sporting park construction update (2/23/11)

6
Building the Future Current Activities this Week: Site/Playing field: Grading site on the East side of building to be ongoing. Cleaning up areas in preparation of plaza work is ongoing. Underground drainage and irrigation at the playing field is ongoing. Concrete Flatwork: Area 1-Suite and Press level tub intermediate stairs are ongoing. Area 1- Platform for Stadium Suite bar area is complete. Area 3-Base slab at cauldron club extended out for curtain wall installation is complete. Finishing of exposed concrete walls to be ongoing. Area 1- SOG work at SW toilet entry to be completed. Masonry : Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is ongoing. Block installation at SW toilet entry to be ongoing. Sealing and final wash of block on the East side to begin. Stone: Area 1-Stone installation in area H to be ongoing. Steel : Installation of roll up doors in concessions is ongoing. Installation of stone support steel at Stadium Suite is ongoing. Area 3-Subroof under Stair #1 to be ongoing. Installation of SE corner screen wall tubes is ongoing. Installation of bar joists and roof decking in area H to begin. Installation of dock overhead doors to begin. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner From: Nick Durand Office: Kansas City Date: 2.23.2011 Re: Sporting Kansas City Project Update – Week of 2.23.2011 Installation of field drainage and irrigation lines. Installation of Suite level intermediate stairs.

Upload: sportingkc

Post on 29-Nov-2014

1.601 views

Category:

Sports


2 download

DESCRIPTION

Sporting Kansas City's state-of-the-art, $180 million plus Sporting Park is currently under construction in Kansas City, Kansas near The Legends at Village West. This stadium construction update for the week of February 23, 2011 is courtesy of Turner Construction. For more information on Sporting Park, visit SportingKC.com/virtualvenue or watch the webcam at www.sportingwebcam.com

TRANSCRIPT

Page 1: Sporting Park Construction Update (2/23/11)

Building the Future

Current Activities this Week:

Site/Playing field:

Grading site on the East side of building to be ongoing.

Cleaning up areas in preparation of plaza work is ongoing.

Underground drainage and irrigation at the playing field

is ongoing.

Concrete Flatwork:

Area 1-Suite and Press level tub intermediate stairs are

ongoing.

Area 1- Platform for Stadium Suite bar area is complete.

Area 3-Base slab at cauldron club extended out for

curtain wall installation is complete.

Finishing of exposed concrete walls to be ongoing.

Area 1- SOG work at SW toilet entry to be completed.

Masonry:

Block installation at NW transformer area to be ongoing.

Block installation at Terrace Bar is ongoing.

Block installation at SW toilet entry to be ongoing.

Sealing and final wash of block on the East side to begin.

Stone:

Area 1-Stone installation in area H to be ongoing.

Steel:

Installation of roll up doors in concessions is ongoing.

Installation of stone support steel at Stadium Suite is

ongoing.

Area 3-Subroof under Stair #1 to be ongoing.

Installation of SE corner screen wall tubes is ongoing.

Installation of bar joists and roof decking in area H to begin.

Installation of dock overhead doors to begin.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

Brandon Valdez-Turner

From: Nick Durand

Office: Kansas City

Date: 2.23.2011

Re: Sporting Kansas City

Project Update – Week of

2.23.2011

Installation of field drainage and irrigation

lines.

Installation of Suite level intermediate stairs.

Page 2: Sporting Park Construction Update (2/23/11)

Building the Future

Roofing and Sheet metal:

Area 1-Alucobond metal panel installation at Suite and

Press level on field side is near complete.

Alucobond metal panel and subgirt installation is

ongoing at Concourse buildings.

Drilling anchors for exterior fins is ongoing in all areas.

Area 3-Concourse building roofing is ongoing in the SE.

Louver installation at East side is complete.

Gutter shrouds at canopy gutter are ongoing.

Canopy deck flashing installation is ongoing.

Polycarbonate:

Area 1-Polycarbonate installation is ongoing.

Area 2-Polycarbonate installation is ongoing.

Metal Stud Framing/Drywall/Ceilings:

Area 1- Drywall installation is near complete.

Area 3-Drywall installation and finishing is near complete.

DAFS installation is ongoing at exterior soffits.

Stud framing for North screenwall/ metal panels is ongoing.

Drywall installation in concessions/retail areas is

Ongoing.

FRP installation in Concessions is ongoing.

Ceiling grid installation is ongoing on all levels.

Glass:

Area 1-Storefront at 24-27 lines installation is

complete.

Area 1-installation of aluminum door frames is ongoing.

Area 1-installation of store fronts at VIP entrance is

complete.

Installation of storefronts at Main Concourse retail

buildings is ongoing.

Installation of Press level Solar innovation sliders is

ongoing.

Area 1- installation of interior storefronts is ongoing.

MEP:

Ductwork installation in the west tower is complete

and is ongoing on the East side field level.

Plumbing rough is complete in the west tower and is

ongoing on the East side field level.

