    APPENDIX I

    (See paragraph-6)

    FORM 1

    (I) Basic InformationSerial

    Number

    Item Details

    1. Name of the project/s SKYLINE Proposed Group Housing Project

    promoted by M/s Sunprime Infratech Pvt. Ltd.

    2. S. No. in the schedule Category B under item 8(a) of the schedule of

    Gazette Notification dated September 14th, 2006.

    3. Proposed

    capacity/area/length/tonnage to

    be handled/command area/lease

    area/number of wells to bedrilled

    S.

    No.

    Particulars Details

    1. Total Plot Area 7582.62 Sq. m

    2. Built up Area 35549.12 Sq. m

    3. Gross Built up Area 42251.02 Sq. m

    4. FloorArea

    Ratio

    Permissible 2.25 (17060.89Sq. m)

    Total Net

    FAR

    Achieved

    3.13= 2.25+ 0.88*

    (23760.37 Sq. m)

    5. Ground

    Coverage

    Permissible 35 % (2653.91 Sq.

    m)

    Achieved 25.59 % (1940.98

    Sq. m)

    6. Landscape

    Area

    Permissible 1137.39 Sq. m (15

    % of total plot

    area- 7582.62 Sq.

    m)

    Achieved 1623.16 Sq. m

    (21.41 % of total

    plot area- 7582.62

    Sq. m)

    7. Height Achieved 44.90 m (up to

    Terrace Floor)& 52.65 m (up to

    Machine Room)

    *By Laws Permitting purchase of FAR is enclosed

    as Annexure XXVII.

    4. New/Expansion/Modernization It is a new project.

    5. Existing Capacity / Area etc. -

    6. Category of Project i.e. A or

    B

    B

    7. Does it attract the generalcondition? If yes, please specify

    No

    8. Does it attract the specific No

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    2/14

    condition? If yes, please specify

    9. Location Kota

    Plot/Survey/Khasra No. Plot No. 1/A,

    Village Rajiv Gandhi Nagar

    Tehsil Ladpura

    District Kota

    State Rajasthan

    10. Nearest railway station/airport

    along with distance in Kms.

    Dakaniya Talaav Railway station at about1.67 km

    towards NE

    Kota Railway Station at about 10.12 km towards

    NNE

    Kota Airbase at 2.90 km towards North

    NH- 12 at about 0.02 km towards East.

    11. Nearest Town, city, District

    Headquarters along withdistance in Kms.

    The Project is situated in Kota city.

    12. Village Panchayats, Zila

    Parishad, MunicipalCorporation, Local body

    (complete postal addresses with

    telephone nos. to be given)

    Urban Improvement Trust,

    Near C.A.D Circle, Kota,Rajasthan

    (+91-0744) 2500777, 2414149; +9198290-38031

    13. Name of the applicant M/s Sunprime Infratech Pvt. Ltd.

    14. Registered Address F-316, Bhamashah Mandi Road, Road No. 6, IPIAKota-324005

    15. Address for correspondence:

    Name Mr. Ramesh Kumar Yadav

    Designation (Owner/

    Partner/CEO)

    Director & Authorized Signatory

    Address 1/A, Rajeev Gandhi Nagar, Opp. City Mall,Jhalawar Road, Kota, Rajasthan

    Pin Code 324005

    E-mail [email protected] &

    [email protected]

    Telephone No. 09414188396

    Fax No. 0744-2490584

    16. Details of Alternative Sites

    examined, if any. Location of

    these sites should be shown on

    a topo sheet.

    No alternative site was examined as the land is

    developed and allocated to the proponent by UIT

    (Urban Improvement Trust) kota.

    Plot is developed for Group Housing Purpose.Geographical location-Latitude- 25 08'08.53"N

    Longitude - 7551'13.89" E

    17. Interlinked Projects No

    18. Whether separate application of

    interlinked project has been

    submitted?

