spring hill high school – phase 1 – weekly progress report
TRANSCRIPT
Construction Manager: JE Dunn Architect: DLR Group Owner: Spring Hill School District
Spring Hill High School – Phase 1 – Weekly Progress Report – September 15, 2017
Concrete Benches are Complete – Bldg F Fire Ceilings are Ready to be Installed
2nd Floor – Bldg 4 – Ceilings Nearly Complete Phase 2 – Footings Being Installed
Project Status This Week:
Concrete Benches Completed
Ceilings – 2nd floor – Ready to be
Painted
Overhead MEP is nearly complete on 1st
floor
Next Week:
Ceilings – 2nd Floor – Complete
Fire Ceilings Complete
Continue Phase 2 Footings
Personnel on site: 40
JE Dunn Superintendent: 1
Accidents: 0
Lost time accidents: 0
Accident Free for: 153
Weather Days: 0