Occupation Evaluation

Has the project delivered its strategic project

objectives?

• Reflection

• Documenting & disseminating lessons learnt

Page 19: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Stage-Gate approach: Options

• Peer review

• Independent review

• Ownership• Central requirement & local accountability• Avoid conflicts of interest

Page 20: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

The need for process discipline

• Maximise VfM• Market confidence• To counter external pressure• Minimise procurement cost & time

– Time = money– Every change requires resources and time

• Individual responsibility to meet the critical path really is critical!

Page 21: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

PPP vs. conventional projects

• Differences process controls are necessary because:

– New forms of project delivery require a higher degree of scrutiny

– Fixed risk transfer impacts on available mitigation strategies resulting a need to manage future liabilities

– Public-Private relationship regulated through a single contract resulting in a greater interdependency within the public sector

– Projects often negotiated with a highly developed and competitive market requiring an increased level of delegated authority.

Page 22: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Resource planning 1

Get it right from the start!

• Each of the 6 stages have different resource requirements

– Conception – technical, financial– Development – management, commercial (L/F/T),

specialist input– Procurement – management, specialist commercial– Construction – management, monitoring, specialist

technical– Operation – management, monitoring– Handback – monitoring, specialist technical

Page 23: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Resource planning 2

Competitive Dialogue issues:

– A number of separate but parallel negotiations– Each bidder may come up with different

technical solutions needing specialist advice to the authority

– Financial, legal and technical input requirements increase inline with the number of bidders

Page 24: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Resource planning 3

• Resource Planning is key for successful project delivery

• Upfront investing into a long term partnership

• Continuity is key for successful delivery of benefits and continuous improvement

• Project Management requirement does not end at FC!

Page 25: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Summary

• A well structured Stage Gate -type review process in an invaluable project management & monitoring process and can help in market creation.

• In order to deliver successful outcomes all PPP projects should prepare a resource management plan covering the period from project development to handback.

Page 26: Stage Gate approach towards project management Training event on PPP programming and process management 27 May 2008 Twinning Project CZ/2005/IB/FI/04 Mikko

Mikko AJ Ramstedt

[email protected]

0131 244 4940

Questions?