Sherpa Trade and Invest 76 (Pty) Ltd
Forestry and Related Waste Streams for the Production of Renewable Energy
2
Agenda
Background
Location - Sawmill Problems and the Ideal Solution
Project
Connectivity
Client
3
Background
Sherpa was formed with the main purpose of becoming a Power Utility Company in South Africa to achieve the following Goals:
• To assist Eskom with constant stable Power in the allocated areas
• To assist the surrounding businesses with an environmental solution for the waste streams
To provide South Africa with a new exciting Industry in the Biomass Power Generation sector
To provide a solution to Southern Africa in the form of a waste to energy programe
4
Agenda
Background
Location – Sawmill Problems and the Ideal solution
Project
Connectivity
Client
5
Northern
Cape
Limpopo
Western
Cape
Eastern Cape
North WestGauteng
Sherpa will convert wood and related waste streams from plantations and sawmill into renewable energy.
• Operations are located in the Mpumalanga Province
Operation Area
Swaziland
6
Reason and Method for Power Generation
Eskom power line (GGN 79/5) supply is poor (30%)
Forestry area – Sawmills and Plantation produce waste streams
Power line (GGN 79/5) supply will increase to 52% with the additional Power
Local municipality and outer communities will benefit from the Power Generation and supply in the area
7
Forestry Area – Local sawmills (100 Km radius)
8
Common Problems caused at sawmills
9
Agenda
Background
Location – Sawmill Problems and the Ideal solution
Project
Connectivity
Client
10
Project
The Project is to Generate Power through Biomass Gasification using waste streams from the surrounding areas and this will be done as follows:
• Collection of waste streams from several sawmills in the area (Sawdust, Bark and Wood pieces)
• Processing of the waste streams to the correct size and moisture content
– > 10mm x 10mm x 10mm
– > 20% moisture content
• Storage of the wet and dry waste streams
• Gasification of the solid waste streams into a synthetic gas form
• Cleaning and cooling of the synthetic gas
• Power production by means of synthetic gas generators (2.4 Mwe @ 400 VAC)
• Controlling, metering and measuring of the Power produced
• Step up to 22Kv
• Metering, reverse protection and connection to the National grid at point GGN 79/5
11
Gasification Power Generation model
12
Actual Plant Design - Graskop
13
Project Summary
1) Eskom has a 9 Mwe supply line that currently supplies only 2.78 Mwe (30%). An additional 2.0 Mwe will increase the capacity to 4.78 Mwe (52%)
2) The local area will benefit from the additional Power been supplied
3) An Environmental problem that has been ongoing for years will be solved
4) Much needed work will become available directly and indirectly to the project
14
Agenda
Background
Location – Sawmill Problems and the Ideal solution
Project
Connectivity
Client
15
Connectivity
Eskom has three 22 Kv lines that supply the local area namely:
Graskop town sub station / Venus area
Groothout line to a major sawmill
Pilgrims Rest / Leroro area
Sherpa will produce Power and supply the correct phase, voltage and current to the main GGN line that will feed the above lines
There are four metering point:
Low voltage
High voltage
Eskom point
Client/Eskom point
16
Connectivity diagram
17
Agenda
Background
Location – Sawmill Problems and the Ideal solution
Project
Connectivity
Client
18
Client
The Client is the Listed Company – Carbon Worx
They have agreed to purchase all the Power generated
They will have a meter point at their site and will be credited by Eskom for the Power consumed with accordance to the DUoS (Distribution Use of System) agreement
The DUoS has been drawn up between Eskom, Sherpa and the client
A PPA (Power Purchase Agreement) has been drawn up between the Sherpa and the client
The above mechanism is a Third Party Wheeling arrangement
The tariff has been submitted to Nersa with accordance to the PPA