st marys bay and masefield beach improvement project ... · legend: preferred pipeline route...

7
St Marys Bay and Masefield Beach Improvement Project – Overview Auckland Council Healthy Waters team, in conjunction with Watercare and Panuku propose to undertake a major infrastructure project to reconfigure the existing combined sewer and stormwater network at St Marys Bay and Masefield Beach as the first step in a programme to improve water quality and remove combined sewer overflows from Auckland’s Beaches. We plan to lodge for Resource Consents this year and start building next year – making tangible improvement by 2021. A. Why are we doing it? The historic combined stormwater and wastewater network utilised in St Marys Bay and Herne Bay catchments is designed to over flow from time to time but today existing outfalls discharge frequently to local beaches St Marys Bay and Masefield Beach. The outfall at St Marys Bay discharges at the shoreline and one outfall at Masefield Beach is broken and needs replacing. We are undertaking this project in order to make tangible progress in improving water quality for these local environments, to make an overall reduction in combined sewer overflows to the Harbour and to pave the way for future improvements that will further improve water quality. This project came out of the programme of work that was undertaken last year between Healthy Waters, Watercare, Panuku, Auckland Transport and members of the Panuku Mana Whenua forums. B. How will it work? The project works by collecting flows from London Street and Hackett Street near St Marys Bay and Sarsfield Street near Masefield Beach in new pipelines which terminate in a common collection point near Pt Erin. The pipeline from St Marys Bay is big enough that it can store flows so that these can be returned to the main sewer when it has capacity. A new outfall will be constructed from the common collection point so that flows can be safely discharged to the harbour when there is no spare sewer capacity. The project is being designed so that it will integrate into long-term network improvement plans being developed by Watercare and Healthy Waters, which will further reduce combined sewer overflows and improve water quality The next page shows more detail of how the project will work when it is built. .

Upload: others

Post on 30-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

St Marys Bay and Masefield Beach Improvement Project – Overview

Auckland Council Healthy Waters team, in conjunction with Watercare and Panuku propose to undertake a major infrastructure project to reconfigure the existing combined sewer and stormwater network at St Marys Bay and Masefield Beach as the first step in a programme to improve water quality and remove combined sewer overflows from Auckland’s Beaches. We plan to lodge for Resource Consents this year and start building next year – making tangible improvement by 2021.

A. Whyarewedoingit?The historic combined stormwater and wastewater network utilised in St Marys Bay and Herne Bay catchments is designed to over flow from time to time but today existing outfalls discharge frequently to local beaches St Marys Bay and Masefield Beach. The outfall at St Marys Bay discharges at the shoreline and one outfall at Masefield Beach is broken and needs replacing. We are undertaking this project in order to make tangible progress in improving water quality for these local environments, to make an overall reduction in combined sewer overflows to the Harbour and to pave the way for future improvements that will further improve water quality. This project came out of the programme of work that was undertaken last year between Healthy Waters, Watercare, Panuku, Auckland Transport and members of the Panuku Mana Whenua forums.

B. Howwillitwork?The project works by collecting flows from London Street and Hackett Street near St Marys Bay and Sarsfield Street near Masefield Beach in new pipelines which terminate in a common collection point near Pt Erin. The pipeline from St Marys Bay is big enough that it can store flows so that these can be returned to the main sewer when it has capacity. A new outfall will be constructed from the common collection point so that flows can be safely discharged to the harbour when there is no spare sewer capacity. The project is being designed so that it will integrate into long-term network improvement plans being developed by Watercare and Healthy Waters, which will further reduce combined sewer overflows and improve water quality

The next page shows more detail of how the project will work when it is built.

.

Page 2: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

St Marys Bay and Masefield Beach Improvement Project – Overview

How does it work?

1. A new collector system takes overflows from the existing Hackett, London and New Street overflows and conveys them to a new connection near Pt Erin Park (black and yellow).

2 New collector pipes take the existing Sarsfield Street overflows to the same point (pink)

3 A new pump station at this point returns low flows back to the main branch 5 sewer (blue)

4 A new marine outfall (to replace the existing outfall) is used to discharge high, dilute flows to the receiving environment (light blue).

