Significant Wood Design and ConstructionChanges to the 2018 IBC and NDS-BCD121
Michelle Kam-Biron, P.E., S.E., S.E.C.BSenior Director, EducationAmerican Wood Council
Lori Koch, P.E.Manager, Educational OutreachAmerican Wood Council
Participants may download the presentation here: http://www.awc.org/education/resources
The American Wood Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider # 50111237.Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
2/21/2019
2
Course Description
The 2018 International Building Code (IBC) published by the International Code Council and the National Design Specification® (NDS) for Wood Constructionpublished by the American Wood Council are both now available. This presentation will provide an overview of the significant changes to wood design and construction provisions relative to previous editions and include design examples. Most of the changes in the NDS are a result of the adoption of the ASCE/SEI Standard 7-16 Minimum Design Loads and Associated Criteria for Buildings and Other Structures which includes increased wind loads.
Learning ObjectivesUpon completion, participants will be better able to identify:
Identify changes in the 2018 IBC and NDSNDS Changes
Identify wind load increases in ASCE 7-16that affect wood design and construction
ASCE 7-16
Identify new fastener provisions developed to address increased wind loads
Fasteners
Design nails for withdrawal and head pull-through to resist new wind loads
Nail Design
1 3
2 4
2/21/2019
3
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
Polling Question1. What is your profession?
a. Architect
b. Engineer
c. Code Official
d. Fire Service
e. Builder/Manufacturer/Other
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 6
IBC
2018
• Exterior Balconies
• Fire Retardant Treated Wood
• Heavy Timber & Mass Timber
• Construction Type
2/21/2019
4
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
NDS History
1944
1962
1968
1971
1973
1977
1982
1986
1991
1997
2001
2005
2012
2015
2018
2015
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
ANSI ACCREDITATIONAWC – ANSI-accredited standards developer• Consensus Body
• Wood Design Standards Committee
2/21/2019
5
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 9
NAVIGATING THE IBC
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
202 DEFINITIONS
Conventional Light-Frame Construction (Modification)Light-Frame Construction (Modification)
2/21/2019
6
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 1
FRT WOOD SHEATHING EXT. WALL ASSEMBLIES
602.3, 602.4.1• Fire-retardant-treated wood framing
and sheathing permitted within exterior walls of Type III and IV construction
• 2-hour rating or less
• Type IV - Minimum of 6 inches in thickness
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 2
TYPE IV CONSTRUCTION
602.4 TYPE IV• Minimum sizes moved to Ch. 23
2/21/2019
7
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 3
COL. PROTECTION IN LIGHT-FRAME CONSTRUCTION
704.2, 704.4.1• Required fire-resistance rating
permitted to be provided with membrane protection
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 4
COLUMNS WITHIN WALL ASSEMBLY
IBC 704.2 and 704.3 No additional fireproofing required for the column in the assembly
2/21/2019
8
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 5
706.2• Applicable only in SDCs D, E and F
• Allows for continuous diaphragm for floor and/or roof assembly
• Also stabilizes double fire walls to resist impact during seismic event
STRUCTURAL CONTINUITY OF DOUBLE FIRE WALLS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 6
STRUCTURAL CONTINUITY OF DOUBLE FIRE WALLS
Graphics: WoodWorks
2/21/2019
9
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 7
DEFLECTION – TABLE 1604.3
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 8
DEFLECTION – TABLE 1604.3
2015 IBC
2018 IBC
2/21/2019
10
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 1 9
DEFLECTION – TABLE 1604.3
2015 IBC
2018 IBC
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 0
TABLE 1607.1Balcony & Deck live load
= 1.5 x room live load
< 100 psf
Same as occupancy served
DECK LIVE LOADS
2/21/2019
11
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 1
1615• New section and definitions
address tsunami-resistant design of critical infrastructure and essential facilities
• Applicable to Risk Category III and IV structures located in Tsunami Design Zones
TSUNAMI LOADS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 2
1704.6.1 1704.6.2 & 1704.6.3• Clarifies and consolidates requirements for structural observation for both
seismic and wind into 1704.6.1
• Modifies the wind trigger from structural observation from 110 mph to 130 mph for Risk Categories III or IV
STRUCTURAL OBSERVATION
2/21/2019
12
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 3
1705.11.1 Structural wood• Clarifies the main wind force-resisting system fastening exception to special
inspection in wood frame construction (based on nail spacing for sheathing exceeding 4 inches on center) at the panel edges.
