spring hill high school – phase 1 – weekly progress report

1
Construction Manager: JE Dunn Architect: DLR Group Owner: Spring Hill School District Spring Hill High School – Phase 1 – Weekly Progress Report – September 15, 2017 Concrete Benches are Complete – Bldg F Fire Ceilings are Ready to be Installed 2 nd Floor – Bldg 4 – Ceilings Nearly Complete Phase 2 – Footings Being Installed Project Status This Week: Concrete Benches Completed Ceilings – 2 nd floor – Ready to be Painted Overhead MEP is nearly complete on 1 st floor Next Week: Ceilings – 2 nd Floor – Complete Fire Ceilings Complete Continue Phase 2 Footings Personnel on site: 40 JE Dunn Superintendent: 1 Accidents: 0 Lost time accidents: 0 Accident Free for: 153 Weather Days: 0 Learn. Create. Adapt. Succeed.

Upload: others

Post on 01-Jun-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Spring Hill High School – Phase 1 – Weekly Progress Report

Construction Manager: JE Dunn Architect: DLR Group Owner: Spring Hill School District

Spring Hill High School – Phase 1 – Weekly Progress Report – September 15, 2017

Concrete Benches are Complete – Bldg F Fire Ceilings are Ready to be Installed

2nd Floor – Bldg 4 – Ceilings Nearly Complete Phase 2 – Footings Being Installed

Project Status This Week:

Concrete Benches Completed

Ceilings – 2nd floor – Ready to be

Painted

Overhead MEP is nearly complete on 1st

floor

Next Week:

Ceilings – 2nd Floor – Complete

Fire Ceilings Complete

Continue Phase 2 Footings

Personnel on site: 40

JE Dunn Superintendent: 1

Accidents: 0

Lost time accidents: 0

Accident Free for: 153

Weather Days: 0