What are the benefits?

The number of overflows at St Marys Bay is reduced from around 70 per year to around 2 – 4 per year

The number of overflows at Masefield Beach is reduced from around 70 per year to zero.

The new outfall will discharge in high rainfall events around 30 times per year.

Page 3: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

St Marys Bay and Masefield Beach Improvement Project – Overview

C. Whatwillitachieve?

The project will work in two ways. Firstly, it will resolve the issues of overflows to both of these local beaches by replacing the existing old outfalls with a single new outfall that will discharge much further out in the harbour, away from the beaches. Secondly, the project will also significantly reduce the total number of overflows to the harbour by returning low flows to the main sewer when spare capacity (or ‘room’) is available to take extra flow.

• It will reduce combined sewer overflows to St Marys Bay from over 70 per year to around 2 – 4 per year • It will reduce combined sewer overflows to Masefield beach from over 70 to zero per year • It will replace the existing old outfalls at Masefield Beach with a single new outfall • This new outfall will discharge away from all beaches out into the Harbour. This new outfall will discharge around 30 times per year • The project will be a first step towards overall improvement of the combined sewer network (which will reduce overflows from other locations ) and it can

work with any future solution that is proposed for the wider network.

Howwilloverflowsbereduced?• The overflows can be reduced because there is a large storage volume in the tunnel between St Marys Bay and Pt Erin. This means that the overflows can be

stored in the tunnel until there is enough spare capacity in the main sewer to return the flows there, where they can be taken to Mangere Wastewater Treatment Plant to be treated.

• When there are very high rainfall events (such as those Auckland experienced during March) then the outfall will discharge out into the harbour. There will still be a small amount of wastewater in this discharge.

Howwilltheremainingoverflowschange?• There will be fewer overflows – so stormwater and wastewater will enter the harbour much less often than it does now • The overflows will be screened – so they will have some degree of treatment before discharging • Because of the storage and return component, the total annual load of wastewater to the receiving environment will be reduced

o It is very difficult to accurately quantify the different amounts of wastewater and stormwater in any one overflow because this depends on so many different variables – how much rain there is, how full the sewer was at the time, if there are any blockages, if there are other flows in the network causing problems etc. It is more useful to think in overall terms that the total load will be reduced.

Whatwillhappeninthelong-term?• We are replacing infrastructure that is up to 100 years old. The infrastructure built as part of this project will be part of Auckland’s water infrastructure for the

long-term, either as part of an improved combined network or as stormwater-only infrastructure. As additional projects are undertaken to improve the situation, this project will become part of the wider solution.

Page 4: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

D. Whereexactlywillitbebuilt?The Healthy Waters team has spent some time looking at where it could be possible to build all this new infrastructure. In particular, we have been looking at how we could construct the various parts of the project safely, minimising impacts on the community and the environment. We have also needed to consider the safety of our operations team and ongoing impacts on the community and environment once the infrastructure is commissioned.

We now believe that we have enough meaningful information to seek feedback from the community. Part of this is looking at the location of the main pump station near Pt Erin and where the new outfall could go. The next pages show the options we are considering.

• The first sketch shows one overall alignment from London St through to Pt Erin. There are not many options for the pipe between London St and St Marys Reserve due to the lack of space.

• The next sketch shows potential options for the final pump station and collection shaft. The route of the pipeline between St Marys Reserve and Pt Erin is determined by this pump station location. The Healthy Waters team prefers the northernmost location as it is the safest from a construction and operations perspective and has the least impact on neighbouring communities.

• The final sketch shows options for the new marine outfall. The Healthy Waters team prefers the ‘blue’ option that discharges out by the Harbour Bridge. This is because there is the least amount of construction in the marine environment, this option avoids existing mussel beds and at this stage it looks the easiest and safest to construct.

No final decisions have been made and feedback is sought at this stage.