Installation of metal panels at concessions.

Block work at SW toilet entrance.

Page 3: Sporting Park Construction Update (2/23/11)

Building the Future

Site-SE and SW transformers have been energized.

NW transformer is now set and primary cables are being pulled to transformer.

Installation of the backbone cable is complete and is terminated

in the IT rooms.

All racks and cabinets in the West tower have been

assembled and termination of cables is near complete.

Concession building rough in for all MEP is near complete.

Installation of permanent lights and speakers in soffits is ongoing.

Fixtures and devices are being installed in the West

tower and termination of branch circuits is ongoing.

South scoreboard module installation is complete.

Sub air equipment is installed and all secondary

work is complete.

Area 1-installation of toilet fixtures on Suite and Field level

is ongoing.

Broadcast cable pulls from loading dock to the Video

Production room is ongoing.

Tie –in of canopy gutters to downspouts is ongoing.

North scoreboard structure installation to begin.

Elevators:

F1 elevator installation is near completion.

P2 & P3 elevator installation is ongoing.

P4 & P5 elevator installation is ongoing.

P1 has been delivered and installation to begin.

Painting:

Area 1-Painting at Field level is ongoing.

Area 1-Painting in Main Concourse buildings is ongoing.

Area 1-Painting on Press and Suite level is near complete.

Sealing of exposed concrete floors is ongoing.

Resinous flooring at field level is ongoing.

Resinous flooring in Concessions, Suite, and Press

is ongoing.

Painting of stair structure and walls is ongoing.

Tile:

Tile in Suites on Suite level is complete.

Tile installation in club areas at Suite and Press levels

has begun.

Tile in restrooms at all levels is ongoing.

Installation of storefronts at V.I.P entrance.

Tile installation at Field Club.

Page 4: Sporting Park Construction Update (2/23/11)

Building the Future

Food Service:

Countertop installation in Concessions is complete.

Installation of all counters and kitchen equipment at Mezz level, Suite level, and Press

level to be ongoing.

Cooler installation in concessions and cauldron club is near complete.

Exhaust hood installation in cauldron club to begin.

Projected Activities occurring next Week:

Concrete Flatwork:

Area 1-Suite and Press level tub intermediate stairs to be

completed.

Finishing of exposed walls to be completed.

Cauldron Club topping slab installation to begin.

Stone/masonry:

Block installation at NW transformer area to be complete.

Block installation at Terrace Bar to be ongoing.

Block installation at SW toilet entry to be complete.

Stone installation in area H to be ongoing.

Steel:

Installation of roll up doors in concessions to be complete.

Installation of stone support steel at Stadium Suite to be

ongoing.

Area 3-Subroof under Stair #1 to be complete.

Installation of SE corner screen wall tubes to be complete.

Installation of bar joists and roof decking in area H to

be completed.

Installation of dock overhead doors to be ongoing.

Roofing and Sheet metal:

Canopy gutter shroud installation to be ongoing.

Area 3-North East concourse roof to begin.

Installation of metal panels at concessions to be ongoing.

Field measuring for metal panels at Stadium Suite to be

complete.

Installation of coping cap at concourse roof to be ongoing.

Painting is ongoing in RR’s at Main

Concourse.

Overhead door installation at loading dock.

Page 5: Sporting Park Construction Update (2/23/11)

Building the Future

Metal Stud Framing/drywall soffits:

Area 1- Drywall installation to be complete.

Area 3-Drywall installation and finishing to be complete.

DAFS installation to be ongoing at exterior soffits.

Stud framing for North screenwall/ metal panels to be complete.

Drywall installation in concessions/retail to be complete.

FRP installation in Concessions to be ongoing.

Ceiling grid installation to be ongoing on all levels.

Glass:

Area 1-Aluminum door frame installation to be ongoing.

Installation of storefronts at Main Concourse buildings

to be ongoing.

Installation of interior glazing at Field and Mezz. level to

be near complete.

Installation of Solar innovation sliders at back of suites on

Press level to be ongoing.

MEP:

NW transformer to be energized.

Installation of North Scoreboard to be ongoing.

Preliminary hydrostatic testing of the fire sprinkler lines to begin.

Energizing mechanical equipment to begin commissioning/start up.

Paint:

Area 1-Painting of the Suite and Press level areas to

be near complete.

Painting of the Main Concourse buildings to be ongoing.

Painting at Field level to be ongoing.

Sealing of concrete floors to be ongoing.

Painting of stair #4 and #9 to be complete.

Resinous flooring to be ongoing in concessions.

Playing Field:

Installation of underground drainage and irrigation lines

to be ongoing.

Drilling for fin anchors is ongoing.

Locker installation at field level.

Page 6: Sporting Park Construction Update (2/23/11)

Building the Future

Additional Photos:

Framing for metal panels at North main

concourse.

Subroof installation under Stair #1.

Tile and millwork installation at Executive Suites.

South scoreboard module installation is complete.