RII Resources and Infrastructure IndustryRIIWMG203D Drain and dewater civil construction siteAssessment Tools – Candidate Guide

Candidate Name:

Page 2: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Copyright

© SkillsDMC. All rights reserved

SkillsDMC (Resources and Infrastructure Industry Skills Council Ltd)

Tower 1, Level 1, Suite 2, 475 Victoria Avenue, Chatswood, NSW 2067

Telephone: +61 (02) 9324 8600

Facsimile: +61 (02) 9324 8699

Email: [email protected]

Web: www.skillsdmc.com.au

Published by: SkillsDMC (Resources and Infrastructure Industry Skills Council Ltd)

Tower 1, Level 1, Suite 2, 475 Victoria Avenue, Chatswood, NSW 2067 AUSTRALIA

First published: 2015

Disclaimer:

SkillsDMC is the owner of all copyright and other intellectual property rights in the products and any modifications made by SkillsDMC to the materials (parent document issued to you at point of sale and as reflected in the invoice). You acknowledge that, apart from the limited licence granted under these Terms of Sale, you have no right, title or interest (including intellectual property rights) in the products. You will do anything reasonably required to give effect to SkillsDMC’s ownership of the products (parent document).

SkillsDMC Issued June 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction siteReview June 2016 Version 1

Page 2 of 21

Page 3: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

IntroductionIn preparation for your assessment, the trainer/assessor will advise you of the best approach in readiness for your assessment.

RIIWMG203D - Drain and dewater civil construction siteYou are now required to show your Assessor that you are competent in the tasks that you have learned. This guide will give you all the information that you will require in order to successfully complete your assessments.

The following pages must be completed, signed and returned to the trainer/assessor.

If you have any queries regarding your assessment, you should contact the trainer/assessor for guidance.

Completing the assessment All sections of the assessment must be completed with an ink pen. Pre–assessment: Make sure you understand the assessment and any appeal processes. Ask the

assessor to explain or clarify any information you do not understand. Both you and the assessor must sign the Pre-assessment form prior to commencing the assessment.

Performance will often need to be demonstrated over a period of time and/or in different locations. More than one assessment of a block of tasks may be necessary. Your assessor may copy any relevant part of a blank assessment tool for re-use, then date it and attach it to the original once completed.

Where appropriate, the assessor may assess your performance across different conditions e.g. wet and dry weather; day and night; different equipment attachments; different materials, etc.

Your assessor may provide suitable breaks if needed in the assessment activity between blocks of tasks.

Outcomes from your theory and other supporting evidence assessments will be reflected in the final assessment summary.

On completing the overall assessment the “Assessment Summary” sheet must be completed by both you and the assessor.

The assessor will communicate any feedback comments to you if required. If the Not Satisfactory box is ticked, the assessor will inform you and possibly your supervisor, to

discuss further training needs to be given to bring you up to a satisfactory level. Prior to commencement, you have the right to appeal under your organisation’s Fair Treatment

policy (or equivalent).

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 3 of 21

Page 4: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Marking Guide – Drain and dewater civil construction siteThe following information outlines the assessment items you will be required to complete for this unit. For each separate assessment method there are acceptable responses recorded and parameters are set in which the assessment context is defined.

Note that some methods require collection of a number of pieces of ‘evidence’ over a period of time. Other methods, such as the theory assessment, will take a limited number of time.

Assessment Method 1Nature of task: Direct Observation and Competency Conversation

Location for assessment: Candidate Workplace

Supervision: Trainer/ Assessor

Commence Date: Complete Date:

Information:

1. Skills need to be applied in the workplace in a variety of circumstances. As such, assessors must ensure that the Candidate can competently and safely undertake the task/s being assessed in different situations and conditions, to industry standards. Sound assessment practice involves the assessor determining that Candidates/employees are able to demonstrate the required level of performance prescribed by the unit of competency consistently, over time, and in a range of workplace conditions/settings.

