site name: · web viewthis method statement covers the installation of the drainage including...
TRANSCRIPT
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard1 of 6METHOD STATEMENT
Drainage Connection Works
1 Description of Works, Duration and Location
This method statement covers the installation of the drainage including new manholes and also connecting in to Existing Manholes/ Drains. The pipes will be various sizes ranging from 150mm to 300 mm dia. The manholes will be precast concrete1200mm dia and the drainage depths for the connections are approx. – 3500mm in different locations.
The duration of works will be approx. 5 weeks as per the contract programme.
Location of the site is : Middlewood Locks, Salford, Manchester
2 Supervision (incl Phone Numbers)
ACS Contracts Manager – Paul Howard – 07875 425128ACS Site manager– Mick Ellis – 07794 027460ACS Site Engineer – Dave Longden – 07823 550461
3 Information Available on Known Hazards
Movement of plant – Works will be carried out within exclusion zones with a competent Banksman in attendance.
Refer to site specific risk assessment register for applicable risk assessments.There may be a number of live services within the site working area, these services will be identified using site plans, cable avoidance tools / equipment and trial holes as and when required.
ACS has been issued with the relevant utility survey drawings which indicate the services expected in each location. Each specific excavation will be accompanied by a marked up service drawing which will be issued along with the permit to dig. All excavations and mechanical works will be controlled by the issue of specific permits to dig. All permits will be issued by BCEGI on request.
4
SITE PLAN – Planned works areas
Work OperationsNo works are to commence until the following processes/procedures are in place:
1. This Method Statement & associated Risk Assessments have been submitted to the relevant persons / Authorities.
2. Site inductions and site briefings have been completed.3. Agree and mark out areas with the relevant persons / Authorities.4. Check existing service drawings, carry out CAT scans advise relevant persons of any findings.
Erect fencing to segregate the work area and agree with the principle contractor
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 1 of 6
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard2 of 6METHOD STATEMENT
Drainage Connection Works
safe pedestrian access / signage and relevant traffic management systems.5. Issue to the operatives a permit to dig with a copy of the relevant service drawings.6. All ACS site operatives & management associated with the project, have the appropriate
CSCS / CPCS training certs.7. All Approved for Construction drawings & Schedules will be available on site.8. Sufficient and suitable welfare facilities will be established on site by the client.9. The works area and agreed fencing lines has been defined and agreed between all parties.
Once the above is in place, site works can proceed as follows:
DRAINAGE SEQUENCE
The site engineer will mark out the position of the drainage run to the latest revision drawing. Proposed manhole location will then be excavated using the 20t Excavator to a depth of
225mm below the existing pipe invert level a per the specification. The excavation will be checked on weekly basis and recorded on an excavation inspection
sheet by a competent person. The excavation will receive a visual inspection at the start of each shift by a competent person.
Manhole excavations will be stabilized using sheet and frame shoring equipment. Temporary works designs will be passed on to the client for approval before work commences.
Access to the excavation will be via a wooden pole ladder fixed to a purpose made ladder platform that is attached to the trench sheets.
A gas monitor will be hung on a rope within the excavation throughout the shift. Readings will be logged on a topman record at 8am, 1030am, 130pm and 4pm.
An escape set will be kept within easy reach in the excavation throughout the shift. All material generated will be left on site and the laydown/ storage area will be confirmed and
agreed with BECGI on site. On completion of the excavation specified concrete will placed to the man hole base, additional
care will be taken to ensure the concrete surrounds the underside of the existing pipe work in the outfall manholes where applicable.
A section of the existing pipe will be removed and a new channel will be installed with one new rocker pipe outside of the manhole on both sides.
Precast concrete manhole rings will be lifted into place using certified man hole lifting eyes THE EXCAVATOR BUCKET MUST BE REMOVED WHILST PLACING THE MAN HOLE RINGS. Grano benching will be formed to complete the base. When possible the benching works are to be carried out before the man hole cover slab is in place, this will reduce the amount of works carried out within a confined space. Operatives entering a confined space must be trained and signed onto the confined space method statement.
