SR 0068 Karns Crossing Bridge Replacement
1
SR 0068 Section 253Butler and Summit TownshipsButler County, PA
EXISTING KARNS CROSSING BRIDGE
RENDERING OF PROPOSED KARNS CROSSING BRIDGE
Project Team
2
PennDOT District 10:• Jason Layman, E.I.T. – Project Manager
Michael Baker International, Inc: • Sean Hart, P.E., C.B.S.I. – Project Manager
Direct Project Questions to Jason Layman: • [email protected]• (724) 357-7614
Please complete the survey at the end of this presentation.
Project Purpose
• The purpose of this project is to address identified deficiencies along SR 0068 between SR 0422 and Hospital Way
3
Project Location Map
4
Project Location Map
5
Project Needs
• Replacement of the Karns Crossing Bridge Carries SR 0068 over the B&LE and B&P Railroads
• Replacement of the Twin-Cell Arch Culvert Carries SR 0068 over the Connoquenessing Creek
• Correct the Traffic Safety Issues at: SR 0068 / Delwood Road Intersection SR 0068 / SR 0422 EB Onramp Intersection
6
Project Requirements
• Maintain 1 Lane of Traffic in Each Direction along SR 0068 During Construction
• Maintain Access to Butler Memorial Hospital During Construction
7
Project Description
• Replace the Karns Crossing Bridge New 3 Span Continuous Steel Plate Girder Bridge
• Replace the Twin-Cell Arch Culvert over the Connoquenessing Creek New 1 Span Prestressed Concrete Bulb-Tee Beam Bridge
8
Project Description (continued)
• Correct the Traffic Safety Issues at the SR 0068 / Delwood Road Intersection and SR 0068 / SR 0422 EB Onramp Intersection Add a Right Turn Lane on to Delwood Road for SR 0068 WB
Traffic (heading towards Butler) Add a Left Turn Lane on to Delwood Road for SR 0068 EB
Traffic (heading towards SR 0422 Interchange) Add a Right Turn Lane on to SR 0422 EB Onramp for SR 0068
EB Traffic
• Construct a Retaining Wall between SR 0068 and the B&LE Railroad
9
Project Description – Quick Facts
Average Daily Traffic (ADT) = 12,900 for Design Year 2042• 4% Truck Traffic
Roadway Dimensions• Existing Lane/Shoulder Width = 11’ Lanes, Shoulders
Vary 3’ to 6’• Proposed Lane/Shoulder Width = 11’ Lanes, 8’
Shoulders
10
Project Description – Quick Facts (continued)
Karns Crossing Bridge
• Existing Roadway Width = 34’ with 5’ sidewalk• Proposed Roadway Width = 63’ with no sidewalk• Wider Shoulders on Proposed Bridge can be used for
Pedestrians
11
Project Description – Quick Facts (continued)
Karns Crossing Bridge (continued)
• B&LE Railroad Horizontal Clearance: 9’-7” Minimum Existing 18’-0” Required 20’-7” Minimum Proposed
• B&LE Railroad Vertical Clearance: 21’-4’ Minimum Existing 23’-0” Required 23’-11” Minimum Proposed
12
Project Description – Quick Facts (continued)
Karns Crossing Bridge (continued)
• B&P Railroad Horizontal Clearance: 8’-8” Minimum Existing 18’-0” Required 20’-3” Minimum Proposed
• B&P Railroad Vertical Clearance: 21’-2’ Minimum Existing 23’-0” Required 27’-0” Minimum Proposed
13
Project Description – Quick Facts (continued)
Twin-Cell Arch Culvert• Existing Roadway Width = 50’• Proposed Roadway Width = 74’-7 ½”
14
Project Overview – Existing Karns Crossing Bridge
15
Typical Roadway across Existing Karns Crossing Bridge(Looking Westbound Towards Butler)
Existing Karns Crossing Bridge. Photo Taken from Parking Lot Adjacent to B&LE Railroad and Delwood Road
Project Overview – Existing Twin-Cell Arch Culvert
16
Existing Twin-Cell Arch Culvert Carrying SR 0068 over the Connoquenessing Creek. Culvert is Located Between Existing
Karns Crossing Bridge and SR 0422.
Looking through One Cell of Existing Twin-Cell Arch Culvert which Carries SR 0068 over the Connoquenessing Creek
Project Overview – Delwood Road Intersection
17
SR 0068 / Delwood Road Intersection(Looking Right Towards Butler)
SR 0068 Looking Westbound at the Delwood Road Intersection
SR 0068 / Delwood Road Intersection(Looking Left Towards SR 0422)
Project Overview – SR 0422 Interchange
18
SR 0068 Eastbound Looing at the SR 0422 Interchange
SR 0068 Eastbound Looing at the SR 0422 Interchange
Delwood Road Detour
19
Detour RouteDelwood Road will be closed at its intersection with SR 0068 for some phases during construction.
Motorists traveling between SR 0068 and Delwood Road will use 3rd Street and E. Brady Street for the detour route.The detour route is highlighted in blue in the adjacent figure.
Delwood Road Detour Route
Rendering of Proposed Karns Crossing Bridge
20
Rendering of Proposed Bridge (Looking Northeast Towards SR 0422)
Rendering of Proposed Karns Crossing Bridge
21
Rendering of Proposed Bridge (Looking West)
Project Plans
22
Project Plans
23
Project Plans
24
Project Plans
25
Project Plans
26
Project Plans
27
Project Plans
28
Project Schedule
29
Proposed Construction:• Start 2022• Dependent upon construction funding
Anticipated Construction Duration: • 3 Years (2022 to 2024)
Project Survey
30
Please complete the survey below in order to provide feedback about the project: