Page 1: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Session 4KY Type 1 End Treatment

ET-PLUS Slide 6 by Trinity Highway Products

SKT-SP Slide 63 by Road Systems

Page 2: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

How do you know which version of a Proprietary Guardrail End

Treatment KY is Using?

Go to the KYTC Div of Design Home Page

http://transportation.ky.gov/Highway-Design On the lower right click on Standard

Drawing Brings up:

Standard Drawings Active Sepia List Approved Shop Drawings - Click

The drawings show the version PLUS, SP, 27 etc.

Basic Info – very useful

Page 3: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

http://transportation.ky.gov/Highway-Design Design Home PageStandard Drawings Lower Right

Page 4: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Standard DrawingsActive Sepia ListApproved Shop Drawings

Click

Page 5: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Approved Shop DrawingsClick “Alternate 1 Trinity ET

Plus”

Page 6: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Approved Shop Drawing “Alternate 1 Trinity ET Plus”

Page 7: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

The ET-Plus KY Uses is50’, 7 SYT Post & 1 HBA Post

The Title Block Details which ET-Plus Model KY is using

Page 8: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Parts ListYou can learn a lot just looking

at the Parts List and the Drawing

Page 9: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Standard Drawing RBR-020 Guardrail End Treatment

Type 1

Page 10: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Standard Drawing RBI-004Installation of Guardrail End

Treatment Type 1

Page 11: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Installation Instructions for Proprietary Guard Rail End

Terminals This Std Draw Note appears on each Proprietary End

Treatment used in KY - “The Manufacturer SHALL furnish two (2) sets of shop plans to the contractor with each installation”

Each Proprietary End Treatment “see shop drawings” Added to Sect 719.03 of 2012 Std Specs: “Proprietary

end treatments SHALL be installed according to the manufacturer’s assembly or installation instructions”

SHOULD NOT LET THE CONTRACTOR BEGIN INSTALLATION BEFORE SUPPLYING YOU WITH THESE SHOP PLANS & INSTALLATION INSTRUCTIONS – Both you and the contractor need these documents to properly do your jobs of installing and inspection propriety guardrail end terminals

Page 12: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Type 1 Trinity – ET-Plushttp://www.highwayguardrail.com/products/etplus.html

Page 13: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Type 1 ET-PlusStandard Drawing Note

“The Manufacture Shall Furnish Two (2) Sets of Shop Plans to the Contractor with Each Installation”

For the ET-Plus this is on line at http://www.highwayguardrail.com/pro

ducts/pdfs/ETPlus-Manual.pdf Call 1-800-527-7976 if you do NOT Understand Manual

This Manual is cumbersome and somewhat hard to follow

Page 14: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

http://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdf

Page 15: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus - Absorbs Energy by Extruding the Rail Thru Impact Head and Knocking Down Post

Page 16: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Hit ET-Plus with SYT Post that Bend (Yield) upon

Impact

Page 17: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plushttp://www.highwayguardrail.com/products/etplus.html

Energy Absorbing End Treatment 50 feet long Post 1 - HBA Post (Hinged Break-

Away) Post 2-8 7 SYT Post (Steel Yielding

Terminal) Has a Strut between Post 1&2 No Tube or Soil Plates Standard Guardrail begins at Post 9

Page 18: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plushttp://www.highwayguardrail.com/products/etplus.html

Do Not attach Guardrail to Post 1 Under no circumstances shall the

guardrail within the ET-Plus Pay Limit be Curved – see Installation Instructions

Page 19: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing HBA Post-Bottom

Post 1

Install the Bottom of the HBA Post such that the LARGE HOLE 13/16” is placed downstream (away from the Impact Head)

Page 20: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing HBA Post-Top

Post 1 Align the Holes of the Post Plates

(either side of Ears) on the Top and Bottom Post

Insert a 3/8” x 2” Hex Head Bolt through the 7/16” hole in the Post Plates (Ears) with washer and lockwasher under the 3/8” Nut (one bolt assembly on each side of Post)

Note 3/8” Bolts can be installed with nuts inside or outside of Post Plates

Page 21: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing HBA - Top Post 1

Are Lock Washer & Washer on??

Page 22: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing HBA Post-Top

Post 1 On the side opposite the Strut -

Insert a ¾” x 2 ½ ” Hex Head Bolt through the 13/16” hole in the Post Plates with washer and lockwasher under the ¾” Nut

Note ¾ ” Bolts can be installed with nuts inside or outside of Post Plates

DO NOT install the ¾” Bolt on the Strut Side until installing the Strut

Page 23: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing HBA Post - Top Post

1Are Lockwasher & Washers

on??

