sisk's latest plan for greystones harbour, with phasing
DESCRIPTION
Plan for construction phasing at Greystones Harbour prepared for Sisk or their architectsTRANSCRIPT
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 1Month 1 - Month 14
36 Houses and Block O, Club Buildings and Part1 of the Public Square
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 2Month 12 - Month 24
(PHASE 1 complete)
21 Houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 3Month 16 - Month 28
(PHASE 2 complete)
53 Houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 4Month 19 - Month 32
(PHASE 4 ongoing)
28 Apartments, Public Square Part 2 and Public Park
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 4Month 19 - Month 32
(PHASE 4 complete)
28 Apartments, Public Square Part 2 and Public Park
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 5Month 18 - Month 42
(PHASE 3 complete)
49 Apartments and 4 houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 6Month 29 - Month 44
(PHASE 5 complete)
39 Apartments and 4 houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 7Month 41 - Month 55
(PHASE 6 complete)
41 Apartments and 6 houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 8Month 45 - Month 61
(PHASE 7 complete)
52 Apartments and 6 houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 9Month 38 - Month 51
(PHASE 8 complete)
19 houses
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
COMPLETION
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 1a5 Aug 2014 - 17 Sept 2015
architectural visualisation15 hazelbrook road terenure dublin 6w tel 01 4965340project: Phasing Development, Greystones
PHASE 1b5 Aug 2014 - 17 Sept 2015