SPECIAL INSPECTION
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 4
POLLING QUESTION
2. Which of the following is NOT true for floor sheathing at light‐frame double fire walls? It may be:
a) 1” thick.
b) Continuous thru fire walls in SDC E‐F
c) Continuous thru fire walls in high wind zones & SDC D.
d) Answers b) and c)
2/21/2019
13
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 5
Chapter 23WOOD
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 6
• 2018 National Design Specification(NDS) for Wood Construction
• 2015 Special Design Provisions for Wind and Seismic (SDPWS)
• 2018 Wood Frame Construction Manual for One-and-Two Family Dwellings (WFCM)
• ANSI 117-2015 Standard Specification for Structured Glued Laminated Timber of Softwood Species
REFERENCED STANDARDS
2/21/2019
14
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 7
• ANSI A190.1-2017 Structural Glued Laminated Timber
• ANSI/APA PRG-320-2017 Standard for Performance-Rated Cross-Laminated Timber
• ANSI/APA PRP 210-2014 Standard for Performance-Rated Engineered Wood Siding
• ANSI/APA PRR 410-2016 Standard for Performance-Rated Engineered Wood Rim Boards
REFERENCED STANDARDS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 8
2303.2.2• Lumber of FRT wood to be
impregnated with chemicals• Paints, coating, stains and
other surface treatments not an approved method
FIRE-RETARDANT-TREATED WOOD
2/21/2019
15
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 2 9
2303.2 Fire-retardant-treated wood. Fire-retardant-treated wood is any wood product that, when impregnated with chemicals by a pressure process or other means during manufacture, shall have, when tested….
2303.2.2 Other means during manufacture. For wood products impregnated with chemicals by other means during manufacture, the treatment shall be an integral part of the manufacturing process of the wood product. The treatment shall provide permanent protection to all surfaces of the wood product. The use of paints, coatings, stains or other surface treatment are not an approved method of protection as required in this section.
FIRE-RETARDANT-TREATED WOOD
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 0
TABLE 2304.9.3.2• New alternative fastener
schedule for construction of mechanically laminated decking [also called Nail Laminated Timber (NLT)]
• Provides for equivalency where power-driven fasteners are used instead of 20d nails
MECHANICALLY LAMINATED DECKING
Architect: Profeta Royalty ArchitectureStructural Engineer: Structural FocusCompleted: 2011
2/21/2019
16
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 1
MECHANICALLY LAMINATED DECKING
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 2
MECHANICALLY LAMINATED DECKING
2/21/2019
17
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 3
TABLE 2304.10.1• 8d common and ring shank
nails now addressed for fastening of roof sheathing when nailing 6 inches or 12 inches on center
• Provides for alignment of 2018 IBC and IRC
FASTENERS SCHEDULE ROOF REQUIREMENTS NAILS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 4
RING SHANK NAILS
2/21/2019
18
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 5
HEAVY-TIMBER CONSTRUCTION
2304.11• Heavy timber provisions of
Chapter 23 have been reorganized
• Wood member size equivalencies relocated from Section 602.4
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 6
HEAVY-TIMBER CONSTRUCTION
Relocated from Ch. 6
2/21/2019
19
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 7
2304.12.2.5, 2304.12.2.6SUPPORTING MEMBERS FOR PERMEABLE FLOORS AND ROOFS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 8
SUPPORTING MEMBERS FOR PERMEABLE FLOORS AND ROOFSIBC & IEBC CH. 1
• Details in construction documents and inspections for impervious moisture barriers used in exterior balconies.
2/21/2019
20
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 3 9
2304.12.2.5, 2304.12.2.6
• Where an impervious moisture barrier system is used to protect the wood structure supporting moisture-permeable floors, positive drainage and ventilation shall be provided for water that infiltrates the moisture-permeable floor topping
SUPPORTING MEMBERS FOR PERMEABLE FLOORS AND ROOFS
Requires positive drainage
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 0
HEADER AND GIRDER SPANS – EXTERIOR WALLS
2/21/2019
21
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 1
HEADER AND GIRDER SPANS – EXTERIOR WALLS
TABLE 2308.4.1.1 (1)
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 2
HEADER AND GIRDER SPANS – INTERIOR WALLS
2/21/2019
22
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 3
2308.5.5.1• Single member headers now
permitted in Section 2308• Typically limited to spans of
2-4 ft, Table 2308.4.1.1(1)• Increases energy efficiency by
allowing for a greater thickness of cavity insulation
OPENINGS IN EXTERIOR BEARING WALLS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 4
ASCE 7-16Changes
2/21/2019
23
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 5
• General reference to ASCE 7 references 2015 edition in IBC Chapter 35
• IBC wind and seismic load provisions agree with updated criteria in ASCE 7-16
• References in IBC Chapter 18 Soil & Foundation seismic provisions to coordinate with ASCE 7-16
ASCE 7-16 CHANGES
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 6
IBC allows three paths to determine snow load:
1. Use the IBC to determine snow loads (Figure 1608.2 or Table 1608.2 for Alaska)
2. Use new ASCE 7 tables for the western US and New Hampshire.
3. Reference state produced maps which have greater detail for the western US and New Hampshire.
ASCE 7-16 CHANGES
2/21/2019
24
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 7
• Requirements for secondary drains –rain loads • ASCE 7-16 bases minimum requirements
on a 15 min/100-yr event.
• IBC still uses the 1 hr/100-yr event for both primary and secondary minimum drain flow.
ASCE 7-16 CHANGES
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 8
RESOURCES
http://www.awc.org/pdf/codes-standards/publications/archives/StructureMag-CodesStandards_ReprintWithAppendix-Tyree-1801.pdf
2/21/2019
25
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 4 9
RESOURCES
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S 5 0
RESOURCES
https://buildingscience.com/documents/building-science-insights-newsletters/bsi-093-all-decked-out
2/21/2019
26
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
Polling Question
3. Exterior balconies w/ an impervious moisture barrier system over wood structure supporting moisture‐permeable floors shall have:
a) Positive draining of water
b) Ventilation below the floor system
c) Details in construction documents
d) Inspections for impervious moisture barriers
e) All of the above.
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 2
2018 NDS® CHANGESNational Design Specification® for Wood Construction
2/21/2019
27
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 3
GOVERNING CODES FOR WOOD DESIGN
2018 NDS referenced in 2018 IBC and IRC
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 4
GOVERNING CODES FOR WOOD DESIGN
2015 SDPWS referenced in 2018 IBC and IRC
2/21/2019
28
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 5
2018 NDS – PRIMARY CHANGES
• References ASCE 7-16• Added equation for withdrawal design values for
smooth shank stainless steel nails• New provisions for Roof Sheathing Ring Shank
nails in accordance with ASTM F 1667• New design provisions for fastener head pull-
through • Revision to method for calculating lateral design
values for threaded nails • Revised timber rivet design value tables• Revised terminology for Fire Design of Wood
Members• NDS Supplement design values updated
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 6
NDS 2018 CHAPTERS1. General Requirements for Structural Design *2. Design Values for Structural Members *3. Design Provisions and Equations *4. Sawn Lumber *5. Structural Glued Laminated Timber *6. Round Timber Poles and Piles7. Prefabricated Wood I-Joists8. Structural Composite Lumber *9. Wood Structural Panels10. Cross-Laminated Timber *11. Mechanical Connections *12. Dowel-Type Fasteners *13. Split Ring and Shear Plate Connectors14. Timber Rivets *15. Special Loading Conditions16. Fire Design of Wood Members *
* Changes
2/21/2019
29
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 7
A. Construction and Design PracticesB. Load Duration (ASD Only)C. Temperature EffectsD. Lateral Stability of BeamsE. Local Stresses in Fastener GroupsF. Design for Creep and Critical Deflection ApplicationsG. Effective Column LengthH. Lateral Stability of ColumnsI. Yield Limit Equations for ConnectionsJ. Solution of Hankinson EquationK. Typical Dimensions for Split Ring and Shear Plate ConnectorsL. Typical Dimensions for Dowel-Type Fasteners and WashersM. Manufacturing Tolerances for Rivets and Steel Side Plates for
Timber Rivet Connections N. Appendix for Load and Resistance Factor Design (LRFD) –
Mandatory
NDS 2018 APPENDICES
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 8
1. Sawn Lumber Grading Agencies2. Species Combinations3. Section Properties4. Reference Design Values
• Sawn Lumber and Timber*• MSR and MEL *• Decking• Non-North American Sawn Lumber *• Structural Glued Laminated Timber *• Timber Poles and Piles
NDS 2018 SUPPLEMENT
* Changes
2/21/2019
30
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S5 9
CHAPTER 1
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 0
MINIMUM DESIGN LOADS
• Reference Loads• Minimum Load Standards• ASCE 7-16
2/21/2019
31
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 1
NOTATION
1.6 Notation
• EIeff = effective bending stiffness of the CLT section, lbs-in.2/ft of panel width
• GAeff = effective shear stiffness of the CLT section, lbs/ft of panel width
• DH = fastener head diameter, in.