Page 24: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Final Assembly @ Base of Post 1

From ET-Plus Shop Drawing

Page 25: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Final Assembly @ Base of Post 1

Washer but does not have Lockwasher

Page 26: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Washer & LockWasher

Page 27: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusPost 2 – 8 SYT Post

If properly Graded, drive all the 6’ SYT Post to the optimum depth where centers of the 4 Yielding Holes through the Flanges are at the Ground Line

Note: Post 2 does NOT have an offset block

Note: Post 3-8 receive 8” offset blocks

Page 28: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Strut Post 1

Place Angle Strut on the Flange of the HBA Post 1 with ¾” Hex Head Bolt placed through the top and bottom Post Plates and connect with a ¾” Washer and Lockwasher under the ¾” Nut.

Note: Strut can be placed with one of the leg flat or leg edge on the ground

Note: Strut can be installed on traffic side or field side of the Post

Page 29: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Installing the Strut Post 1Again where is the Washer &

Lockwasher??

Page 30: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Strut Post 2

Place 2 – 7/16” Hex head Bolts with Washer into the two Slotted Holes of the Strut

Place a Lockwasher and Nut on the ends of each of the Inserted Bolts

Tighten Nuts to snug position

Page 31: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Strut Post 2

Washers are Important

Incorrect - Loose Fit Without Washer & Lockwasher

CorrectTight Fit With Washer

Page 32: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstall Offset Blocks & Rail

PanelsPost 3 - 8

25’ or 12’6” Rail Panels are acceptable Splice the rail Panels with 8 - 5/8” x 1

¼” HGR Splice Bolts and Nuts Do NOT connect Rail Panel @ Post 1 NO Offset Blocks @ Post 1 or 2 Post 3-8 Insert 5/8” x 10” HGR Bolt thru

Rail Panel, 8” Offset Block and SYT Post Connect with 5/8” Round Washer and

HGR Nut

Page 33: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Post 2 No Offset BlockPost 3-8 8” Offset Block

Composite or Wood

Page 34: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing Rail Panel to Post

2 NO Offset Block @ post 2 Insert 5/8” x 1 ¼” HGR Bolt

through the Rail Panel and SYT Post @ Post 2

Connect with 5/8” Round Washer and HGR Nut

Page 35: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-Plus Installing Rail Panel to Post

2

Page 36: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

Assembly Secure Cable Anchor Assembly to the

Rail by Inserting the Square Protruding Hooks/Lugs into Square Holes in Rail Panel toward Post 1. Secure by pulling the Bracket toward the Impact head insuring the Hooks/Lugs are well Seated into the Square Holes.

Page 37: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Protruding Hooks /Lugs on ET-Plus Cable bracket

Page 38: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

AssemblyCable Bracket

Page 39: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Protruding Hooks /Lugs on ET-Plus Cable bracket

Post 1

Page 40: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

Assembly Slide one end of Cable into the Cable

Anchor Bracket and the other end into Post 1

Place a 1” Washer and Hex Nut on the Bracket End near Post 2 and tighten until at least 2 Threads are showing

Place Bearing Plate on Impact Side of Post 1 where Cable extends through Post 1

Bearing Plate must have Long Dimension (5”) Up

Page 41: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Bearing Plate with Tabs on both sides to keep Bearing Plate Oriented with 5” UP

Page 42: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

Assembly Place 1” Washer and Hex Nut on the

end of the Cable extending through Post 1

Restrain the Cable with locking pliers at the end of the Cable being tightened

Tighten the Hex Nuts on the Cable Ends until TAUT – it is considered TAUT when Cable does not deflect more than 1” when pressure is applied

Page 43: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

TightenAnchorCable – Using Vice Grips

Page 44: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

Assembly Shank portion of Anchor Cable MUST BE

positioned so it bears on the bottom edge of the web of the HBA Post (Post 1)

Shank portion of Cable must also be centered Horizontally so the Bearing Plate bears uniformly on both Fingers of Post 1

Page 45: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Shank Portion of the Cable Bears on Bottom Edge of HBA

Post

Page 46: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Cable Anchor

Assembly

Page 47: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

47

What happened here???Impacting Vehicle NOT

Contained

Page 48: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

What happened here???WHAT is on the ground &

WHY?

