sisk's latest plan for greystones harbour, with phasing

13
architectural visualisation 15 hazelbrook road terenure dublin 6w tel 01 4965340 project: Phasing Development, Greystones PHASE 1 Month 1 - Month 14 36 Houses and Block O, Club Buildings and Part1 of the Public Square

Upload: basil-milller

Post on 01-Apr-2016

218 views

Category:

Documents


3 download

DESCRIPTION

Plan for construction phasing at Greystones Harbour prepared for Sisk or their architects

TRANSCRIPT

Page 1: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 1Month 1 - Month 14

36 Houses and Block O, Club Buildings and Part1 of the Public Square

Page 2: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 2Month 12 - Month 24

(PHASE 1 complete)

21 Houses

Page 3: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 3Month 16 - Month 28

(PHASE 2 complete)

53 Houses

Page 4: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 4Month 19 - Month 32

(PHASE 4 ongoing)

28 Apartments, Public Square Part 2 and Public Park

Page 5: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 4Month 19 - Month 32

(PHASE 4 complete)

28 Apartments, Public Square Part 2 and Public Park

Page 6: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 5Month 18 - Month 42

(PHASE 3 complete)

49 Apartments and 4 houses

Page 7: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 6Month 29 - Month 44

(PHASE 5 complete)

39 Apartments and 4 houses

Page 8: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 7Month 41 - Month 55

(PHASE 6 complete)

41 Apartments and 6 houses

Page 9: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 8Month 45 - Month 61

(PHASE 7 complete)

52 Apartments and 6 houses

Page 10: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 9Month 38 - Month 51

(PHASE 8 complete)

19 houses

Page 11: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

COMPLETION

Page 12: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 1a5 Aug 2014 - 17 Sept 2015

Page 13: Sisk's latest plan for Greystones Harbour, with phasing

architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones

PHASE 1b5 Aug 2014 - 17 Sept 2015