Page 1: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

1

Spaceport America

Doña Ana Spaceport Community Council Update

April 22, 2010

Page 2: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Spaceport America’s Purpose is to enable the Emergence of a New Commercial Space Industry

and be a Catalyst For Economic Development, Tourism, &

Education in New Mexico

Genesis of Spaceport America

2

Page 3: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

3

Agenda

•  Industry Overview & NASA’s New Direction

•  Spaceport Construction Update

•  Space Flight Informed Consent Legislation

•  Education Update

Page 4: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Discover Magazine: Top 100 Discoveries Changing the World (Jan/Feb 2010 Issue)

Page 5: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

VSS Enterprise First Flight Mar. 22nd 2010

Page 6: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Space Industrialization …

Clean Up Orbital Debris Research and Development

Low Cost Access to Space Changes the Game… * Courtesy of XCOR Aerospace

Page 7: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

7

Bringing the business community together to grow the personal and commercial spaceflight industry !

www.ispcs.com  

ISPCS Industry Symposium!October 20 & 21, 2010!

New Mexico Farm & Ranch Heritage Museum

Las Cruces, New Mexico #

Dr. Patricia C. Hynes, ISPCS Chair#

October 19, 2010#Pan American CenterNew Mexico State University#Las Cruces, New Mexico #

Leonard R. Sugerman Free Public Forum

October 22, 2010: Special Event at Spaceport America

Page 8: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

8

NASA Unveils New Direction

•  NASA Administrator Charlie Bolden Shares the President’s New Plan –  Cancel Constellation Program –  Focus on Low Earth Orbit, Research, and Technology Demonstrators …

•  Prepare for Space Exploration –  Pursue Other Heavy Lift Options –  Provide $6B to Commercial Space Over the Next 5 Years –  $50M in Commercial Contracts Awarded for Technologies Supporting to and

from Low Earth Orbit: •  Boeing, Blue Origin, Sierra Nevada Corp., United Space Alliance, and Paragon Space

Development Corp.

•  Feb 2010 Suborbital Science Meeting in Boulder, Colorado –  NASA Pledges $75M towards Suborbital Science

•  Virgin Galactic, XCOR, Masten Space Systems, Armadillo, Blue Origin, etc.

•  Commercial Space => Leverage Government Investment –  Research and Science –  Low Earth Orbit/Space Station

Commercial Space to Play Prominently in NASA’s New Plan

Page 9: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

9

Agenda

•  Industry Overview & NASA’s New Direction

•  Spaceport Construction Update

•  Space Flight Informed Consent Legislation

•  Education Update

Page 10: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

10

Spaceport Construction Team: New Mexico Contractors Winning the Bids!

New Mexico Spaceport Authority Infrastructure Division Director: Chad Rabon

Airfield + Apron David Montoya Const. Inc.

Project Manager: Robert Watson

Site Enabling FNF New Mexico, LLC

Project Manager: J. Sharpe/ Aaron Cohn

Architect/Engineer: AECOM/DMJM

Project Manager: Alan Jefts/ Brian Speicher

Architect/Engineer URS/Foster + Partners/SMPC

Project Manager: Rick Tietgens

Construction Team Evolving…. Most Elements by December 2010

EIS Data Recovery Zia Environmental & Cooperating Agencies

Ongoing

Horizontal Vertical

Water Smithco

Project Manager: Juan Trevizo

Waste Water AUI Inc.

Project Manager: Arturo Zavala

Fuel Storage FNF New Mexico, LLC

Project Manager: Jose Castillo

Off-Site Electrical Sierra Elec. Coop. General Manager:

Jimmy Capps

On-Site Electrical McDade-Woodcock Project Manager:

Bill Vaughan

Internal Roads CMC Construction Project Manager:

Bill Loomis

Terminal & Hangar Summit West

Project Manager: Carl Nicol

Construction Manager: Gerald Martin

Project Manger: Randy Gilbert

External Road/ Ash Canyon

NMDOT / Reiman Corp. :

Complete

* Southern Road and Vertical Range TBD

ARFF Bateman-Hall

Project Manager: Russell Lyday

Fencing TBD

Project Manager: TBD

Communications TBD

Project Manager: TBD

Page 11: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

11 11

Contractor ITB/RFP Summary (Cont’d)

  External Roads: NMDOT Contracted –  AO13 Temporary Road Improvement & Ash Canyon Complete –  Working with Dona Ana & Sierra Counties on Southern Road Approach (MOA in Development)

  NMSA Construction Management: Gerald Martin/HDR Contracted Dec. 2008 –  Construction Management Services

