Work Scope
• Remove vegetation
Exotic brush
• Fill and grade site
Raise site 3 feet
Install runoff detainage
• Install chain-link fence
• Install landscaping
Landscaping
• 14 mahogany trees
• 33 bald cypress trees
• 42 Eagleston holly trees
• 24 live oak trees
• 7 sweet bay magnolia trees
• 10 cabbage palm trees
• 340 Florida privet hedge
• 513 Simpson’s stopper shrubs
• 218 Walter’s viburnum shrubs
• 340 Florida privet hedges
• 513 Simpson’s stopper shrubs
• 218 Walter’s viburmum shrubs
• 110,000 square feet bahia sod
• sprinkler system 4” 30-gph well 2.5-hp pump
Work Scope
• Improve Alabama Road South
• LCEC will repair potholes and cap road with a minimum of 4 inches compacted lime rock from SR82 to the southern-most property line of Southwest Lehigh Substation
Staff Recommendation
• Low bidder: Taylor Pansing
• Longstanding relationship
• Performed work at North Trail, Trafalgar, Lake Trafford, Corbett, and Del Prado substations