    Not Applicable

    19. If yes, date of submission Not Applicable

    20. If no, reason Not Applicable

    21. Whether the proposal involves

    approval/clearance under: if

    No

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/11/2019 Skyline_Form_1_29112013

    3/14

    yes, details of the same and

    their status to be given.

    (a) The Forest

    (Conservation)

    Act, 1980?

    (b) The Wildlife

    (Protection) Act,

    1972?(c) The C.R.Z

    Notification, 1991?

    22. Whether there is any

    Government Order/Policyrelevant/relating to the site?

    No

    23. Forest land involved (hectares) No

    24. Whether there is any litigation

    pending against the project and

    /or land in which the project is

    proposed to be set up?

    (a)

    Name of the court

    (b)Case No.

    (c)Orders/directions of the

    Court, if any and its

    relevance with the

    proposed project.

    No

    (II) Activity

    Construction, operation or decommissioning of the Project involving actions,

    which will cause physical changes in the locality (topography, land use, changesinwater bodies, etc.)

    S. No. Information/ Checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)

    with source of information data

    1.1 Permanent or temporary change in

    land use, land cover or topography

    including increase in intensity of

    land use (with respect to local

    land use plan)

    No

    Yes

    Land useThe proposed site has been auctioned by

    UIT Kota and allocated to project

    proponent. Therefore the proposed

    project will not significantly differ fromexisting land use of locality and it will

    not bring any significant change in land

    use of locality.

    Land coverDue to human activities land cover is

    either directly affected from activity like

    construction of road-building leading to

    deforestation or indirectly from water

    diversion leading to lowering of the water

    table. The proposed project will not

    involve any deforestation only small work

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    4/14

    No

    of site clearance will be done in which

    some shrubs and grasses will be

    removed. It will be balanced by planed

    landscaping on site.

    Excavation of soil will be involved. The

    total expected quantity of earthwork

    involved is about 8000 M3. The

    excavated soil will be balanced withinsite by back filling. Therefore the

    changes will be localized and

    insignificant.

    Topography

    The site is plane but it will need some

    leveling activities. The proposed site

    does not involve any major natural

    drainage channel of locality therefore no

    changes in drainage pattern are

    envisaged.

    1.2 Clearance of existing land,

    vegetation and buildings?

    Yes The proposed site is devoid of any

    buildings thus no demolition of building

    will be practiced.

    The project site is not having any

    vegetation except local perennial herb,

    shrubs and grasses like Crotalaria

    burhia, Leptadenia pyrotechnica,

    Saricostoma pauciflorum and Zizyphus

    nummulariaetc. These will be removed

    during site preparation. To compensate

    that it is proposed to plant 70 tree inaddition to shrubs. The proposed

    landscaping and plantation will have

    positive impact on environment. Details

    of flora are enclosed as Annexure-

    XVI.

    1.3 Creation of new land uses? No The proposed site has been auctioned by

    UIT Kota and allocated to project

    proponent. Therefore the proposed

    project will not create new land uses

    that significantly differ from existing

    land use of locality as per the masterplan.

    1.4 Pre-construction investigations

    e.g. bore houses, soil testing?

    Yes The soil investigation was carried out by

    Indian Geotechnical Consultants,Kota. The detailed Soil investigation

    report is enclosed as Annexure- XIV.

    1.5 Construction works? Yes The Proposed Group Housing Project

    will involve construction of Basement+Ground (Stilt) + 1stto 14thFloor. Details

    are given below:

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    5/14

    Area Statement:

    S. No. Blocks BUA

    (Sq. m.)

    Gross B.U.A.

    (Sq. m.)

    Net FAR

    (Sq. m.)