2. Assessors will evaluate the skills demonstrated by Candidates as specified in the Observation Checklist, (contained in the Assessor Guide).The Assessor will also conduct a competency conversation to determine and record your competence. In other words, these questions guide conversation with you and assist in assessment. The notes taken about this conversation are important evidence for the assessment.

3. The Assessor will provide feedback to you and record results appropriately.4. You and the Assessor should ascertain appropriate times and dates with your Supervisors/ Managers

and plan for the assessment.5. The Assessor should explain the elements of the observation at the pre-assessment and outline how

you will be required to demonstrate competence at the time of the observation.

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 4 of 21

Page 5: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Method 2Nature of task: Theory / Questioning

Location for assessment: Workplace / Own time

Supervision: Trainer / Assessor

Commence Date: Complete Date:

Information:

1. The questions pertaining to this assessment are included in this Candidate Guide.2. The questions and candidate answers are to be submitted to the Assessor as evidence of competency.3. Candidates are required to complete these questions in their own time and to hand them back to the

Assessor at the time of final summative assessment.4. The Assessor should provide feedback to Candidate and record results appropriately on the Marking

Sheet provided (found within the Assessor Guide).

Assessment Method 3Nature of task: Supporting Evidence - Third Party (Supervisor Report)

Location for assessment: Workplace

Supervision: Supervisor

Commence Date: Complete Date:

Information:

1. The Third Party/ Supervisor Report template is included in this Candidate Guide.2. Once completed by your workplace Supervisor, this report is to be extracted from the Candidate Guide

and submitted to the Assessor as evidence of competency.3. Candidates are required to have their Supervisor complete this report in the workplace and to hand

back to the Assessor at the time of final summative assessment.4. The Assessor should provide feedback to the Candidate and record results appropriately on the

Marking Sheet provided (found within the Assessor Guide).

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 5 of 21

Page 6: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Method 4Nature of task: Workplace Portfolio (Project)

Location for assessment: Workplace/ Own time

Supervision: Trainer/ Assessor

Commence Date: Complete Date:

Information:

1. Instructions pertaining to the workplace portfolio (Project) are included in this Candidate Guide.2. The pages reflecting the workplace portfolio (Project) results are to be extracted and to be submitted to

the Assessor as evidence of competency.3. Candidates are required to complete this project in their own time and to hand back to the Assessor at

the time of final summative assessment.4. The Assessor should provide feedback to the Candidate and record results appropriately on the

Marking Sheet provided (found within the Assessor Guide).

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 6 of 21

Page 7: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Summary Cover SheetRIIWMG203D - Drain and dewater civil construction site

Candidate AssessorCandidate name:

(Print)

Candidate comments:

Assessor name:

(Print)

Assessor comments:

Co-AssessorCo-Assessor Assessor name:

(Print)

Co-Assessor comments:

Candidate information

Any documentation provided as evidence must be prepared by you to a satisfactory standard and be in accordance with workplace/site policy and procedures, and industry standards.

If collecting material for an assessment portfolio, please ensure that the confidentiality of colleagues, workers and other persons is protected, and block out any sensitive information.

If you have any doubts regarding confidentiality and privacy issues, contact the organisation concerned.

(Signature)

(Date)

(Signature)

(Date)

Candidate Declaration:

I declare that all work submitted for assessment has been completed by me, that all work has been attributed in the references provided for each item and that the intellectual property of authors is acknowledged.

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 7 of 21

Page 8: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Where work has been completed as part of a group activity, the work of each individual has been recognised.

Assessment Method 2 Theory – QuestioningThe following questions form part of your final Assessment in gaining competency in the following unit;

RIIWMG203D - Drain and dewater civil construction siteQ1. Identify three (3) component parts of a pump that should be checked during a pre-start inspection.

Q2. Identify three (3) potential risks or hazards that you may encounter while draining and dewatering a civil construction site.

Q3. Describe the potential impact on a site if an excavator digs into a water table.

Q4. Name 2 types of pumps that are used to move water on a construction site.

