session 5 4th edition pmp
TRANSCRIPT
![Page 1: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/1.jpg)
Project Time Management
![Page 2: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/2.jpg)
Knowledge Area
Process
Initiating Planning Executing Monitoring & Control Closing
Time
Activity DefinitionActivity SequencingActivity Resource EstimatingActivity Duration EstimatingSchedule Development
Schedule Control
Enter phase/Start project
Exit phase/End project
InitiatingProcesses
ClosingProcesses
PlanningProcesses
ExecutingProcesses
Monitoring &Controlling Processes
Project Time Management
![Page 3: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/3.jpg)
Schedule management plan
• - How will I develop schedule? And control it?
• - Create this Document is not identified as
Separate Process.
• - It is part of Project management plan
![Page 4: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/4.jpg)
Work package
decompose
activities
![Page 5: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/5.jpg)
Rolling wave planning• form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS
![Page 6: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/6.jpg)
Define Activities• The process of identifying the specific actions to be performed
produce the project deliverables.• Work package decomposed into activities (schedule activities)
Inputs
1. Scope baseline2. Enterprise environmental factors
3. Organizational process assets
Tools & Techniques
1. Decompositions2. Rolling wave planning3. Templates4. Expert judgment
Outputs
1. Activity list2. Activity attributes3. Milestone list
![Page 7: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/7.jpg)
Activity List• The activity list is a comprehensive list including all
schedule activities required on the project.
• The activity list includes the activity identifier and a
scope of work description for each activity in
sufficient detail to ensure that project team members
understand what work is required to be completed
![Page 8: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/8.jpg)
ACTIVITY LISTProject Title: Date Prepared:
ID Activity Description of WorkFollow WBS or schedule
Activity name. Description of activity in enough detail so that the person(s) performing the work understands what is required to complete it.
![Page 9: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/9.jpg)
العمل وصف الرق النشاطم
الـتأريض موصالت تمديد يتمالمعدنية باالجزاء وربطها
للمبنى
شبكة عمل المبنى تأريض
1001
والتفتيح التكسير يتماالسالك لمقاطع
مجاري تفتيح
المواسير
1002
العلب اماكن تحديد يتممبين هو كما وتركيبها
باللوحات
علب تركيباالنارة
1003
= جيدا بالعلب المواسير اتصال
المواسير و مقاطع مطابقة
وعدد للمخططات طبقا=
التسليك وجداول األسالك
تمديد
المواسير
1004
2012/10/15 خاص : التاريخ مستشفى بناء المشروع
![Page 10: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/10.jpg)
Activity attributes
• Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.
• The components for each activity evolve over time. During the initial stages of the project they include the Activity ID, WBS ID, and Activity Name, and when completed may include activity codes, activity description
![Page 11: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/11.jpg)
ACTIVITY ATTRIBUTESProject Title: Date Prepared:
ID:
From activity list
Activity:
From activity list
Description of Work:
A description of the activity in enough detail so that the person(s) performing the work understands what is required to complete it.
Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag
Any activities that must occur before the activity.
The nature of the relationship, such as start-to-start, finish-to-start, or finish-to-finish.
Any required delays between activities (lag) or accelerations (lead).
Any activities that must occur after the activity.
The nature of the relationship, such as start- to-start, finish-t-start, or finish-to-finish.
Any required delays between activities (lag) or accelerations (lead).
Number and Type of Resources Required:
The number and roles of people needed to complete the work.
Skill Requirements:The level of skill necessary to complete the work (expert, average, novice or applicable job level).
Other Required Resources:Any equipment, supplies, or other types of resources needed to complete the work.
Type of Effort:
Indicate if the work is a fixed duration, fixed amount of effort, level of effort, apportioned effort or other type of work.Location of Performance:
If the work is to be completed somewhere other than at the performing organizations site, indicate the location.Imposed Dates or Other Constraints:
Indicate any fixed delivery dates, milestones or other constraints.Assumptions:
List any assumptions about resource availability, skill sets, or other assumptions that impact the activity.
![Page 12: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/12.jpg)
ACTIVITY ATTRIBUTESProject Title: Date Prepared:
ID:
1004Activity: المواسير تمديد
Description of Work:
= جيدا بالعلب المواسير اتصال
التسليك و وجداول األسالك وعدد للمخططات طبقا= المواسير مقاطع مطابقة
Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag
مجاري تفتيح
المواسير
تتوقف بداية النشاط الحالي على بداية النشاط السابق
يوم واحد يسبق في البدء
تركيب لوحات التوزيع الفرعي.ة
اماكن تحديدوتركيبها العلب
.