    1 Basement 5615.08 5615.08 344.63

    2 Ground (Stilt) 2928.10 3396.36 378.06

    3 First Floor 1940.98 2389.72 1554.15

    4 Second Floor 1949.77 2389.72 1666.82

    5 Third Floor 1949.77 2389.72 1666.82

    6 Fourth Floor 1949.77 2389.72 1666.82

    7 Fifth Floor 1949.77 2389.72 1666.82

    8 Sixth Floor 1949.77 2389.72 1666.82

    9 Seventh Floor 1949.77 2389.72 1666.82

    10 Eighth Floor 1949.77 2389.72 1666.82

    11 Ninth Floor 1949.77 2389.72 1666.82

    12 10th Floor 1949.77 2389.72 1666.82

    13 11th Floor 1949.77 2389.72 1666.82

    14 12th Floor 1949.77 2389.72 1666.82

    15 13th Floor 1721.27 2106.43 1457.69

    16 14th Floor 1721.27 2106.43 1457.69

    17 Terrace 350.08 350.08 Nil

    Total 35549.12 42251.02 23527.24

    Total F.A.R Achieved = 23527.24 Sq. m

    Club House Area Permissible = 23527.24 X 0.05 = 1176.36 Sq. m

    Total Club House Achieved = Basement= 833.34 Sq. m (stilt = 576.15 Sq. m)=1409.49 Sq. m

    Club House F.A.R = 1409.49 1176.36 = 233.13 Sq. m

    Total Net F.A.R Achieved = 23527.24 + 233.13 = 23760.37 Sq. m (3.13)

    1.6 Demolition works? No Not involved

    1.7 Temporary sites used for

    construction works or housing of

    construction workers?

    Yes They will be housed in temporary houses

    supported by flush WCS during

    construction period only.

    1.8 Above ground buildings,

    structures or earthworks includinglinear structures, cut and fill or

    excavations

    Yes The maximum height of proposed project

    will be 44.90 m (up to Terrace Floor)52.65 m (up to Machine Room).

    Expected quantity of earth work involvedis about 8000 M3.

    1.9 Underground works including

    mining or tunneling?

    No No tunneling activity is involved.

    1.10 Reclamation works? No No reclamation works involved

    1.11 Dredging? No Not involved

    1.12 Offshore structures? No Not applicable

    1.13 Production and manufacturingprocesses?

    No Not applicable

    1.14 Facilities for storage of goods or Yes Temporary stores or sheds were

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    6/14

    materials? constructed for storage of construction

    materials.

    1.15 Facilities for treatment or disposal

    of solid waste or liquid effluents?

    Yes STP of capacity 125 KLD for treatment

    of sewage will be provided. Total sewagegenerated will be 93 KLD. After

    treatment 90% i.e. 83.7 KLD will beavailable. Out of which 29 KLD will be

    used for flushing & gardening andremained 54.7 KLD recycled water will

    be discharged in drains maintained byPHED after taking necessary permission

    from PHED.

    All solid waste from different sectionswill be collected in separate bins. The

    non-organic waste shall be disposed off

    to authorized vendors. The organic waste

    will be converted into manure and used

    within premises for green belt

    development.

    1.16 Facilities for long term housing of

    operational workers?

    Yes Cabins for watchmen, gardeners etc and

    persons engaged in essential services.

    1.17 New road, rail or sea traffic during

    construction or operation?

    No The existing infrastructure is sufficient to

    catch-up for the need of such a small

    project, insignificant increase in traffic

    for transport of men & material is

    envisaged.

    1.18 New road, rail, air waterborne or

    other transport infrastructureincluding new or altered routes

    and stations, ports, airports etc?

    No The proposed project site has well

    connectivity therefore will not requireany change in existing infrastructure.

    1.19 Closure or diversion of existingtransport routes or infrastructure

    leading to changes in traffic

    movements?

    No No public road or infrastructure iscrossing or within the proposed site.

    1.20 New or diverted transmission linesor pipelines?

    No No pipeline or transmission line iscrossing or within the proposed site.

    1.21 Impoundment, damming,

    culverting, realignment or other

    changes to the hydrology ofwatercourses or aquifers?

    No The proposed site does not involve any

    major natural drainage channel of

    locality therefore no changes in drainagepattern are envisaged.