• WH, WH' = reference and adjusted pull-through design value, lbs
• tns = net side member thickness, in.
• achar = effective char depth, in
• aeff = effective char depth, in.
• t eff = non-linear effective char rate (in./hr.0.813) adjusted for exposure time, t
CLT
Fasteners
Fire
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 2
CHAPTER 2
2/21/2019
32
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 3
LOAD DURATION FACTOR
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 4
POLLING QUESTION
4. Exterior Load Duration Factor, CD for Impact Loads is limited to 1.6 wood structural panels
a) True
b) False
2/21/2019
33
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 5
CHAPTER 3
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 6
BEAM STABILITY FACTOR
Source: APA
3.3.3 Beam Stability Factor, CL
2/21/2019
34
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 7
CHAPTER 4
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 8
FLAT USE FACTOR
x
x
yy
2/21/2019
35
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S6 9
INCISING FACTOR
4.3.8 Incising Factor, Ci
Dimensional lumber - Allowance for incising factors from company providing incising
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 0
CHAPTER 8
Source: APA
2/21/2019
36
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 1
DRY SERVICE CONDITIONS
Source: APA
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 2
VOLUME FACTOR
Volume Factor Cv –Tension parallel to grain
2/21/2019
37
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 3
CHAPTER 10
Source: Seagate
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 4
FORMAT CONVERSION FACTOR
Format Conversion Factor
2/21/2019
38
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 5
DEFLECTION – EFFECTIVE SHEAR STIFFNESS
Per ANSI/APA PRG 320-2017
Source: APA
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 6
CHAPTER 11
Roof Sheathing Ring Shank Nails
Option to address significant increases in ASCE 7-16 C&C roof
wind pressures
2/21/2019
39
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 7
ADJUSTMENT FACTORS – HEAD PULL-THROUGH
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 8
WET SERVICE FACTORS – HEAD PULL-THROUGH
2/21/2019
40
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S7 9
CHAPTER 12
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 0
TYPICAL NAIL HEADS
ASTM F1667ASTM F1667
ESR 1539ESR 1539 Photos courtesy of Hitachi – Falcon - Hitachi
Photos courtesy Falcon Fasteners
2/21/2019
41
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 1
TYPICAL NAIL SHANKS
Photos courtesy of Falcon Fasteners
Sketches courtesy ISANTA
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 2
TYPICAL NAIL POINTS
Photos courtesy of Falcon Fasteners
2/21/2019
42
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 3
ROOF SHEATHING RING SHANK NAILS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 4
SMOOTH SHANK NAILS OR SPIKES
2/21/2019
43
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 5
CARBON STEEL NAIL WITHDRAWAL
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 6
STAINLESS STEEL NAIL WITHDRAWAL
NEW
2/21/2019
44
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 7
SMOOTH SHANK NAIL WITHDRAWAL STRENGTH
0
5
10
15
20
25
30
35
40
45
0.55 0.5 0.45 0.4 0.35
Pounds per in
ch of pen
etration
Wood specific gravity
ASD Withdrawal Strength(Smooth shank, 8d common nail)
Carbon steel (bright or galvanized) Stainless steel
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 8
DEFORMED SHANK NAILS
2/21/2019
45
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S8 9
RSRS NAIL WITHDRAWAL
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 0
FASTENER HEAD PULL-THROUGH
2/21/2019
46
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 1
FASTENER HEAD PULL-THROUGH
NEW
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 2
FASTENER UPLIFT CAPACITY
Fastener Uplift Capacity = lesser of W’ and WH’
2/21/2019
47
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 3
FASTENER UPLIFT DESIGN EXAMPLE
Fastener Uplift Capacity - Roof Sheathing Ring Shank Nail
7/16 OSB
2x6
RSRS
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 4
FASTENER UPLIFT DESIGN EXAMPLE
Fastener Uplift Capacity - Roof Sheathing Ring Shank Nail (cont.)