Q5. Name two (2) things you can do to reduce risk during manual handling.

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 8 of 21

Page 9: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Q6. Who should you report equipment faults to?

Q7. Which two (2) pre-start checks would you complete before starting a pump?

A. Look for spillage around the pump

B. Check walkways in place and free of hazards

C. Listen for unusual noise; eg, bearing wear

Q8. Where would you locate the document outlining the traffic signage requirements for a job?

Q9. Identify three (3) pieces of Personal Protective Equipment (PPE) that may be required when draining and dewatering a civil construction site.

Q10. Sediment control practices are used to prevent sand, soil, cement and other building materials from reaching waterways.

True

False

Q11. List three (3) factors that will affect sedimentation control.

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 9 of 21

Page 10: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 10 of 21

Page 11: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Q12. Which document would identify the appropriate sedimentation barriers to install? Where would you locate this document?

Q13. Name two (2) sedimentation barriers used on site.

Q14. Geotextile fabric sediment fences trap sediment but allow water through.

True

False

Q15. You are asked to check an electrical submersible pump that is in use. What do you check first?

Q16. When an electric pump is installed, the cable can be placed on the ground

True

False

Q17. Why is a non-return valve fitted to the start of the pump line?

Q18. Why do you need to check the pump on a regular basis?

A. Ensure it is still pumping

B. Check it is in the water and move if required

C. To check the inlet is not blockedSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and

dewater civil construction siteReview August 2016 Version 1

Page 11 of 21

Page 12: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

D. All of the above

Q19. If you don’t have a mechanical pump for draining, how do you drain surface water?

Q20. Where do you place the electrical submersible pump in a sump?

Q21. What is the difference between a “well” and a “sump”?

Q22. Locating the sump at the lowest point to be drained will maximise pump efficiency.

True

False

Q23. How should a submersible pump be placed into the water?

A. Level and upright

B. Pump is secured

C. Ensure the pump is not buried in mud

D. All of the above

Q24. If an extension cable is used, the back to back should be supported at least 1.5 metres above the ground.

True

False

Q25. Which way does an electric pump kick when started?

A. Clockwise

B. Anti-clockwise

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 12 of 21

Page 13: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 13 of 21

Page 14: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Q26. How would you clear a blocked non-return valve of the pump line?

Q27. Who can adjust a float switch on a stationary pump?

Q28. List two (2) vital fittings required in the air pump air supply line to the air pump.

Q29. What can be fitted to a pump line to assist pushing the water?

Q30. You are asked to remove an air pump from where it is being used. What is the first thing you should do?

Q31. The pump is noisy or vibrating. Name two (2) possible causes.

Q32. Materials should be recycled according to the project environmental management plan.

True

False

Q33. Fill in the missing words:

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 14 of 21

Page 15: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

At the end of the shift it is your responsibility to ensure the tools and equipment are _____________ and ________________.

Assessment Method 3 Supporting Evidence - Supervisor Testimony

Assessment Method 3 Supporting Evidence - Supervisor Testimony

Unit of Competency: RIIWMG203D - Drain and dewater civil construction site

Employee Name:

Employee’s start date with organisation:

Manager Name:

Workplace & Address:

To form part of the process of gathering evidence of competence the Assessor is seeking ‘Supervisor Testimony’ from the Candidate’s line manager. As part of the assessment for the unit listed above, the ‘Performance and Knowledge’ required for this unit has been mapped to the Foundation skills required for this unit.

