SIS 2006 Update. March 22, 2006. Big Picture. Design Phase – April 13 Conceptual Design, Final Design Draft Design Phase – May 30 Configuration Documentation & Testing Preparatory Projects Phase – April 17 – May 30 - PowerPoint PPT PresentationTRANSCRIPT
SIS 2006 Update
March 22, 2006
Big Picture
• Design Phase – April 13– Conceptual Design, Final Design Draft
• Design Phase – May 30– Configuration Documentation & Testing
• Preparatory Projects Phase – April 17 – May 30– Reconfigure K12/HAN/Library, Replace current HECN
routers, Video testing, local projets
• Implementation – June 12 – August 18– Details to be determined
Design
• Conceptual Design is due March 24
• Physical Designs due April 13
• Start equipment orders following week– Includes order lag time and setup time
• Document Configuration
• Perform Testing
Preparatory Projects Phase
• Things we can do before the actual implementation
• Planning the details now – Draft Due April 13
Implementation Phase
• Can’t be determined until many of the design tasks completed
• Planning for it will occur through the month of May
• Intend to have at least K12 & HE completed by August deadline
Current Risks
• Weather in the Red River Valley– Several fiber runs to be completed
• Compressed timeline may impact “burn-in” time
• New Technology
More Information
• Next IVN Session = April 26• www.stagenet.nd.gov/projects/infrastructure/index.html
– Biweekly status reports– Project Plans– RFPs– Lots More
Questions