    1.22 Stream crossings? No -

    1.23 Abstraction or transfers of water

    from ground or surface waters?

    Yes Water will be taken from PHED supply.

    For which application has been submitted

    and receiving photocopy of application is

    enclosed as Annexure- XXIV.

    1.24 Changes in water bodies or theland surface affecting drainage or

    run-off?

    yes Only treated water will be dischargedin drains maintained by PHED after

    taking necessary permission fromPHED.

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    7/14

    1.25 Transport of personnel or

    materials for construction,

    operation or decommissioning?

    Yes During construction phase material of

    construction will be transported to site

    from local market and other sources

    depending on availability.

    During operation stage the transportation

    activities will be due to cars, two

    wheelers and other vehicles of the

    residents.1.26 Long-term dismantling or

    decommissioning or restorationworks?

    No There is no building needing dismantling

    exist on the plot.

    1.27 Ongoing activity during

    decommissioning which could

    have an impact on theenvironment?

    No There will be no decommissioning

    activity.

    1.28 Influx of people to an area in

    either temporarily or permanently?

    Yes During construction phase, there will be

    inward and outward movement of local

    labour in the construction site. However

    during the post construction phase, there

    will be regular movement of residents,

    visitors and other related persons. The

    residential apartment will house about

    1075 persons which will not bring any

    significant increment in total population

    of locality.

    1.29 Introduction of alien species? No Only the plant/ tress of local species and

    suitable for the region will be planted.

    1.30 Loss of native species or genetic

    diversity?

    No There are no grown trees on the proposed

    site, some shrubs and grasses will beremoved. The same will be amplycompensated by proposed plantation and

    landscaping.

    1.31 Any other actions? No -

    2. Use of Natural resources for construction or operation of the Project (such as

    land, water, materials or energy, especially any resources which are non-

    renewable or in short supply):S. No. Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)with source of information data

    2.1 Land especially undeveloped or

    agricultural land (ha)

    No The proposed site is in developing urban

    area and site has been auctioned by UIT

    Kota and allocated to project proponent.

    2.2 Water (expected source &

    competing users) unit: KLD

    Yes

    During construction phase water

    requirement will be 15 KLD which will be

    met from authorized water suppliers.

    During post construction phase daily

    water requirement will be about 115 KLD.

    86 KLD -Fresh water from PHED supply.

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    8/14

    29 KLD -Recycled water from STP.

    2.3 Minerals (MT) No -

    2.4 Construction material stone,

    aggregates, and /soil (expected

    source-MT)

    Yes

    The construction will involve use of

    Stone, Stone Grit, Sand bricks and timber.

    The Stone and Stone grit is available from

    various queries operative around Kota

    city.The source of sand will be river bed sand

    from nearby river of Kota.

    Details are enclosed as Annexure-I.

    2.5 Forests and timber (source MT) Yes Timber will be obtained from authorized

    local timber merchant.

    2.6 Energy including electricity andfuels (source, competing users)

    Unit: fuel (MT), energy (MW)

    The total power demand of the projectwill be 1723 KW.

    The power will be received from JVVNLat 11 KV supply voltage, it will be

    stepped down to 0.433 KV through 1transformer of capacity 2500 kVA.

    To supplement above during power

    failure, it is proposed to provide 1 D.G.

    set of capacity 160 kVA for common

    facilities to cater the essential load only.

    2.7 Any other natural resources (useappropriate standard units)

    Yes Solar energy will be utilized for lightingof common areas and solar water heaters

    for providing hot water to residents.

    3. Use, storage, transport, handling or production of substances or materials,

    which could be harmful to human health or the environment or raise concernsabout actual or perceived risks to human health.

    S. No Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)

    with source of information data

    3.1 Use of substances or materials,

    which are hazardous (as per

    MSIHC rules) to human health

    or the environment (flora, fauna,

    and water supplies)

    No The proposed project will not use any

    hazardous material. Hazardous

    material in proposed project will be

    generated only as used lubricating oil

    from DG Sets which can cause healthhazard. This used oil will be sold to

    authorized recyclers.

