Spring 2013
Master of Business Administration- MBA Semester 1 MB0048 –Operations Research- 4 Credits
(Book ID: B1631) Assignment Set - 1 (60 Marks)
Note: Assignment Set -1 must be written within 6-8 pages. Answer all questions.
Q1. Explain the scope of Operations Research. What are the features of Operations
Research? 10 marks
Q2. Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given
in the matrix below. Determine the optimal assignment. Which operator will have no
assignment?
Operators Jobs
1 2 3 4 5
1 6 2 5 2 6
2 2 5 8 7 7
3 7 8 6 9 8
4 6 2 3 4 5
5 9 3 8 9 7
6 4 7 4 6 8
10 marks
Q3. a. Explain the Monte Carlo Simulation.
b. A Company produces 150 cars. But the production rate varies with the distribution.
Production Rate 147 148 149 150 151 152 153
Probability 0.05 0.10 0.15 0.20 0.30 0.15 0.05
At present the track will hold 150 cars. Using the following random numbers
determine the average number of cars waiting for shipment in the company and
average number of empty space in the truck. Random Numbers 82, 54, 50, 96, 85,
34, 30, 02, 64, 47.
5 +5 = 10
marks
(200 - 250
words each)
Q4. Explain the Characteristics and Constituents of a Queuing System. 10 marks
(300 - 350
words
each)
Research?
For Complete Solved SMU Assignment @ 1500 to 2000 Rs Email: [email protected]
Ph: +91 -9873669404
http://www.smuassignments.net/
For Complete Solved SMU Assignment @ 1500 to 2000 Rs Email: [email protected]
Ph: +91 -9873669404
http://www.smuassignments.net/
Spring 2013
Q5. a. What do you mean by dominance? State the dominance rules for rows and
columns.
b. Find the saddle point of the following game and state the optimum strategies for
players A and B
A
B
1 2 3 4 5
1 9 3 1 8 0
2 6 5 4 6 7
3 2 4 4 3 8
4 5 6 2 2 1
5 +5 = 10
marks
(200 - 250
words
each)
Q6. a What are the differences between PERT and CPM?
b. A project has eleven activities whose duration is given in the following table:
Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7 7 - 8
Duration
(days)
2 8 10 6 3 3 7 5 2 8 3
i. Draw the network
ii. Identify the critical activities and critical path.
5 +5 = 10
marks