1 SOUTH KENSINGTON CWG: 15 JUNE 2016
South Kensington: Consultative Working Group - Design Update
15 JUNE 2016
2 SOUTH KENSINGTON CWG: 15 JUNE 2016
Progress update: pre-application comments
Comments received from Royal Borough, highlighting importance of station heritage and design
Meeting held with Cllr. Tim Coleridge and lead planning officer Sian Saadeh
Encouraged to reflect existing historical elements within design of platform features
Not considering pastiche canopy design
Workshop (2 of 3) held with Alan Baxter and JSA architects to review design options
3 SOUTH KENSINGTON CWG: 15 JUNE 2016
Ticket hall design
4 SOUTH KENSINGTON CWG: 15 JUNE 2016
Canopy design
Reflecting on RBKC comments, John Smith Architects and Alan Baxter are reviewing current design approach
Opportunities to reassess elements of historical design on D&C eastbound platform and apply principles to the current approach
5 SOUTH KENSINGTON CWG: 15 JUNE 2016
Revised canopy design
6 SOUTH KENSINGTON CWG: 15 JUNE 2016
Revised canopy design
7 SOUTH KENSINGTON CWG: 15 JUNE 2016
Overbridge design
8 SOUTH KENSINGTON CWG: 15 JUNE 2016
Next Steps
June: workshops being held with JSA and Alan Baxter & Associates
29 June: meeting scheduled with RBKC officers
July: public drop-in session planned for early July
July: submit listed building consent application
9 SOUTH KENSINGTON CWG: 15 JUNE 2016