Do you believe the Candidate displays the following skills to perform their job tasks to industry standards to meet the following:

Satisfactory ()

Communication (verbal and non-verbal) and Interpersonal Skills to:

Clarify and confirm work requirements and instructions Make verbal reports about plant, tools and equipment Clarify environment protection requirements Use a range of communication techniques Use civil construction terminology

Yes

No

Reading skills to read, understand and apply relevant documentation such as:

Relevant legislation Site policies, procedures and work methods Manufacturer’s guidelines, specifications and manuals Australian standards Code of practice Work instructions Traffic management plan Environmental management plan Risk management plan Workplace forms and templates

Yes

No

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 15 of 21

Page 16: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Method 3 Supporting Evidence - Supervisor Testimony

Do you believe the Candidate displays the following skills to perform their job tasks to industry standards to meet the following:

Satisfactory ()

Numeracy skills to:

Interpret engineering drawings, project drawings, site diagrams Estimate the amount of water to be drained Determine the correct location for a sump or well Carry out relevant measurements for example: well depth, slope. Calculate the appropriate flow rate for pump/s Interpret and measure tolerances and dimensions

Yes

No

Writing skills to complete:

Fault reports Incident/accident reports Environment reports

Yes

No

Learning skills to recognise and respond to:

Non-compliant work Faults with plant, tools and equipment Environmental issues, risks and hazards Appropriate Personal Protective Equipment (PPE) for work tasks Sedimentation control requirements Construction principles Recognise recyclable materials

Yes

No

Any other comments:

Candidate Signature:

Manager Signature:

Date:

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 16 of 21

Page 17: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Method 3 – Other Supporting EvidenceCandidate Name:

Assessor Name:

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations

Other Assessment Evidence: Assessment ComponentMap to relevant assessment component

Satisfactory ()

Other 3rd party report

Details:

Other 3rd party verification of employee performance

Yes

No

Induction / Employer Training Program(s)

Details:

Candidate has participated in Employer Induction / training program(s)

Yes

No

Relevant licence / certificate

Details:

Relevant licences/certificates sighted and endorsed

Yes

No

Work log book / Equipment use log

Details:

Log book sighted and endorsed

Yes

No

Training record book

Details:

Training record sighted and endorsed

Yes

No

Feedback to Candidate:

Candidate Signature: Date:

Assessor Signature: Date:

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 17 of 21

Page 18: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Assessment Method 4 Workplace Portfolio (Project)RIIWMG203D - Drain and dewater civil construction site Part A. Create a workplace portfolio of documentation relevant to draining and dewatering a civil

construction site. Attach all relevant documents.

Part B. Provide a workplace log book documenting your experience draining and dewatering a civil construction site. You may also include video and photographic evidence where you consider it appropriate.

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 18 of 21

Page 19: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Additional SectionThis section provides scope for you to add supplementary assessment items. It can be used to customise additional assessment methods and/or contextualised questions.

The Context of AssessmentThe RTO/Compliance Manager should take time to consult with the candidate’s site to determine the information that will complete the list below. Each of the assessment methods in this Guide should then be conducted using this list as a reference. This will help to ensure that the assessment process is consistent with the organisation’s/site’s work context.

Where assessment is being conducted in a simulated environment, the RTO should complete this page based on the documentation, policies, procedures and equipment that are used in the simulated environment. Further information about appropriate simulated assessment environments can be found in the SkillsDMC Companion Volume: Implementation Guide, available from www.skillsdmc.com.au.

The Assessor using this document should take time to familiarise themselves with the items in the list below. Where this is not possible, the Assessor should consider working with an Industry Subject Matter Expert from the organisation/site who is already familiar and experienced with the items listed.

Specific company policies that must be assessed against:

Specific company procedures (including work procedures) that must be assessed against:

Specific legislative/regulatory/statutory documentation that must be adhered to during the assessment:

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 19 of 21

Page 20: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

Additional ItemsCandidate Name:

Assessor Name:

Evidence

Satisfactory ()

Yes No

Feedback to Candidate:

Workplace project comments:

Candidate Signature: Date:

Assessor Signature: Date:

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 20 of 21

Page 21: SkillsDMC New Template Candidate guide - … · Web viewSkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site Review August 2016 Version

RTO Name here

RTO ID Number here

SkillsDMC Issued August 2015 Candidate Guide RIIWMG203D Drain and dewater civil construction site

Review August 2016 Version 1

Page 21 of 21