Page 5: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

SHELLY BEACH RD

AMIR

IA S

T

EMMET

T ST

HACKETT ST

PERC

IVAL

PAR

ADE

RING TERRACE

LONDON ST

ST MARYS RD

CURR

AN S

T ON

RAM

P

CLIENT

DATE TITLE

REVISION DETAILSDATEREV APPROVED

CHECKED

APPROVED

PROJECT

DRAWN

DESIGNED

PROJECT No. TYPE REVWBS DISC NUMBER DRAWING No.

SCALE SIZEA1

.

ST MARYS BAY

GENERAL ALIGNMENT

255303 0000 DRG CC 1002 A

1:1500PRELIMINARY

NOT FOR CONSTRUCTION

M. TUIKOLOVATU

M. COBELDICK

A FOR CONSULTATION

Filen

ame:

Plot

Date:

Offic

e:P:

\2000

00-B

ST\25

5303

- HA

CKET

T DI

VERS

ION\

5 DEL

IVER

DES

IGN\

504 C

ADD\

DWG\

2553

03-0

000-

DRG-

CC-1

011.D

WG

24/5/

2017

1:20

:51 P

MNZ

AKL

LEGEND:

PREFERRED PIPELINE ROUTE TRENCHED

PREFERRED PIPELINE ROUTE DRILLED

SARFIELD St. CONNECTIONS TRENCHED

SHAFT LOCATIONS

MANA WHENAU AREA OF SIGNIFICANCE

PROPOSED PUMPSTATION

015 30 60m

SCALE 1:1500

Sketch 1 – Overview of the pipelines

Page 6: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

CLIENT

DATE TITLE

REVISION DETAILSDATEREV APPROVED

CHECKED

APPROVED

PROJECT

DRAWN

DESIGNED

PROJECT No. TYPE REVWBS DISC NUMBER DRAWING No.

SCALE SIZEA1

.

ST MARYS BAY

GENERAL ALIGNMENT

255303 0000 DRG CC 1015 A

1:1000PRELIMINARY

NOT FOR CONSTRUCTION

M. TUIKOLOVATU

M. COBELDICK

A FOR CONSULTATION

File

na

me

:P

lot

Da

te:

Off

ice

:P

:\2

00

00

0-B

ST

\25

53

03

- H

AC

KE

TT

DIV

ER

SIO

N\5

DE

LIV

ER

DE

SIG

N\5

04

CA

DD

\DW

G\2

55

30

3-0

00

0-D

RG

-CC

-10

15

.DW

G2

4/5

/20

17

1:2

4:0

9 P

MN

ZA

KL

0

SCALE 1:1000

10 40m20

LEGEND:

PREFERRED PIPELINE ROUTE

ALTERNATIVE PIPELINE ROUTE

MANA WHENAU AREA OF SIGNIFICANCE

EM

METT S

T

AM

IRIA

ST

SHELLY BEACH RDC

UR

RA

N S

T O

N R

AM

P

PUMP STATION 1

PUMP STATION 2

PUMP STATION 3

Sketch 2 – Options for the new pump station and tunnel shaft

Page 7: St Marys Bay and Masefield Beach Improvement Project ... · legend: preferred pipeline route trenched preferred pipeline route drilled sarfield st. connections trenched shaft locations

-14.00 -14.00

-13.00-12.00

-11.00

-11.

00

-11.00-11.00

-11.00-11.00

-11.00

-11.00

-10.00

-10.00

-10.00

-10.00

-10.00

-10.00

-10.00

-9.00

-9.0

0

-9.00

-9.0

0

-9.00

-9.00

-9.00

-9.00

-8.00

-8.00

-8.00

-8.00 -8.00

-8.00

-8.00-8.00

-8.0

0-8.