    3.2 Changes in occurrence of disease

    or affect disease vectors (e.g.

    insect or water borne diseases)

    No Hygienic conditions will be

    maintained.

    3.3 Affect the welfare of people e.g.by changing living conditions?

    Yes The urban cities including Kota aresuffering from shortage of adequate

    and hygienic living conditions. This

    has resulted in mushrooming of

    unauthorized Colonies which lacks

    basic amenities.

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    9/14

    The proposed project will provide all

    basic amenities and hygienic and

    comfortable living conditions.

    3.4 Vulnerable groups of peoplewho could be affected by the

    project e.g. hospital patients,children, the elderly etc.,

    No There are a number of Schools,Colleges, Hospitals etc but it is a small

    group housing project and will notaffect vulnerable group of people.

    3.5 Any other causes No -

    4. Production of solid wastes during construction or operation or

    decommissioning (MT/month)

    S. No. Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)

    with source of information data

    4.1 Spoil, overburden or mine wastes No -

    4.2 Municipal waste (domestic and

    commercial wastes)

    Yes Municipal waste generated from

    residential portions:

    Total population of Residents = 1075

    Persons (considering @ 0.41

    Kg/day/person)

    Solid waste generation= 10750.41

    = 440.75 Kg/day Say 441 Kg/day

    Consider that 60 % of the total solid

    waste will be dry garbage and rest (40

    %) will be wet garbage.

    Dry Garbage = 441 0.60 = 264.6Kg/day

    Wet Garbage = 4350.40 = 176.4

    Kg/day

    Commercial area = 2310.65 m2

    Considering one worker for every 20

    m2area.

    No. of persons employed in

    commercial area are 115.

    Solid waste generated @ 0.41

    Kg/day/person

    Solid waste generation = 0.41 x 115=

    47.2 Kg/day Say 47 Kg/day

    Dry Garbage = 47 0.60 = 28.2

    Kg/day

    Wet Garbage = 470.40 = 18.8

    Kg/day

    Total Solid waste generation at project

    site = 441 + 47 = 488 Kg/day

    Total Dry Garbage = 292.8 Kg/day

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    10/14

    Total wet Garbage = 195.2 Kg/day

    Segregation will be practiced at the

    source level itself.

    Dry waste will be stored in the area

    marked for it, from where it will be

    sent for further disposal.

    Green waste will be converted intomanure along with S.T.P. sludge by

    vermiculture at the project site -

    provisions are made close to STP. The

    manure will be used to develop the

    greenbelt within the premises.

    Area specified for vermiculture will be

    surrounded by fast growing and

    canopy forming trees.

    4.3 Hazardous wastes (as per

    Hazardous waste ManagementRules)

    Yes Used lubricating oil from DG Set will

    be generated during construction ofthe building.

    Waste oil will be properly stored andsold to authorized recyclers.

    4.4 Other industrial process wastes No Not applicable as the proposed project

    is of construction and will not involve

    any industrial activity.

    4.5 Surplus product No Not applicable , Residential

    Apartment

    4.6 Sewage sludge or other sludge

    from effluent treatment

    Yes Dried sludge from STP will be used as

    manure for plants after treatment.4.7 Construction or demolition

    wastes

    Yes Construction wastes will be used for

    road construction.

    4.8 Redundant machinery or

    equipment

    No All machinery after construction will

    be removed from site

    4.9 Contaminated soils or other

    materials

    No No such material envisaged

    4.10 Agricultural wastes No Not applicable

    4.11 Other solid wastes No Not applicable

    5. Release of pollutants or any hazardous, toxic or noxious substances to air

    (Kg/hr)

    S. No. Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible) with

    source of information data

    5.1 Emissions from combustion of

    fossil fuels from stationary or

    mobile sources

    Yes The only source of pollution will be 1 D.G.