  EIS Data Recovery: Zia Environmental Contracted March 2009 –  On-Site Work Complete June 2009 –  FAA, SLO and SHPO Approved Start of Construction August 10, 2009 –  On-Going Cultural Monitoring Plans Developed as Required –  Working through Trail and Site Mitigation Plans… Drafts Submitted to FAA March 2010

•  NM DoIT –  Fiber Optic Service to Site –  NMDoIT Coordination Required Prior to Communications Package Bid Release

•  Special Inspections Bid Opening April 2010 –  Owner Independent Testing Agency –  Sitewide Quality Inspections Required by NM CID Code

  Electric Service: SEC Agreement Executed: Power December 2010 –  SEC Connection to 115kv Transmission Line: Substation & 6 Miles of Distribution Line –  Working with SEC and BLM on the Approach for Permits and Cultural Mitigation

Data Infrastructure to Site & Special Inspections are Remaining Open Issues

Page 12: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

12

Spaceport America Operational Site Plan

  Runway: 10,000 feet long - - - - 200 feet wide

  Access and Internal Roads

  Underground Utilities Water Wastewater Electrical Power Communication

  Terminal and Hangar: 100K Sq. Ft. Virgin Galactic Operations NMSA Offices Public and Visitor Experiences

  ARFF and Maintenance Building

  Vertical Launch Area 12

Page 13: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

13

Spaceport America Site: 467 Confirmed Jobs and Growing …

Airfield: D Montoya Const.

ABQ: 129

Waste Water: AUI

LC & ABQ: 107

Enabling Works: FNF New Mexico

ABQ: 31*

Water: Smithco

T or C: 50

Internal Roads: CMC

T or C: 40

Off-Site Electrical: Sierra Elec. Coop. Elephant Butte: 20

Fencing: TBD

TBD: TBD

Apron: D Montoya Const. ABQ: Est. 30-50

Environmental: Zia Environmental

Las Cruces: 5

On-Site Electrical: McDade Woodcock

ABQ: 15

Terminal Hangar: Summit West

ABQ: Est. 150-300

ARFF: Bateman-Hall

ID/NM: Est. 50-100

Communication: TBD

TBD: TBD

Fuel Storage: FNF New Mexico

ABQ: 31*

NMSA & Design Team: AECOM, URS, Molzin-Corbin, etc.

ABQ/LC: 65

Construction Manager: Gerald Martin

ABQ: 8

Page 14: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Spaceport America Business Model

•  Two Revenue Sources:

1.  Job Based Revenue Generation: Jobs, Tourism, Education, Construction –  Income Tax –  Property Tax –  GRT

2.  Site Based Revenue: Tenants and Tourism –  Lease Fees –  User Fees –  Tour and Merchandizing

•  Budget: –  NMSA Operating Budget –  Site Operational Cost

Jobs for New Mexico, Inspiring the Next Generation, General Fund Benefit

Revenue Greater than Costs:

Positive Impact for New Mexico

Operational Self-Sufficiency

Benefits All of New Mexico

Jobs: $8M-$13M* to the General Fund

Construction GRT: $8M-$12M*

20 Yr VG Lease: $250M

2010 $16M - $25M

* NMSA Business Models

Page 15: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

15

Construction Status

Entry Sign at A-039 A-039 Box Culvert

1.3 Million Gallon Water Tank Terminal Hangar Facility

Page 16: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Fuel Storage Electrical Conduit to Water Wells

Waste Water Tanks Waste Water Corridor

Construction Status

Page 17: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

17

Construction Status: Airfield Paving: 42 Inch Section

24 Inch Compacted Soil Top 6 Inches: Cement/Soil Mix

4 Inch Asphalt Layer 14 Inches of Concrete On Top of Asphalt

Page 18: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

18

Airfield Construction Status: Concrete In Process

14 Inch Concrete Lay-Down Concrete Laser Leveled

Local Aggregate on Site Mining Pit at the Lewis Cain HQ

Page 19: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

THF Construction Status

County Road A-013 Completed Gerald Martin Offices In Place

Lineup of Airfield Grading Equipment

Asphalt Plant

Stair Tower Foundation Placing Concrete Forms

View from Berm View of THF/Berm from Taxiway

Page 20: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

20 20 20

Construction Status: Site Fly-Over

* Courtesy Mark Greenberg

Dec. 2009

Oct. 2009

* Courtesy Bob Martin

Runway Complete Summer 2010

* Courtesy Dick Woodsum

March 2010

Page 21: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

21

Aircraft Rescue Fire-fighting Facility & Operations Center

Page 22: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

22

Spaceport America Conceptual Image URS/Foster + Partners

22

Spaceport America 2011

T – One Year

Page 23: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

23 23 23

Vertical Launch Complex

• Lunar Lander Pads Installed: –  X Prize Lunar Lander Challenge

–  Infrastructure Available to Support Customers

–  Pads Completed in July 2009

• Compliments Spaceport America’s UP Aerospace Launch Rail

–  MOOG FTS Launch August 4th –  Lockheed Martin Launch October 10th

Vertical Launch Business Picking Up …

Page 24: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

24

Agenda

•  Industry Overview & NASA’s New Direction

•  Spaceport Construction Update

•  Space Flight Informed Consent Legislation

•  Education Update

Page 25: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

25 25

Space Flight Informed Consent Signed

•  Informed Consent Legislation:

–  Supports 2004 Federal Commercial Space Launch Amendments Act •  Informed Consent Legislation: Full Disclosure, Assumption of Risk •  FAA/AST to License, not Certify •  Participants, not Passengers •  Affects Participants Only

–  Virginia & Florida Passed Legislation in 2007 and 2008

–  Risk Management Division to Provide Insurance Coverage Requirements •  Spaceport Coverage •  Flight Providers/Spaceport Tenants Required to Carry Insurance

•  Senate Bill #9 Passed Unanimously in Senate and House –  Senator Mary Kay Papen Sponsor –  Governor Signed into Law on February 27th

New Mexico Remains Competitive with Other States….

Page 26: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

26

Agenda

•  Industry Overview & NASA’s New Direction

•  Spaceport Construction Update

•  Space Flight Informed Consent Legislation

•  Education Update

Page 27: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Education Vision for Spaceport America

•  Collaborate with multi-pronged approach –  Inclusive K-20 student and educator focus –  Align stakeholders with shared vision

•  Create Spaceport America as a student laboratory –  Hands-on, participatory, emotional experiences –  Leverage student fascination in unique industry sector to engage & inspire

•  Service local workforce development needs –  Help fill the STEM pipeline with more students –  Emphasize relevant skills through applied opportunities –  Facilitate valuable interactions with government and industry

•  Become catalytic for schools and school districts –  Academic year programs to integrate with school day –  Out of school programs to inform the school day work –  Develop local spaceport-related education Community of Practice

27

Page 28: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Workforce Needs for Spaceport America

•  Technical –  Engineers:

•  Aerospace, Mechanical, Electrical –  Technicians:

•  CAD/CAM, Aerospace, Electrical, Mechanical, •  Hazardous Materials, Launch Support, Heavy Maintenance

–  Computing: •  Computer Systems / IT Professionals, Programmers

–  Operations: •  Flight Ops, Ground Ops, Flight Safety, Security

•  Business –  Admin:

•  Secretarial, Purchasing, Human Resources –  Management:

•  Business Administration, Economics, HRTM, •  Financial Modeling, Project Management

–  Sales/Marketing: •  Customer Service, Public Affairs, Graphic Design

•  Ancillary – Supply Chain, Tourism –  Nursing, Food Service, Transportation Services, Security, Janitorial, Real Estate/

Housing, Child Care, Manufacturing, Composites, Biofuels, Precision Tooling/Cleaning, Media, etc.

28

Page 29: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

2nd Annual Student Launch Program Event

•  NM Space Grant / NMSU / NMSA collaboration

–  Liftoff ~6am, 5/4/2010 –  Student payload experiments from:

• New Mexico State University • University of New Mexico • Dona Ana Community College • Southwestern Indian Polytechnic Institute

• San Juan College • NM Highlands University • Central NM Community College • Hot Springs High School (T or C)

May 4th Event Open to Public – Register at www.SpaceportAmerica.com

Page 30: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

2nd Annual Student Launch Program Event

•  Annual access to space for students* –  1st ever program of its kind in the world

•  Academic year workforce development program –  Applied learning in the classroom, not after school –  Facilitated by NASA/NM Space Grant Consortium

•  Improve skills useful to area Hi-tech Employers –  Design and development process –  Fabrication/machining –  Time/project management –  Critical thinking/problem solving/research –  Communication/teamwork –  Presentation/documentation –  Launch operations

•  Intention to expand throughout New Mexico –  All colleges, universities –  All 89 K-12 school districts

Looking to Partner to Expand Impact of Program to more NM Students * Contingent on Funding, Desire to Increase Frequency, Potential to Expand Globally as Funding Mechanism

Page 31: Spaceport America · 4/22/2010  · Spaceport America Operational Site Plan Runway: 10,000 feet long - - - - 200 feet wide Access and Internal Roads Underground Utilities Water Wastewater

Delivering the Future of Space …

Spaceport America Conceptual Image of URS/Foster + Partners Design: Vyonyx Artist Rendering