00

-8.00

-8.0

0

-7.00

-7.0

0

-7.00

-7.00

-7.00

-7.00

-7.00

-7.00

-7.00

-6.00

-6.00

-6.00

-6.00

-6.00

-6.00

-6.00

-5.0

0-5

.00 -5.0

0-5.00

-5.00

-5.00

-5.00

-5.00

-5.00

-5.00

-5.00

-5.00-5.00

-5.00

-5.00

-5.00 -5.00

-5.00

-4.00

-4.0

0

-4.00

-4.00

-4.00

-4.00

-4.0

0

-4.00

-3.00

-3.00

-3.0

0

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-3.00

-2.00-2.00

-2.00

-2.0

0

-2.00

-2.00

-2.00

-2.00

-2.00

-2.00

-2.0

0-2

.00-2.00

-2.00

-2.00

-2.00

-2.00-2.00

-2.0

0

-2.00

-2.00

-2.00 -2.00

-2.00

-2.00-2.00 -2.00

-2.0

0

-2.00 -2.00

-2.00-2.00

-2.00

-2.0

0

-2.00

-2.00

-2.00

-2.00-2.00-2.00

-2.00

-2.00

-2.00

-2.00

-2.00-2.00

-2.00-2.00

-2.0

0-2.

00

-2.00

-2.00

-2.00

-2.00

-2.00

-1.00

-1.00

-1.00

-1.00

-1.00-1.00

0.00

0.00

0.00

0.00

0.00

0.00

1.00

1.00

1.00

1.00

1.001.00

1.00 2.00

2.00

2.00

2.00

2.00

2.00

2.00

3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.003.00

3.00

3.00

3.00

3.00

3.003.003.

003.0

0

3.00 3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.00

3.003.00

3.00

4.00

4.00

4.00

4.00

4.00

4.00

4.00

4.00

4.00

4.00

4.004.00

4.00

5.00

5.00

5.00

5.00

5.00

5.00

5.00

5.00

6.00

6.00

6.00 6.00

6.00

6.00

7.00

7.00

7.00

7.00

7.007.00

7.00

8.00

8.00

8.00

8.008.00

8.008.00

9.00

9.00

9.00

9.00

9.009.00

9.00

10.00

10.00

10.00

11.00

11.00

11.00

12.00

12.00

12.00

13.00

13.00

13.00

14.00

14.00

14.00

14.00

15.00

15.00

15.00

15.00

15.00

16.00

16.00

16.00

16.00

16.00

17.00

17.00

17.00

17.00

17.00

18.00

18.00

18.00

18.0

018

.00

19.00

19.00

19.0020.00

20.00

20.00

21.0021.00

22.00

22.00

23.00

24.00

25.00

25.00

26.00

27.00

SHELLY BEACH RD

CURR

AN S

T ON

RAM

P

POINT ERIN PARK SHAFT

SWMH3

SWMH2

SWMH1

OUTFALL

OUTFALL MH

OUTFALL

LEGEND:

MARINE PIPELINE DRILLED OPTION 1

MARINE PIPELINE TRENCHED OPTION 1

MARINE PIPELINE DRILLED OPTION 2

MARINE PIPELINE TRENCHED OPTION 2

MARINE PIPELINE DRILLED OPTION 3

MARINE PIPELINE TRENCHED OPTION 3

MANA WHENAU AREA OF SIGNIFICANCE

CLIENT

DATE TITLE

REVISION DETAILSDATEREV APPROVED

CHECKED

APPROVED

PROJECT

DRAWN

DESIGNED

PROJECT No. TYPE REVWBS DISC NUMBER DRAWING No.

SCALE SIZEA1

.

ST MARYS BAY

ST MARYS BAY CONCEPT DESIGNOUTFALL OPTIONS

255303 0000 DRG CC 1004 A

1:1500PRELIMINARY

NOT FOR CONSTRUCTION

M. TUIKOLOVATU

M. COBELDICK

A PRELIMINARYB FOR CONSULTATION

File

nam

e:Pl

ot D

ate:

Offi

ce:

\\AUR

ECO

N.IN

FO\S

HARE

S\NZ

AKL\

PRO

JECT

S\20

0000

-BST

\255

303

- HAC

KETT

DIV

ERSI

ON\

5 DE

LIVE

R DE

SIG

N\50

4 CA

DD\D

WG

\255

303-

0000

-DRG

-CC-

1004

.DW

G24

/5/2

017

1:56

:07

PMNZ

AKL

015 30 60m

SCALE 1:1500

Sketch 3 – Locations for the new outfall