Once the manhole rings have been installed, a manhole surround shutter will be set in place and concrete will be placed and vibrated around the manhole. This will then be left till the next working day before it is stripped, this is to ensure that the concrete has cured enough before disturbing it.
Any backdrops will be constructed as per the design details with full concrete surround. Suitable protection will be placed to the openings within the cover slab to prevent falls and the
area will remain fenced until the backfill works are complete. Any ground water encountered will be controlled by pumping and discharging into agreed
locations which will be agreed before any works begin. No personnel are to enter any unsuitable trench/excavation and daily inspections must be
carried out and inspections recorded weekly. These will be issued to BCEGI on a weekly basis along with all plant check sheets and also small tools and lifting equipment weekly logs.
All excavations when left open must be fenced off to prevent unauthorized access. Specified backfill will be placed in layers by the machine and once the agreed cover to the pipe
is reached the trench will be compacted by roller or vibrating plate.
5 Control of Operations
Ensure a competent and authorised person is in attendance throughout the duration of the site works.
Ensure a site induction is provided and attended by all persons involved in the works.
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 2 of 6
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard3 of 6METHOD STATEMENT
Drainage Connection Works
Ensure all site specific hazards are identified & any control measures are in place and understood.
Ensure a daily POWRA is undertaken at the start of each shift, by the competent person.
Ensure all operatives sign in and sign out a daily basis.
All plant movements are controlled by banksman.
All plant and wagons leaving the site do so with due regard to other road users and pedestrians.
Ensure compliance with method statements and associated documentation.
Ensure all operatives are fully briefed and understand any site specific escape procedures that are in place, this will be discussed in the site induction.
Deep excavation, information and warnings signs are to be erected at each work location and remain in place until the works are complete.
6 Storage / Materials Handling
A designated storage area must be identified and agreed with the client. All materials must be stored in this area, unless otherwise agreed with the client.
All materials will be stored in the site compound and brought to the face of work as and when required.
All materials will be delivered using Hampson street as access, all deliveries will be co-ordinated through the client to ensure there is a planned rotation to all deliveries.
7 Operatives (incl. Competence)
Machine / Plant Operators – E Carroll - CPCS / CSCS
Pipe Layer – Patrick Clarke – CSCS / CPCS- and Confined space trained
Slinger Banksman – Chris Livesy – CPSC – CSCS and Confined space trained
8 Accompanying Risk Assessments
Refer to site specific risk register for identified risk assessments.
ACS-P16-008-RA-COM-005
Refer to site specific COSHH register for identified COSHH assessments
1. Concrete/Cement2. Grease3. Diesel Engine Oil4. Petrol5. Hydraulic Oil
9 Plant and Equipment
20 tonne excavator9 tonne forward tipping dumperBomag 120 rollerCompressor & breakersCable Avoidance ToolForward & Reverse Plate CompactorHerras Fence Panels & Work Signs.Sthil Saw
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 3 of 6
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard4 of 6METHOD STATEMENT
Drainage Connection Works
Battery Powered pipe Lasers.Gas monitorRelevant shoring equipmentLifting chains & shackle (suitably rated for loads requiring lifting)GeneratorsWater pumpsHand ToolsDavit winch arm (for use in specific rescue procedure)
ALL SMALL ITEMS OF PLANT SHOULD BE SAT ON DRIP TRAYS WITH SPILL KITS IN CLOSE PROXIMITY.
NO SEMI-AUTOMATIC QUICK HITCH DEVICES ON ALL EXCAVATORS – FULLY AUTOMATIC OR FULLY MANUAL ONLY.
10 Safety of Third Parties
The work site is located within a secure site fence line, all excavations and plant movements are to be co-ordinated and where possible carried out within fenced areas.
Consideration will be shown to the local residents at all times, work will be done in an agreed sequence and cause as little disruption as possible.Other contractors may be present on site undertaking various works. The work area`s will be segregated with fencing and appropriate signage to prevent unauthorised access.
Co-ordination meetings will be held weekly.
No tools or equipment will be left out overnight and will be locked away in the designated storage cabin. This will be agreed with the client on arrival to site.
11 PPE Requirements
MANDATORY PERSONEL PROTECTIVE EQUIPMENT.