    Set of capacity 160 kVA. The emissions

    will be discharged through vent of proper

    height.

    D.G Set will confirm emission limits as

    prescribed under E P Act- 1986 and having

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    11/14

    acoustic arrangement as per EP act- 1986.

    The D.G Set will carry Type approval

    Certificate.

    5.2 Emissions from productionprocesses

    No -

    5.3 Emissions from materials handling

    including storage or transport

    Yes Dust during transportation and unloading

    of material. The measures to minimize the

    effects are given in EnvironmentalManagement Plan.

    5.4 Emissions from construction

    activities including plant and

    equipment

    Yes The measures to minimize the effects are

    given in Environmental Management Plan.

    5.5 Dust or odours from handling of

    materials including constructionmaterials, sewage and waste

    Yes The measures to minimize the effects are

    given in Environmental Management Plan.

    5.6 Emissions from incineration of

    waste

    No No such operations envisaged

    5.7 Emissions from burning of wastein open air (e.g. slash materials,

    construction debris)

    No Waste would be collected and handed overto the authorized vendor.

    5.8 Emissions from any other sources No -

    6. Generation of Noise and Vibration, and Emissions of Light and Heat:

    S. No. Information/Checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible) with

    source of information data with source

    of information data6.1 From operation of equipment

    e.g. engines, ventilation plant,

    crushers

    Yes but

    negligibl

    e

    Noise generated by equipment will be

    nominal. The measures to minimize the

    effects are given in Environmental

    Management Plan.

    6.2 From industrial or similar

    processes

    No It is a construction Project.

    6.3 From construction or demolition Yes But insignificant to result in adverse effecton environment.

    6.4 From blasting or piling No Not involved

    6.5 From construction or operational

    traffic

    Yes During construction phase the noise will be

    generated from movement of vehicles,

    earthwork, concrete mixer etc.

    6.6 From lighting or cooling systems No Silent generators will be used.

    6.7 From any other sources No -

    7. Risks of contamination of land or water from releases of pollutants into the

    ground or into sewers, surface waters, groundwater, coastal waters or the sea:

    S. No. Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)

    with source of information data

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    12/14

    7.1 From handling storage, use or

    spillage of hazardous materials

    Yes Used lubricating oil from D.G Set will be

    properly stored and sold to authorized

    recyclers.

    7.2 From discharge of sewage or othereffluents to water or the land

    (expected made and place ofdischarge)

    Yes The Sewage generated will be treated andhandled properly to minimize the impact.

    During construction phase septic tankwould be provided and during operation

    phase STP would be provided.7.3 By deposition of pollutants

    emitted to air into the land or into

    water

    No The only source of air pollution will be 1

    D.G. Set of capacity 160 kVA which

    would have vent of proper height.

    7.4 From any other sources No -

    7.5 Is there a risk of long term build

    up of pollutants in the environmentfrom these sources?

    No Not envisaged.

    8. Risk of accidents during construction or operation of the Project, which could

    affect human health or the environment

    S. No. Information/checklist

    confirmation

    Yes/No Details thereof (with approximate

    quantities/rates, wherever possible)

    with source of information data

    8.1 From explosions, spillages, fires

    from storage, handling, use or

    production of hazardous substances

    No These operations are not involved.

    8.2 From any other causes No -

    8.3 Could the project be affected by

    natural disasters causing

    environmental damage (e.g. floods,

    earthquakes, landsides, cloudburst

    etc)?

    Yes There is no history of such disasters.

    Proper safety measures as per Disaster

    Management Plan will be adopted to

    face such incidents.

    9. Factors which should be considered (such as consequential development)

    which could lead to environmental effects or the potential for cumulative impacts

    with other existing or planned activities in the locality.

