![Page 1: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/1.jpg)
Dulles Corridor Metrorail ProjectSilver Line Phase 2 Implementation
Board Transportation Committee Update
December 12, 2017
Mark Canale, Fairfax County Project ManagerFairfax County Department of Transportation
![Page 2: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/2.jpg)
2
Project Status
Phase 1
• Old Meadow Road Realignment – 90% design complete. Construction completion scheduled for the end of 2018.
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 73% complete
• Package A (Rail line, system, and stations) – 74%
• Package B (Rail yard at Dulles) – 69%
• Contractual Substantial Completion – August 2019 • WMATA Board to establish Revenue Operations Date
![Page 3: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/3.jpg)
3
• Reston Town Center Station – Precast & structural steel detailing, pavilion area work ongoing, pedestrian bridge erection
• Herndon Station – Structural steel painting and detailing, south pavilion construction, pedestrian bridge erection and decks poured
• Innovation Station – Detailing work, pedestrian bridge erection, pavilion construction, skylights installed, electrical and plumbing
Phase 2 – Station Construction
![Page 4: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/4.jpg)
4
• Dulles Airport Station – Structural steel roof erection, station mechanical/electrical/plumbing work, tunnel tie-in
• Loudoun Gateway Station – Station precast, roof erection, mechanical electrical plumbing rough in, pedestrian bridge are being assembled
• Ashburn Station - Station foundation, columns, support walls, precast erection, and pedestrian bridge being assembled
Phase 2 – Station Construction
![Page 5: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/5.jpg)
5
• Pedestrian bridges set at Herndon, Reston Town Center, and Innovation Center Station
• Aerial guideway rail and concrete ties, switch work, track
• Utility Relocation ongoing
• Traction Power Feeders – continue to install duct bank to tie into Traction Power Substations (TPSS) and Tie Breaker Stations (TBS)
• Ground grids being installed to TPSS and TBS, continue 34.5kV cable installation and conduit installation
• Three TPSS structures delivered and assembled on slab
Phase 2 – Aerial, Track, Utilities, Systems
![Page 6: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/6.jpg)
6
• Under Construction - Service and Inspection Building, Maintenance Way Building, Transportation Police Building, Train Wash Facility, Warehouse Facility, Vehicle Storage Facility
• Ongoing - Track work in rail yard, utility installation, duct bank, storm lines, sanitary lines, water lines, site lighting, and site road work.
Phase 2 – Rail Yard at Dulles Airport
![Page 7: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/7.jpg)
7
• Budget• Total Budget $2.778B• Total Forecast $2.778B• Total Expenditures $1.482B
• Contingency Utilization• Total Contingency $551.5M• Total Contingency Utilized $197.8M• Remaining Contingency $353.7M
Phase 2 – Cost Summary
![Page 8: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/8.jpg)
8
• Total Project Estimate: $44.5M
• Construction Progress: 55% complete
• Garage Bridge Erection: Completed Nov 2017
-Access road re-opened as scheduled-
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): February 2019 – March 2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
![Page 9: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/9.jpg)
Herndon Monroe Bridge Construction
9
![Page 10: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/10.jpg)
10
Herndon Metrorail Garage
PHOTOS
![Page 11: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/11.jpg)
11
• Total Project Estimate: $52 million
• Construction Progress: 18% complete
• Precast Fabrication: October 2017
• Precast Erection: April 2018
Schedule
• Construction Award: March 2017
• Construction: April 2017
• Ready for Occupancy: April/May 2019
Innovation Metrorail Garage
![Page 12: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/12.jpg)
12
Innovation Metrorail Garage
![Page 13: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/13.jpg)
13
Reston Town Center Station
![Page 14: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/14.jpg)
14
Herndon Station
![Page 15: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/15.jpg)
15
Innovation Center Station
![Page 16: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/16.jpg)
16
Dulles Airport Station
![Page 17: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/17.jpg)
17
Rail Yard Dulles Airport
![Page 18: Silver Line Phase 2 Implementation - Fairfax County...Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 12, 2017 Mark](https://reader034.vdocuments.mx/reader034/viewer/2022050714/5f09eca17e708231d42928b9/html5/thumbnails/18.jpg)
18