Hard hat,Safety boots,Hi-viz Clothing.Safety GlassesSafety Gloves appropriate to the work tasksEar defenders to be available as well all other PPE deemed relevant to the tasks to be carried out.
12 First Aid Requirements (incl. Name of first aider)
First aid kits will be available on site, in the site office`s.
ACS - nominated first aider`s: Mick Ellis – Chris Livsey
Nearest hospital –Salford Royal NHS Foundation Trust
13 Welfare Requirements
Welfare facilities are available on site. This will be discussed within the site induction.
14 Fire and Emergency Procedures
Muster point and fire procedure plans will be displayed in the site office and advised at the site inductions.
15 Confined Space Entry
1. Barriers will be erected around the manhole.
2. The manhole cover will be removed and allowed to vent for 15 minutes.
3. Peak gas readings will be taken and logged on a topman record. A gas
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 4 of 6
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard5 of 6METHOD STATEMENT
Drainage Connection Works
monitor will be left in the manhole on a rope and readings will be logged every 2 hours.
4. A tripod and winch will be erected above the manhole.
5. An operative will attach via harness to the tripod.
6. The operative will enter the manhole via the manhole steps or pole ladder. The operative will carry an air escape set while he is in the manhole.
7. The topman will stay at the manhole while work is being carried out.
8. The operative inside the manhole will leave via the steps or pole ladder after the work is complete.
9. Equipment will be removed from the manhole.
The cover will be replaced and barriers will be removed.
16 Confined Space Emergency Procedures
In the event of a gas alarm the following procedures will be followed.
The operative in the base of the excavation/manhole will don the escape set which must always be kept within easy reach.
The operative will egress the excavation/manhole via the pole ladder/manhole steps.
Work must cease and the site supervision must be informed.
Work can only resume when the site supervision have confirmed it is safe to do so.
17 Environmental Issues
Site specific environmental issues:
1. Refuelling Activities - ACS to ensure that all refuelling operations are carried out in a designated area with fuel spill kits available on hand. Emergency procedures to be displayed at re-fuelling designated area.
2. All timber will be supplied with the relevant FSC certification.
3. Concrete wash out – The concrete wagons will wash out in the designated wash out area (to be agreed on site). This will be created by utilising a small metal skip, lined with plastic sheeting. The concrete delivery drivers will be directed to wash out in the skip. Upon completion of the concrete works, the washout/water will be left to settle and solidify. The water will be segregated and removed from the skip (usually by small pump) and disposed into an agreed soakaway area of the site. The solidified concrete will be disposed off site, with the skip, to the local recycling facility.
4. Surface water and pumping from excavations will be required and specific locations will be identified and procedures agreed with site management.
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 5 of 6
ACS CONSTRUCTION GROUP Ref :Revision :
Issue Date :Originated By :
Page :
ACS-P16-008-MS-001319-07-2016P Howard6 of 6METHOD STATEMENT
Drainage Connection Works
Person producing the Method Statement:Name (Please print):
Paul Howard
Signature: Position:
Contracts Manager
Date:
06-04-2016
Person approving the Method Statement:Name (Please print):
Terry Day
Signature: Position:
SHE Manager
Date:
06-04-2016
ALL PERSONS SIGNING THIS METHOD STATEMENT WILL HAVE READ SIGNED AND UNDERSTOOD THE CONTENTS OF THIS METHOD STATMENT AND THE ASSOCIATED RISK ASSESSMENTS. If site conditions vary or if works are to be carried out in a different manor or sequence then it should be included in the amendment procedure on page 8.
Employee Signatures:No Signature Name/Date No Signature Name/Date
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
Important Telephone Numbers
Paul Grady ACS Managing and Safety Director 07771 730 490
Danny Doohan ACS Operations Director 07764 443 280
Paul Howard ACS Contracts Manager 07875 425128
Terry Day ACS SHE Manager 07800 604 877
Office ACS Office at Cheadle Hulme 0161 486 6300
Amendment Procedures
If it is necessary to amend this method statement, the method statement will be rewritten.
Form: ACS FRM 015 Issue: 13 (27-05-2015) Originator: S. Curran Page 6 of 6