    S. No. Information/checklist

    confirmation

    Yes/No Details thereof with approximate

    quantities/rates, wherever possible)

    with source of information data

    9.1 Lead to development of supporting.

    cities, ancillary development or

    development stimulated by the

    project which could have impact on

    the environment e.g.:

    Supporting infrastructure

    (Roads, power supply, waste or

    No The project is within municipal area of

    Kota district with well developed

    infrastructure.

    This is a small project and will not

    make any significant impact.

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    13/14

    waste water treatment etc.)

    Housing development

    Extractive industries

    Supply industries

    Other

    9.2 Lead to after-use of the site, which

    could haven impact on the

    environment

    No This is a construction Project.

    9.3 Set a precedent for later

    developments

    No The project will be developed strictly

    as per UIT rules.

    9.4 Have cumulative effects due to

    proximity to other existing or

    planned projects with similar effects

    No It is a well developed residential area.

    (III) Environmental Sensitivity

    S. No. Areas Name/

    Identity

    Aerial distance (within 15 km.)

    Proposed project location boundary1 Areas protected under international

    conventions, national or local

    legislation for their ecological,landscape, cultural or other related

    value

    No No such areas exist in the projectinfluence area.

    2 Areas which are important orsensitive for ecological reasons

    Wetlands, watercourses or otherwater bodies, coastal zone,

    biospheres, mountains, forests

    No No such areas exist in the nearvicinity.

    3 Areas used by protected, important

    or sensitive species of flora or faunafor breeding, nesting, foraging,

    resting, over wintering, migration

    No No such areas exist.

    4 Inland, coastal, marine or

    underground waters

    No Water requirement of construction

    will be met from authorized water

    supplier and during post construction

    water will be met from PHED supply.

    The application to PHED has been

    submitted. We are sure to get

    connection from PHED beforeoperation phase of project.

    We are planning to recharge runoff on

    100 % basis and also propose to

    recycle.

    5 State, National boundaries No -

    6 Routes or facilities used by thepublic for access to recreation or

    other tourist, pilgrim areas

    No -

    7 Defense installations Yes -

    8 Densely populated or built-up area Yes The project is proposed to come up in

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

    Authorized Signatory EIA Consultant

  • 8/11/2019 Skyline_Form_1_29112013

    14/14

    developing area of Kota city.

    9 Areas occupied by sensitive man-made land uses (hospitals, schools,

    places of worship, communityfacilities)

    No Number of Schools, places of worshipand hospitals are there in Kota but the

    project will not make any significantimpact on these.

    10 Areas containing important, high

    quality or source resources

    (ground water resources, surfaceresources, forestry, agriculture,

    fisheries, tourism minerals)

    No It is very small non polluting project.

    It will not have any impact on high

    quality resource.

    11 Areas already subjected to pollution

    or environmental damage.(those

    where existing legal environmental

    standards are exceeded)

    No Project is situated in urban setting (of

    Kota district). Moreover the housing

    projects do not warrant general

    condition or specific condition as per

    EIA Notification.

    12 Areas susceptible to natural hazardwhich could cause the project to

    present environmental problems(earthquakes, subsidence,

    landslides, erosion, flooding or

    extreme or adverse climatic

    conditions)

    No Kota is semiarid region and in the last40 years just five flooding events in

    Kota district have been reported.Kota is under seismic zone II as per

    NBC 2005. Hence it is a safe region.

    However, in structural design

    provision for earthquake forces have

    been made. Map of India showing

    seismic zones of India is enclosed

    with the questionnaire as Annexure-

    XVII.

    (b)

    I hereby given undertaking that the data and information given in the application and enclosuresare true to the best of my knowledge and belief and I am aware that if any part of the data andinformation submitted is found to be false or misleading at any stage, the project will be rejected

    and clearance give, if any to the project will be revoked at our risk and cost.

    Date:

    Place: Kota

    Ramesh Kumar Yadav

    (Director & Authorized Signatory)

    1/A, Rajeev Gandhi Nagar, Opp. City Mall,

    Jhalawar Road, Kota, Rajasthan

    Pin Code-324005

    M/s Sunprime Infratech Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.