Page 49: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Extruder Head

Rail feeds out the Extruder Head away from traffic – Arm points away from traffic

Push the Extruder Head as far as it will go on the Rail panel, making sure the Rail is in the Channel Chute

Place the Extruder head against the HBA Post (Post 1) parallel to the ground

Page 50: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusProperly Installed Extruder

HeadPushed all the way on

Page 51: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Improper Installation - Extruder Head not Pushed all the way on (very old ET) Would Spear Vehicle

Page 52: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Improper Installation - Extruder Head not Pushed all the way on

Page 53: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Extruder Head

Top and Bottom Flanges on the side of the Extruder Head each has 3 holes – use the hole that best aligns with the holes in top and bottom of the HBA Post & Extruder Head parallel to the rail panels

Place a 3/8” washer on a 3/8” x 1 ½” Hex Head Bolt – Insert Bolt through Flange of Extruder Head and Flange of HBA Post

Place 3/8” Fender Washer Under 3/8” Nut on the end of the inserted Bolt

Tighten until snug

Page 54: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PlusInstalling the Extruder Head

3 Holes in Extruder Head Flanges

Page 55: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Fender Washer

Page 56: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Properly Installed Extruder Head

Page 57: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Extruder Head should be Parallel to the Guardrail – Not dipping down like this

Page 58: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Extruder Head should be Parallel to the Guardrail –

Not dipping down like these

Page 59: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Energy Absorbing End TreatmentsSTRAIGHT FLARE / NOT CURVED

NO C

URVES

Page 60: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

From the ET-PlusInstallation Checklist

Extruder Head is pushed on as far as it will go on the rail panel ensuring the panels fully engage with the feeder chute

The Extruder Channel is approximately parallel to finished grade

Cable Anchor Bracket is locked into place, by pulling the bracket toward Post 1 making sure the Hooks/Lugs are well seated into the Square Holes

Page 61: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

From the ET-PlusInstallation Checklist

Shank portion of Cable Anchor positioned against bottom web of top portion HBA Post 1

Hex Nuts on ends of Anchor Cable are tightened taut (Cable deflects less than 1”)

Cable Bearing Plate Oriented such that 5” dimension is up

Page 62: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Properly Installed ET-Plus

Page 63: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

SKT-SP Road Systems Sequential Kinking Terminal –

Standard Post

Page 64: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

SKT-SP Road Systems http://roadsystems.com/pdf/fleat/SP-Installation-Manual.pdf

SKT-SP & FLEAT-SP

A very easy to follow“Assembly Instructions”With Drawings and Photos

Page 65: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Approved Shop Drawing SKT-SP 37’ 6” System

Page 66: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Except for 5 Differences the SKT-SP and the FLEAT-SP are

Identical Please note: To Avoid duplication

the Installation for the Type 1 SKT-SP is Covered with the Type 4A FLEAT-SP of this Training

Page 67: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

5 Differences Type 1 SKT-SP

Type 4A FLEAT-SP 1. Flare

SKT-SP: 12” FLEAT-SP: 48” 2. Extrudes Guardrail

SKT-SP Away from Traffic FLEAT-SP Towards Traffic

3. Size of Impact Head & Feeder Chute SKT-SP Longer FLEAT-SP Shorter

Page 68: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

5 Differences Type 1 SKT-27

Type 4A FLEAT-27 4. Cable Fed Inside/Outside Feeder

Chute SKT-SP Cable Fed thru Feeder Chute FLEAT-SP Cable Fed Outside Feeder

Chute 5. Bolt or No Bolt Connection to

Post 3 SKT-SP Guardrail IS Bolted to Post 3 FLEAT-SP Guardrail is NOT Bolted to

Post 3

Page 69: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Flare SKT-SP: 12” FLEAT-SP:

48”

FLEAT-SP48” FlareSKT-SP 12” Flare

Next to Roadway/Shoulder

Page 70: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Extrudes GuardrailSKT-SP Away from TrafficFLEAT-SP Towards Traffic

SKT-SP Away from Traffic FLEAT-SP Towards Traffic

Page 71: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Size of Impact Head and Feeder Chute

SKT-SP LongerFLEAT-SP Shorter

SKT-SP LongerImpact HeadFeeder Chute

FLEAT-SP ShorterImpact HeadFeeder Chute

Feeder Chute Ends

Page 72: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

SRT-SP Cable feed inside/thru the Feeder Chute FLEAT-SP cable does NOT

Page 73: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

The KYTC Pay Limits for the Type 1 End Treatment SKT-SP is 50’ even though the SKT-SP Shop Drawing says 12’ 6” for the

37’ 6” System

KYTC Type 1 Guardrail End treatment Pay Limits 50 FeetStandard Drawing RBR-020 Guardrail End Treatment Type 1

Road Systems SKT-SPPay Limits 12’ 6”

Page 74: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

Manufactures Installation Info

SKT-SP Road Systems http://roadsystems.com/fleat.html http://roadsystems.com/pdf/fleat/SP-Installation-Manual.pdf 1-432-263-2435

ET-Plus Trinity Highway Products http://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdf 1-800-282-7668 Elizabethtown KY

Both have a short Section on Repairs

Page 75: Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems

ET-PLUS and SKT-SP Installation manuals

ET-PLUS SKT-SP & FLEAT-SP