st. elizabeths west campus transportation preserving the...
TRANSCRIPT
St. Elizabeths West CampusTransportationSt. Elizabeths West CampusTransportation
Preserving the Legacy │ Realizing PotentialPreserving the Legacy │ Realizing Potential
February 14, 2006
Transportation StudiesTransportation Studies
• Traffic Impact Study
• Transportation Management Plan
St. Elizabeths West Campus
Transportation TasksTransportation Tasks
• Assess Existing Roadway Conditions
• Project Background Conditions
• DDOT Projects
• Development Projects
• Secondary Site Access
• Understand Existing USCG Employee Characteristics
• Residential Zip Code Data
• Employee Travel Mode Survey
• Multi-Modal Transportation Options
St. Elizabeths West Campus
St. Es West St. Es West CampusCampus
MLK
Ave
nue
MLK
Ave
nue
II--29529
5So
. Cap
itol
So. C
apito
l
Firth SterlingFirth SterlingSuitland Pkwy
Suitland Pkwy
Malcolm X Malcolm X
II--295295
Existing Condition – Levels of Service (LOS)Existing Condition – Levels of Service (LOS)
St. Elizabeths West Campus
CDMartin Luther King/Howard
ECFirth Sterling/South Capitol
DDMalcolm X/Martin Luther King
BCSo. Capitol Street/Malcolm X Southbound
ACSo. Capitol Street/Malcolm X Northbound
ACI-295/Malcolm X
DBMartin Luther King/Good Hope Road
EBFirth Sterling/Howard Road
FFFirth Sterling / Suitland Parkway
PMAMIntersection
DDOT PlansDDOT Plans
• South Capitol EIS
St. Elizabeths West Campus
South Capitol Bridge Replacement and Roadway Improvements
11th Street Bridge Replacement
St. Es West St. Es West CampusCampus
DDOT Schedule and FundingDDOT Schedule and Funding
• 11th Street Bridge Replacement
EIS underway – Record of Decision expected in Fall 2006
Fully funded - $250 million
Scheduled completion – 2010
• South Capitol Bridge Replacement and Roadway Improvements
EIS underway – Record of Decision expected in Summer 2007
$148 million appropriated 2005 – project estimate is $365 million
Scheduled completion -2018 unless DDOT’s gets out-of-cycle
earmarked funds
St. Elizabeths West Campus
St. Es Development TrafficSt. Es Development Traffic
• 14,000 employees on site
• NCPC parking goal for St. Es is one space for 4 employees = 3,500
employee parking spaces for entire build-out
• Early traffic estimates indicate 1,400 peak hour vehicles
St. Elizabeths West Campus
Executive Briefing Page 8
Secondary Site AccessSecondary Site Access
Secondary Site Access
Additional Considerations
Secondary Site Access
Additional Considerations
• National Park Service Property
• Land Acquisition
• Additional Engineering Studies
• Security
• Traffic Operations
100%
7%
1%
12%
8%
7%
3%
7%
2%
34%
9%
10%
2%25%29%44%Total
50%50%DC
60%40%Frederick Co.
100%Baltimore/AA/CC/HC
60%40%Montgomery Co.
30%70%Prince Georges Co. (South)
10%90%Prince Georges Co. (Middle)
100%Prince Georges Co. (North)
100%Charles Co.
30%70%VA outside Beltway
30%70%VA inside Beltway
30%70%Alexandria
SuitlandPkwy
I-395I-295(SB)
I-295 (NB)
USCG Employee Residential Distribution
44%
29%
2%
25%US Coast Guard Employee Residential DistributionUS Coast Guard Employee Residential Distribution
USCG Survey ResultsUSCG Survey Results
Transportation ManagementTransportation Management
• Metrorail
• Streetcar
• Carpooling
• Agency Shuttle/Express Bus
• Telecommuting