Site Report Poroton Home. to Building shell – in record time. In record time to the complete building shell. Location: Trier Outside wall: ThermoPlan T10 Inside wall: Planziegel Hlz Incl. special bricks Team: 3 workers (1 master craftsman, 2 assistant ) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Site Report Poroton Home

Site ReportPoroton Home

to Building shell – in record time

Page 2: Site Report Poroton Home

In record time to the complete building shell

•Location: Trier•Outside wall: ThermoPlan T10•Inside wall: Planziegel Hlz•Incl. special bricks

•Team: 3 workers (1 master craftsman, 2

assistant)•Constr. period: 5 days for the complete

building shell.

Page 3: Site Report Poroton Home

The bottom slab is casted

Page 4: Site Report Poroton Home

The first delivery

Page 5: Site Report Poroton Home

Professional discharging

Page 6: Site Report Poroton Home
Page 7: Site Report Poroton Home

The second delivery... Everything has to be at it‘s place.

Page 8: Site Report Poroton Home

The first layer

Page 9: Site Report Poroton Home

After 4 hours , the first layer is ready

Page 10: Site Report Poroton Home

Now, the plan-bricks have to be worked up

Page 11: Site Report Poroton Home

Brick after brick

Page 12: Site Report Poroton Home

Some hours later-The building is growing fast

Page 13: Site Report Poroton Home
Page 14: Site Report Poroton Home

The result of one day

Page 15: Site Report Poroton Home

The next day - The inside walls

Page 16: Site Report Poroton Home

Nearly ready

Page 17: Site Report Poroton Home

After 30 hours with 3 workers

Page 18: Site Report Poroton Home

After 30 hours with 3 workers

Page 19: Site Report Poroton Home

During the time lag of ceiling delivering – the garage was

built

Page 20: Site Report Poroton Home

Bricks for the top floor

Page 21: Site Report Poroton Home

Again – the first layer is ready

Page 22: Site Report Poroton Home

Exact plans allowed the preparation of the bricks for the pitch

Page 23: Site Report Poroton Home

Usage of U-Blocks for the ring armature

Page 24: Site Report Poroton Home

The ring armature encloses the masonry

Page 25: Site Report Poroton Home

Some details

Page 26: Site Report Poroton Home

Working with concrete is finished

Page 27: Site Report Poroton Home

Inside walls in top floor

Page 28: Site Report Poroton Home

Now, the truss can be constructed

Page 29: Site Report Poroton Home

Craftsmanship – just great

Page 30: Site Report Poroton Home

Insulation at the ring armature....

Page 31: Site Report Poroton Home

Finished

Page 32: Site Report Poroton Home

The result of 120 hours work

Page 33: Site Report Poroton Home

FinallyThe complete building shell was finished after 5 days.

-With 1 craftsman and 2 helpers -Top quality, 100% brick

A brickhouse makes you happy