Project - Quarterly Progress Report Promoter’s Name : Hamlet Apartment Private Limited Project Name : Mantri Serene Phase II Project Registration No : TN/01/BUILDING/0167/2017 Quarter Ending : 31-03-2019 A. Sales Sl. No. Description Nos Total Area (Sq ft) 1. Plots/Flats Booked size wise (As given in Carpet Area Statement while registering) 27 35,155 2. Parking Lots 153 20,578.5 3. UDS Registered in Sq.mtr Nil Nil B. Construction Sl. No. Description Block/Tower No. Status 1. Stage of construction of each Block/Tower, Floor wise Tower C Stilt floor roof slab in progress Tower D 1st floor roof slab in progress Tower E 2nd floor roof slab in progress 2. Status of common Amenities for each Block/Tower, Item wise Tower C (STP WTP Lift lobby) - Structure works in progress C. Details of Clearances 1. Completion Certificate No. (Not applied yet) Compliance Report, if any (Not Applicable) D. Latest Photo with Date (Refer attachment) Note: Report the above mentioned under “Registered Projects” in www.tnrera.in

Upload: others

Post on 02-Jan-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Project - Quarterly Progress Report

Promoter’s Name : Hamlet Apartment Private Limited Project Name : Mantri Serene Phase II Project Registration No : TN/01/BUILDING/0167/2017 Quarter Ending : 31-03-2019

A. Sales

Sl. No.

Description Nos Total Area (Sq ft)

1. Plots/Flats Booked size wise (As given in Carpet Area Statement while registering)

27 35,155

2. Parking Lots 153 20,578.5 3. UDS Registered in Sq.mtr Nil Nil

B. Construction

Sl. No.

Description Block/Tower No.

Status

1. Stage of construction of each Block/Tower, Floor wise

Tower C Stilt floor roof

slab in progress Tower D 1st floor roof

slab in progress Tower E 2nd floor roof

slab in progress 2. Status of common Amenities for each

Block/Tower, Item wise Tower C (STP WTP

Lift lobby) - Structure works in progress

C. Details of Clearances

1. Completion Certificate No. (Not applied yet) 2. Compliance Report, if any (Not Applicable)

D. Latest Photo with Date (Refer attachment)

Note: Report the above mentioned under “Registered Projects” in www.tnrera.in

Page 2: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2”

PROGRESS REPORT PHOTOS MARCH’19

Page 3: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

SERENE-2 OVER ALL VIEW SLAB

Page 4: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing C 1st Floor Slab

Page 5: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing D 1st Floor Slab Completed

Page 6: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E 2nd Floor Slab Completed

Page 7: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E 3rd Floor Slab form work & 1st floor block work in progress in progress

Page 8: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E North side back filling in progress

Page 9: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E 3rd Floor Slab form work in progress

Page 10: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E Stilt floor level PCC casting in progress

Page 11: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E Stilt floor back filling in progress

Page 12: SERENE-2 OVER ALL VIEW SLAB · 2020. 6. 12. · RESIDENTIAL PROJECT “ MANTRI SERENE – PARCEL 2” PROGRESS REPORT PHOTOS MARCH’19 . SERENE-2 OVER ALL VIEW SLAB . Wing C 1st

Wing E Stilt floor Bull marked for PCC in progress