اليوجد
Number and Type of Resources Required:
عدد ( لكل) 3مطلوب كهربائيالكلي العدد يكون 12دور
كهربائي
Skill Requirements:
خبرة سابق له يكونبكهرباء العمل فيوله المستشفياتبالكود بالعمل خبرة
القياسي المصري
Other Required Resources:
اتركيب على مشرف مهندس وجود
Type of Effort:
لمدة العمل العاملين 8يكون وعدد يوميا المشرف 12ساعات والمهندس Location of Performance:
المستشفى مبنى وهو المشروع مكان فيImposed Dates or Other Constraints:
I عن اليزيد فيما النشاط من االنتهاء يوم 15مطلوبAssumptions:
الموجودة العمالة في المهارة ووجود العمل النجاز المطلوبة العمالة توفير يفترض
![Page 13: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/13.jpg)
• A milestone is a significant point or event in the project. A milestone list identifies all milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.
Milestone List
![Page 14: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/14.jpg)
MILESTONE LISTProject Title: Date Prepared:
Milestone Milestone Description TypeMilestone name. Description of milestone in
enough detail to understand what is needed to meet the milestone.
Internal or external. Interim of final. Mandatory or optional.
![Page 15: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/15.jpg)
المشروع مراحل قائمة2012/10/15لتاريخ ا
بناء : المشروع اسمخاص مستشفى
المرحلة نوع المرحلة وصف المرحلة
جزء بها ضرورية مرحلة
االعمال وهو داخلي
خارجي وجزء المساحية
البنكية الضمانات وهو
مكاتب االشرافتجهيزالتأمينات تجهيز
البنكية والضماناتوتنفيذ األرض تسوية
المساحية األعمال
التحضير
داخليا وتتم ضرورية هي الحفر آليات بإستخدام تتم ” أعمال وتشمل الكباش"
الحفرالدمك أعمال
الدمك أعمال فحص
الحفر
داخليا وتتم ضرورية هي محاور ) تثبيتالشبمونة( األعمدة
القواعد طوبارتسميح حديد وتثبيت تنفيذ
القواعدالقواعد صب
ز القواع اا طوبار دلة
القواعد
![Page 16: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/16.jpg)
• Sequence Activities• Process of identifying and documenting relationship among the project activities
Inputs
1. Activity list2. Activity attributes3. Milestone list4. Project scope statement5. Organizational process assets
Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Applying leads and lags4. Schedule network templates
Outputs
1. Project schedule network diagram
2. Project document updates
![Page 17: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/17.jpg)
Precedence Diagramming Method (PDM)
• Finish-to-Start (FS)
• Finish-to-Finish (FF)
• Start-to-Start (SS)
• Start-to-Finish (SF)
logical relationships:
![Page 18: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/18.jpg)
• Applying Leads & Lags• Use leads and lags to support realistic and achievable project schedule.
• Each activity is connected at least to one predecessor and one successor except the start and the end.
• Leads.– May be added to start an activity before the predecessor activity is complete.
• Lags– Inserted waiting time between activities
A B C
predecessor Successor
B
A
B
A
![Page 19: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/19.jpg)
Dependency DeterminationTo define sequence among activity, these type of dependency are used:
1. Mandatory (hard logic)– Inherent in the nature of work being done or required by the contract– E.g. You must design before you can develop
2. Discretionary (preferred, preferential, or soft logic)– Define base on knowledge– Can be changed if needed– Important when how to shorten or re-sequence the project
3. External– Based on the need t of the party outside the project
![Page 20: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/20.jpg)
.1 Project Schedule Network Diagrams
- Project schedule network diagrams are schematic
displays of the project’s schedule activities and the
logical relationships among them, also referred to as
dependencies..
- A project schedule network diagram can be
produced manually or by using project management
![Page 21: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/21.jpg)
Activity-On-Node (AON)
Precedence Diagramming Method (PDM)
![Page 22: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/22.jpg)
![Page 23: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/23.jpg)
•1- you are a project manager on a us $5.000.000 software development Project . While Working with your project team to develop a network diagram ,your data architects suggest that quality could be improver if the data model is approved by senior management before moving on the other design elements. They support this suggestion with an article from a leading software development journal. Which of the following best describes what this type of inputs is called?
•A- mandatory dependency
•B- discretionary dependency
•C- external dependency
•D- heuristic
![Page 24: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/24.jpg)
2- Which of the following is not an activity attribute:
1-Person responsible for the activity
2-Location where to perform the activity
3-Time when to perform the activity
4-Leads and Lags
![Page 25: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/25.jpg)
3-Lag means:
A-the amount of time an activity can be delaying the project
finish date.
B- the amount of time an activity can be delayed without
delaying the early start date of its successor
C- waiting time
D-the product of a forward and backward Pass
![Page 26: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/26.jpg)
•4-Activity Definition is typically performed by which of the following
A-Project Manager who created the WBS
B.Project Team Members responsible for the work package
C.Project Officer
D.Project Stakeholder
![Page 27: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/27.jpg)
5- A schedule activity may begin 10
days before the predecessor activity
finishes This is an example of
A-ADM2-PDMC- A dependency with lag
D- A dependency with lead
![Page 28: Session 5 4th edition PMP](https://reader035.vdocuments.mx/reader035/viewer/2022081514/554c6bfeb4c90575798b4c0b/html5/thumbnails/28.jpg)
Thank you