sharing the scars of a p3 capital project john illingworth deputy ceo ~ goodwin development trust
TRANSCRIPT
Our initial considerations
Does your project:-• Fit the funders criteria• Match• State Aid• Land • Planning permission• Cashflow• OJEU
Good SPD fit
Sure Start Cap and Rev
N/A !
You need to own some
New build/refurb
It goes out first
£3.8 M
What do you know about building?
• Who has delivered a £1M capital project before ?
• Ask someone who has
How do I appoint ...
• Valuer• Contractor • Architect • Mechanical & Electrical engineers• Structural engineers • Quantity Surveyors• Clerk of Works• Lawyer
What did that assumption cost?
• £145,000• And a threat of a Judicial Review
It isn’t just cash that costs