2/21/2019
48
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 5
FASTENER UPLIFT DESIGN EXAMPLE
Fastener Uplift Capacity - Roof Sheathing Ring Shank Nail (cont.)
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 6
FASTENER UPLIFT DESIGN EXAMPLE
Fastener Uplift Capacity - Roof Sheathing Ring Shank Nail (cont.)
Fastener head pull-through of 67 lbs is less than withdrawal capacity of 88 lbs and controls design capacity. See NDS Table 11.3.1 for application of additional adjustment factors for connections based on end use conditions.
2/21/2019
49
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 7
FASTENER UPLIFT CAPACITY
2018 WFCM Table 3.10
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 8
1
• Increase in hurricane regions
• Larger roof zones
• Interior roof zones increase most
C&C Loads
ASCE 7 WIND LOAD CHANGES
http://www.structuremag.org/?p=13360
2/21/2019
50
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S9 9
ASCE 7 WIND LOAD CHANGES
C&C Roof Coefficients
Roof Slope
Ratio of ASCE 7-16/ASCE 7-10Roof GCp - GCpi Roof Overhang GCp - GCpi
3r 3e 2r 2n 2e 1 3r 3e 2r 2n 2e 1
7 < Θ ≤ 20 1.36 1.14 1.69 1.69 1.16 2.02 1.27 1.11 1.59 1.59 1.14 -
20 < Θ ≤ 27 1.36 0.96 1.43 1.43 0.89 1.56 1.27 0.97 1.36 1.36 0.91 -
27 < Θ ≤ 45 1.58 2.45 1.43 1.58 1.43 1.68 1.40 2.00 1.30 1.40 1.30 -
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 0
FASTENER UPLIFT CAPACITY COMPARISONS
110mph Exposure B, 7/16" WSP, Framing G = 0.42, Rafter spacing = 24”• For lower wind speed zones and lower G framing, RSRS gives simpler nailing schedule option
Nail Type Perimeter Nailing (Zones 2 & 3)
Interior Nailing (Zone 1)
RSRS 6/12 6/128d Common 6/6 6/12
2/21/2019
51
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 1
FASTENER UPLIFT CAPACITY COMPARISONS
180mph Exposure B, 19/32" WSP, Framing G = 0.55, Rafter spacing = 24”• Assume complex roof where separating perimeter and interior zones is difficult• RSRS nails with 19/32" WSP allow 6/6 nailing everywhere – simple • For higher wind speeds and higher G framing, RSRS provides beneficial options
Nail Type Perimeter Nailing Interior NailingRSRS 6/6 6/128d Common 4/4 6/6
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 2
DOWEL DIAMETER
Roof Sheathing Ring Shank
Post-Frame Ring Shank
2/21/2019
52
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 3
RSRS NAIL LATERAL VALUES
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 4
POLLING QUESTION
5. The new equations for fastener head pull‐through are based on which of the following:
a) Fastener head diameter
b) Specific gravity of side member
c) Net side member thickness
d) All of the above
2/21/2019
53
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 5
CHAPTER 16
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 6
CHAR RATE
2/21/2019
54
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 7
CHAR DEPTH
Structural Fire
Design
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 8
CONNECTIONS
Photo courtesy of Softwood Lumber Board
2/21/2019
55
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 0 9
APPENDIX L
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S1 1 0
APPENDIX L
NEW
2/21/2019
56
S i g n i f i c a n t W o o d D e s i g n a n d C o n s t r u c t i o n C h a n g e s t o t h e 2 0 1 8 I B C a n d N D S
RESOURCES
E-courses
2018 NDS Changes - National Design Specification®
for Wood Construction (STD120)
2018 WFCM Changes - Wood Frame Construction Manual for One- and Two-Family Dwellings (STD350)
http://awc.org/education/ecourses
T h i s p r e s e n t a t i o n i s p r o t e c t e d b y U S a n d I n t e r n a t i o n a l C o p y r i g h t l a w s . R e p r o d u c t i o n , d i s t r i b u t i o n , d i s p l a y a n d u s e o f t h e p r e s e n t a t i o n w i t h o u t w r i t t e n p e r m i s s i o n o f A m e r i c a n W o o d C o u n c i l ( A W C ) i s
p r o h i b i t e d . © A m e r i c a n W o o d C o u n c i l 2 0 1 7
in [email protected] | www.awc.org
This concludes the American Institute of Architects Continuing Education Systems Course